An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Waters Montgomery, AL Case Study

  2. Project Summary • Location – Montgomery, AL • Acreage – 1,250 acres • Units – 2,500 residential units • Product Type - Traditional Neighborhood Community surrounding a 200 acre community lake. • Master Plan – Eight (8) distinct Hamlets (i.e. stand-alone communities), including approximately 350 residential units and commercial uses each. • Topography – Gently rolling • Soil – Prairie gumbo clay

  3. Project Summary • First Hamlet – Lucas Point: • 350 units, including approximately 60 live/work units and 45 commercial units. • Home Prices - $150,000 to over $1 million • Projected Sales Absorption – 4 years

  4. Considerations • Public sewer is not available • Cost prohibitive to extend public sewer • Minimize upfront capital investment, and spread cost over life of project. • Maximize economic return by providing project design flexibility; offering multiple products and price points. • Highest and best use achieved through clustered development with substantial open space (conservation development) • Professional operation, maintenance and customer service

  5. Solution • Collection System – site topography allows for individual STEG versus STEP systems • Treatment - Recirculating Sand/Gravel Filter; built in phases • Disposal • Drip Irrigation – built in phases • Storage Pond – reduce drip irrigation installation costs and land application area.

  6. Ownership & Management • Once system is constructed and approved, ownership of facility and fee simple ownership in treatment site is transferred to Utility as “Contribution In-Aid” (non-taxable transaction). Developer maintains fee simple ownership of disposal area, and provides Utility with non-exclusive easement. • Utility will own, operate and maintain system in perpetuity. (includes individual and central system components ) • Utility is certified as wastewater system operator by the State of Alabama Department of Public Health • Utility provides performance bond to the State Health Department and evidence of financial viability to the Public Service Commission

  7. Developer Benefits • Turn-key solution • Minimize upfront capital cost • Operating Utility company assumes liability • Operating Utility is regulated and financially viable • Ability to re-use treated effluent for community irrigation • Development flexibility through multiple price points and product offerings • Value created by optimization of open space • Proven technology