DFSProjekt ADQ – Aeronautical Data Quality ADQ Implementation Workshop Brussels – 28./29.May 2013 Anette Grossmann-Jorschik, Projectmanager DFS
DFS Projekt ADQ – agenda • Basic Parameters • Analysis ofcurrentstage • DFS´sstrategy • Milestones
Basic ParametersEU Regulation and possible Means of Compliance (MoC) DO DQR AIX DAL eAIP DFS, Projekt ADQ
Basic ParametersKey findings of the planning phase ADQ requires electronic andstructureddata in definedqualityrightfromthedatageneratinginstance. The data must bemadeavailable in good time andwithoutanyloss in qualityto all involvedinstances. Every singlestep in a processand all involvedinstancesandpersons must bedocumentedandverified. Cannotbeachievedwithoutmodifyingthe IT-Infrastructure of DFS (GDV, CNS-AA, HDB)! DFS, Projekt ADQ
Analysis current stageADQ – What to do ...? DFS, Projekt ADQ
Analysis of current stage IT-landscape Geo-Informations Systeme EAD System Airspace- and Performance planning Aeronautische Datenbank Systems AIP-ProdukcionandPublication Obstacle Data Base Externaldatasupplier (authorities, Airports) CNS-dataarchiv Datenkonsumierende Systeme DFS Action to be taken Nicht für ADQ-1 relevant Datenkonsumierende Systeme extern System Frequency-management
DFS‘s ADQ Strategy Design principles of the planning phase • Identify and document media breaks and manual data entry in the IT application environment of DFS • Adjust the affected processes through standards of Aeronautical Data Processing • Identify and resolve redundancies in data management and consolidation of historically grown databases • Wherever possible standards, open interfaces and COTS products should be required
DFS‘s ADQ Strategy Key measures of the planning phase • Analysis and conceptual implementation of Regulation 73/2010, executive rulesand Guidelines ADQ (> 700 pages) • Analysis and documentation of the application environment for handling of “Aeronautical Data„ • Basic concept of an interface for data exchange with Airports • Design of a consolidated IT architecture for aeronautical data • Design of a master process (process patterns) for handling of aeronautical data (creation, format changes, forwarding, verification, validation and authentication)
DFS ADQ StrategyADQ – DFS‘s conceptual Approach for theit IT-landscape Data managementprocess systems EAD Externaldatasupplier (authorities, airports, ANSPs via EAD) Aeronautical Database Systems AIP-productionandpublishing Data supplyinterface (AIXM) Data provisioninterface Data consumingsystems DFS Data supplyingsystems DFS Is not relevant to ADQ-1 Externaldataconsumingsystems Verification systems DFS, Projekt ADQ
DFS´s ADQ StrategyTarget-IT landscape with a DFS- wide AIM Process (according article 6 VO EU 73/2010) ADQ compliant DFS Deutsche Flugsicherung GmbH, GB AIM
DFS‘s ADQ StrategyIntegration of external Partners: Example: AirportANSP AIM-Process (DAL-Process) DataRequest Data Set -Format AIXM 5.x Airport ANSP Direct electronic Connection AIP Push / Pull – Exchange Data Provider / Consumer Agreement Service Level Agreement Process Integration Authority? Data Delivery Authority DFS, Projekt ADQ
DFS‘s ADQ StrategyADQ – DFS‘s Internal Concept for their new IT-Architecture • Meetsrequirementsof VO (EU) 73/2010 • Data setformat • Data exchangeformat • Data protection Effectivlysupportsthenewlydesigned, cross-cuttingAIM-Data Management-Process Dokumentation der relevanten Ist-Anwendungslandschaft (Systeme, Schnittstellen, Daten, Integration) Konzeption einer ADQ-konformen und optimiertenSoll-Anwendungslandschaft Technische Anforderungen aus VO 73/2010 (und MOC) Anforderungen aus dem neu entworfenen AIM-DM-Prozess • Is sustainable so astosupportthe ICAO-strategyfrom AIS to AIM • Supports theprinciple: Data orientationinsteadofproductorientation • Is open forstrategicdevelopments (e.g. SOA, SWIM) Realisesconsolidationandoptimization potential in today´sheterogenousapplicationenvironment Needs foraction in theapplicationenvironment Most economicalsolutionconcerningthecostdrivers • Satisfiesthe EAM-principlesof DFS • Satisfiesthestandardsof DFS Technische und architekturbezogene Rahmenbedingungen Wirtschaftliche und organisatorische Rahmenbedingungen DFS, Projekt ADQ
MilestonesProjectplan timetable realisation phase July 1st 2014Nesessary IT-technical aspectsare implementedforverification ofthecompliance July 1st 2013 The Regulation enters intoforcefornew aeronauicaldateand information June 30th 2017Existingdata must be ADQ-compliant 2014 2015 2012 2013 M831.12.2015 Completion of project ADQ M111.12.2012PA 2 approved M330.06.2013DFS- processes are documented ADQ- compliantly M431.03.2014 Consolidated and ADQ- Extended AERO DB is functional for test operations M530.06.2014 DFS- IT-systems and processes are ADQ- compliant M631.03.2015 Final test for replacement of decentralised IT-systems M730.06.2015 Replacement of legacy systems, end of project ADQ M231.03.2013 IDS-Demonstrator is functional DFS, Projekt ADQ