1 / 49

HF UPGRADE PROJECT

HF UPGRADE PROJECT. Y. Onel For HF Upgrade Project Collaboration Nov 7, 2011. HF PROJECT REVIEW I. Upgrade HF Internal Pre-PRR, October 5, 2011 HF Project News Yasar Onel (Physics and Astronomy Department)

tyme
Download Presentation

HF UPGRADE PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HF UPGRADE PROJECT Y. Onel For HF Upgrade Project Collaboration Nov 7, 2011

  2. HF PROJECT REVIEW I Upgrade HF Internal Pre-PRR, October 5, 2011 • HF Project News Yasar Onel (Physics and Astronomy Department) • July 2011 TB Results Dr. Burak Bilki (University of Iowa (US)), Taylan Yetkin (University of Iowa (US)) • Self-Trigger Results from July TB2011 Elif Asli Albayrak (University of Iowa (US) • New Base Board Sergey Los (Fermilab), Sergey Los (Fermi National Accelerator Lab. (US)) • New ROBOX Ianos Schmidt (University of Iowa (US) • Bulgarian HV,Commercial HV Sergey Los (Fermilab), Ianos Schmidt (University of Iowa (US)), Slawomir Tkaczyk (Fermi National Accelerator Lab. (US)) • New Cables Theresa Shaw (Fermi National Accelerator Lab. (Fermilab), Aliko Mestvirishvili (University of Iowa (US)) • Sleeve R&D David Winn (Fairfield University (US)), Lucien Cremaldi (University of Mississippi (US)), Ianos Schmidt (University of Iowa (US)) • Testing/Characterization(Iowa/UMD) Ugur Akgun (University of Iowa)

  3. HF PROJECT REVIEWS II • We will start with our additional internal reviews on November 14 and November 16 at 11 am - 1 pm CDT. • November 14--- Test beam October results and HV system. • Talks by Y.Onel , Burak-Taylan, Sergey, Ianos and Swalek (CAEN info) • November 16-- Cables (EVO). • Talks by Y.Onel , Alexi, Terry, Sergey, Ianos • December 8---Dry Run –Review (all topics-subjects/talks based on Oct 5 Internal review-- will prepare a schedule of talks) • January 12, 2012 --CMWS PRR at CERN

  4. Recent highlights and news Characterization and testing of the first 6 sets- 610 PMT’s are done. Working on the 7th batch. 8th batch just arrived bringing our total to 890 PMT’s. • We started with the batch measurements- focusing on specialty tests: • surface nonuniformity tests (already presented GJ) • Afterpulse tests (already presented GF) • Single photoelectron tests (already presented by Jared) • We started with the double pulse linearity measurements using the first board from Sergey. We will repeat these measurements with the latest version. The UMD test station is doing well and good results on the cross check.

  5. PMT Tests at Iowa and UMD • Total 890 PMTs are delivered. Standard tests (timing, gain, dark current, linearity) are done for first six batches. We are running special tests (surface scan, single photoelectron, afterpulse) . • We prepared detailed manuals for PMT tests: http://www.physics.uiowa.edu/~uakgun/temp/PMT_TEST_MANUALS/ • We have recently started life-time measurements with two independent set-ups. ( Iowa Photodetector lab and U.Akgun Lab)

  6. July 100 August 110 September 130 October 150 November 150 December 200 January2012 200 February 200 March 160 Total 1800 New PMT Delivery schedule

  7. Reviews • PMT’s, Sockets were tested in JulyTB and Oct TB. • July TB Data analysis + Double Pulse Linearity at Iowa • RBX- Mechanics and Sleeves were tested in JulyTB • New Cables test with QIE 8 on bench at FERMI and CERN-904 internal sign off before Oct TB. • Internal review 1 ( Oct 5th, Very successful) • New (Cables,Base Boards, RBX)were tested in Oct TB • Oct TB Analysis and draft CMS and Journal publications draft • Internal review 2 and 3 ( Nov 14 and 16) • Cables, Power Supplies Prototype Bulgarian or commercial and October TB. • Dry Run-Review December 8th. • CMS PRR for RBX and Power Supplies  Full system

  8. Set up The setup and the test procedure is very similar to CMS IN 2002/030, where the Hamamatsu R7525 double pulse tests were described. Blue LED Light guide PMT Filter wheel

  9. Serial # JA0475 9300 photoelectron Pulse Ratio Area of the first pulse (nVs)

  10. New HF Upgrade Power Supply • We have an arrangement with our Bulgarian group to prototype new power supply system for the HF. We hope receive this prototype by the end of March 2012. • We are also looking into the commercial solutions (Swalek will look into this)

  11. New Milestones • HF PMT 1-Jun-11 Sleeve Design Approval - Internal HCAL Review • 5-Oct-11 New Date • HF PMT 15-Jun-11 HCAL Sign Off of Pre-Production ROBOX • 5- Oct-11 New Date • HF PMT 15-Sep-11 New Cable Scheme Design Approval • HCAL Review 16-Nov-11 New Date • HF PMT 31-Oct-11 PMT Testing 50% Comp • 1-Jan-12 New Date • HF PMT 8-Dec-11 Production Readiness Review (Dry Run-Review) • CMS PRR 12-Jan-12 New Date (this is full system, including HV Power Supplies)

  12. Test Beam 2011 • We had a very successful run in July 2011. • Our “Punch Through Studies” at the Test Beam was also successful. • We had two presentations from our group to the HCAL Test Beam meeting on September 6. • 1-HF TB2011 Results by Burak Bilki-Taylan Yetkin ( Presentation by Taylan) • 2-HCAL July 2011 Test BeamReports Self Trigger Runs by E. A.Albayrak, G.Aydin, Y.Gunaydin (Presentation by Asli)

  13. Test Beam July 2011 • We have tested the new PMTs inside a RBX with different readout options. • During the test electron, muon, and pion beams were used. • Since the characteristics of the new PMT were studied in previous test beams, we focused on the RBX itself. • The primary goal of the test was to study RBX as a whole unit with Čerenkov light or punch through particles. • We observed comparable behavior from each PMT (i.e. similar p.e. output). • Preliminary look suggests no electronic malfunctioning with 2-anode and 4-anode readouts. • Previous studies for filtering and recovery (TB2010) were briefly repeated with the new data for verification.

  14. Run Plan October Test Beam • Proposal for the run plan: • 1. Electron -> absorber -> bundle -> New RBX --- 80 GeV and 6-7 X0 are OK as before. We need to test the characteristics of both fiber ends first, then run over all PMTs in pairs. • 2. Muon -> New RBX without light guides --- need statistics for better algorithm tests, scan through the board. • 3. A few electron/pion energies -> EM calorimeter with 4A PMT --- will go for a shower leakage probability estimator and an algorithm performance monitor. we also need an electron energy scan. • 4. Pion -> absorber -> New RBX without light guides --- I do not think that we terribly need this, what we already have is really good. We can do this with a better table alignment.

  15. Bulgarian HV system • 1. Production of proto: they would need of about 2000 USD and accept the schedule -March 2012. • 2. About full production: For estimate its cost, we have to specify the number of crates and the number of modules,. At CERN we spoke of 12 modules and 6 crates, Also, after the prototype is done, they could clarify the possibility of using the old crates and if yes, for how many modules inside the crate. • Approximative prices of the different parts of the system are - 9 channel module - about 1000 USD - 1 crate with power supply - about 850 USD - 1 crate controller - about 150 USD. • 3. About the documentation and support : We will discuss further the volume and the contents of the documentation, but it will include the Instruction for exploitation and mechanical and electrical schemes of all PC boards in the crate as well as scheme of the connections between them. About the support they foresee a free of charge support during the first year of the exploitation. After that their specialist shall come to CERN when it is necessary, but the travel and leaving expenses have to be paid by the US Team at CERN.

  16. HV Specs • HF Multianode PMT Power Supply Upgrade. Supply currents for the existing prototype Base Board were revisited, and decreased as follows: • a. 1000V - 5mA • b. 200V - 5mA • c. 100V - 10mA • There are 4 sectors at each end with 9 ROBOXes in each. ROBOXes have 3 boards in each, and for each sector there are 3 sets of 1000/200/100V power - for different radii of the detector. • Thus, for each end there should be a crate with 4 modules, each having three sets of 1000/200/100V power. • There is a possibility to have instead 2 crates with 2 modules in each, if that allows to use existing crate power supplie s without their power increase.

  17. HF2012 Organization Chart

  18. IOWA Teams 1-4, HF CERN Team, HF Turkish Team Iowa Team #1 PMT characterization Akgun- Ph.D, Lead Engineers Neuhaus, Miller, Tyler Grad. Students Griffiths, Harrington, Tiras Undergrads Funk, Jia, Reed, Squires Iowa Team #2 PMT performance studies in pp collisions Bilki, Clarida and Yetkin Iowa Team #3 Study light guide and sleeve performance Clarida, Ozok and Sen Iowa Team #4 Radiation & Scintillation test sleeves U.Akgun, Neuhaus, Funk, Jia with Mississippi and Fairfield HF CERN Team: Penzo (Trieste), Merlo, Sen , Ozok, Taylan, Ianos, Alexi (Iowa), M.Kaya, O.Kaya, B.Isildak (BU, Istanbul) HF Turkish Team –Kadir (METU, Ankara), B.Isildak ( BU, Istanbul) plus 6-8 grad.students from CU, Adana and in addition summer M.Kaya. O.Kaya ( BU, Istanbul), S.Cercin, Numan ( CU, Adana).

  19. HF Turkish Team • Pt 5 Test Operations ( From Turkey) • Dr.Mithat Kaya (Faculty, Former Iowa) BU, Istanbul • Dr.Murat Guler (Faculty) METU, Ankara • Dr.Omer Mermerkaya (junior faculty) METU, Ankara • Dr.Numan Bakirci (junior faculty) CU, Adana • Dr.Salim Cerci (junior faculty) CU, Adana • Bora Isildak BU, Istanbul • PMT test station at CU, Adana • Dr.Isa Dumanoglu (Faculty) • Dr.Kenan Sogut (Junior Faculty)

  20. New Turkish members • Kerem Cankocak (Faculty, ITU, Istanbul-formerly Iowa) Gural Aydin and Yusuf Gunaydin (Both Junior Faculty, ITU formerly Iowa). • Sertac Ozturk (Junior Faculty CU-formerly Iowa and FERMI LPC and Huseyin Topakli (Junior Faculty, CU formerly FERMI LPC). • H. Bahtiyar, E.Barlas, E.Emirhan, O.Oztirpan, B.Untuc, M.Yucel (Graduate students-ITU). • S.Durgut and Y.Oz (Bogazici University, Istanbul- Grad students of E.Gulmez).

  21. New Iowa Students • Iowa Graduate Students • K.Dilsiz, T.Harrington, M. Haytmuradov, H.Ogul • Iowa Undergraduate Students • J.Buffon, J.Corso, G.Funk ,G.Jia, J.Kingyon, C.Reed, D.Squires, D.Southwick

  22. New Cable Tests

  23. Alexi, Ianos, Richard and Terry • Phase scan was done, in total 12 points from 0ns delay up to 22ns with 2 ns step and new cable behaves as expected, no reflections, no signal distortion seen with PMT and QIE readout. • Six time slices were read out, signal in TS 2Before test beam starts, and before ROBOX with new PMT’s modification, our group will repeat these tests with old cable, modify ROBOX to connect new cable and do once more these tests to compare old and new cables.

  24. ROBOX Test Stand • We should start to equip the ROBOX test stand at P5 during summer 2012.By that time we have define what kind of data we have to take : LASER,LED – at different intensities, different HV etc. • The equipment needed – MiniDAQ, Front End, HV(modified Bulgarian PSU), LV, cables (all sort – HV, LV, ROBOX to QIE), LASER system, Digitial Scopes.

  25. Alexi Proposal for Pt5 • Two fully equipped HF QIE crate. We can connect 6 ROBOX at same time. That makes: Two crates, 24 QIE cards, 2 CCM, 1 CM. • Fully equipped MiniDAQ – HTR’s, DCC, all supporting electronics like trigger boards, TTC, fibers etc. • One fully equipped QIE crate occupies 1.5 HTR With two QIE crate (24 QIE card) we will need 3 HTR + one DCC etc.

  26. Milestones • Production Readiness Review 11/15/11 • Equip ROBOX test stands at SX5 11/23/12* • Start of CMS 2012 Shutdown 12/5/12 • HF Plus ROBOX Reassembly and Testing 5/11/13 • Remount HF Plus ROBOXs 5/31/13 • HF Minus ROBOX Reassembly and Test 7/11/13 • Remount HF Minus ROBOXs 7/25/13 • Install new HF PMT ROBOX Cables on HF Plus 9/4/13 • Install new HF PMT ROBOX Cables on HF Minus 9/18/13 • Burn in HF Minus Side ROBOXs in Garages 9/21/13 • Reinstall HF Minus into CMS 10/31/13 • Burn in HF Plus Side ROBOXs in Garages 1/14/14 • Reinstall HF Plus into CMS 1/30/14 • HF Minus Rework and Installation 3/13/14 • Integrate and Commission HF Minus Side ROBOXs in UXC 3/13/14 • Integrate and Commission HF Plus Side ROBOXs in UXC 3/13/14 • HF Upgrade Installation and Commissioning completed 3/13/14 • CMS Ready for Beam 3/13/14 • *we might move this to an earlier date

  27. Schedule with dates • Production Readiness Review 1 day Tue 11/15/11 Tue 11/15/11 • HF Upgrade Installation and Commissioning 384 days Thu 9/1/12 Wed 3/13/14 • Equip ROBOX test stands at SX5 60 days Thu 9/1/12 Wed 11/23/12 • Gather Miscellaneous Hardware/Equipment for in-situ HF Testing in Garages 60 days Thu 9/1/12 Wed 11/23/12 • Install Miscellaneous Hardware/Equipment for in-situ HF Testing in Garages 10 days Tue 12/6/12 Mon 12/19/12 • Start of CMS 2012 Shutdown 1 day Mon 12/5/12 Mon 12/5/12 • HF Plus Rework and Installation 312 days Mon 12/12/12 Wed 3/13/14 • HF Plus Moved into Garages 8 days Mon 12/12/12 Wed 12/21/12 • Set Up HF Plus Scaffolding 265 days Thu 1/5/13 Fri 1/18/14 • Set Up HF Plus Scaffolding 2 days Thu 1/5/13 Fri 1/6/13 • HF Plus Scaffolding Rental - M&S 265 days Thu 1/5/13 Fri 1/18/14 • HF Plus ROBOX Removal Preparation in Garage 11 days Mon 1/9/13 Mon 1/23/13 • HF Plus ROBOXs Dismounted and Moved to SX5 11 days Tue 1/24/13 Tue 2/7/13 • HF Plus - Mount at Crates New DSub to New Connector Patch Panels 30 days Wed 2/8/14 Tue 3/20/14 • Install new HF PMT ROBOX Cables on HF Plus 60 days Wed 6/13/13 Tue 9/4/13 • HF Plus ROBOX Disassembly 22 days Tue 1/31/13 Wed 2/29/13 • HF Plus ROBOX Reassembly and Testing 72 days Thu 2/2/13 Fri 5/11/13 • Remount HF Plus ROBOXs 72 days Wed 2/22/13 Thu 5/31/13 • Burn in HF Plus Side ROBOXs in Garages 210 days Mon 3/12/13 Mon 1/14/14 • Move HF Plus Out of Garage 2 days Thu 1/17/14 Fri 1/18/14 • Reinstall HF Plus into CMS 6 days Wed 1/23/14 Wed 1/30/14 • Integrate and Commission HF Plus Side ROBOXs in UXC 30 days Thu 1/31/14 Wed 3/13/14 • HF Minus Rework and Installation 305 days Wed 12/21/12 Wed 3/13/14 • HF Minus Moved into Garages 8 days Wed 12/21/12 Fri 1/13/13 • Set Up HF Minus Scaffolding 200 days Mon 1/16/13 Wed 10/17/13 • Set Up HF Minus Scaffolding - Labor 2 days Mon 1/16/13 Tue 1/17/13 • HF Minus Scaffolding Rental - M&S 200 days Mon 1/16/13 Wed 10/17/13 • HF Minus ROBOX Removal Preparation in Garage 11 days Wed 1/18/13 Wed 2/1/13 • HF Minus ROBOXs Dismounted and Moved to SX5 11 days Thu 2/2/13 Thu 2/16/13 • HF Minus - Mount at Crates New DSub to New Connector Patch Panels 30 days Fri 2/17/13 Thu 3/29/13 • Install new HF PMT ROBOX Cables on HF Minus 60 days Wed 6/27/13 Tue 9/18/13 • HF Minus ROBOX Disassembly 22 days Wed 2/29/13 Thu 3/29/13 • HF Minus ROBOX Reassembly and Testing 72 days Tue 4/3/13 Wed 7/11/13 • Remount HF Minus ROBOXs 72 days Tue 4/17/13 Wed 7/25/13 • Burn in HF Minus Side ROBOXs in Garages 40 days Mon 7/30/13 Fri 9/21/13 • Move HF Minus Out of Garage 2 days Mon 10/22/13 Tue 10/23/13 • Reinstall HF Minus into CMS 6 days Wed 10/24/13 Wed 10/31/13 • Integrate and Commission HF Minus Side ROBOXs in UXC 84 days Thu 11/1/13 Wed 3/13/14 • HF Installation and Commissioning Completed - CMS Ready for Beam 1 days Wed 3/13/14 Wed 3/13/14 • CMS Ready for Beam 1 day Wed 3/13/14 Wed 3/13/14

  28. Back-up

  29. One PMT on every Batch: • Cathode surface non-uniformity • Double Pulse Linearity • Single photoelectron resolution • Anode Cross-talks • Afterpulse measurements • One time tests: • PMT Lifetime HF PMT Test Data • On Every PMT • Rise Time • Negative Pulse Width • Transit Time • Transit Time spread • Single Pulse Linearity • Anode Dark Current • Cathode Dark Current • Gain vs HV • Cathode Luminous Sensitivity • Anode Luminous Sensitivity • Cathode Blue Sensitivity

  30. Components Baseboard ROBOX & Light Guides Light Sleeve Cables & ROBOX & Baseboard PMTs & Baseboard Winchester Cable

  31. Components

  32. Sleeve

  33. PMT Power Supply Light Filters Light splitter pin-diode Pmt Base Lazer Equipment List

  34. Duel Pulse Generator PMT signal by Blue LED TTL signal by pulser Light guide Blue LED PMT Filter wheel

  35. Second prototype Base Board is shown, so called “TB2011 Base Board” New Base • 72 ROBOX enclosures • 216 Base boards with 1728 PMTs • Each PMT with an option for 1/2/4-anode readout • 8 power supplies (1 per quadrant) with 3 sets of independent voltages (Vpc, Vd9, Vd10)

  36. Cables (904 & TB Oct 2011)

  37. Winchester Cables • 250mm MMCX pigtails, 305mm adapter cable MMCX Pigtail (Inside ROBOX) Adapter Cable 5 New cables are 35 – 40 cm longer than old ones

  38. ROBOX

  39. Shields • PPP readout box had demonstrated that the design of the mechanics is sound and well understood. • Requirements for production and modifications are understood. • Production schedule is coming together, but requires another iteration.

  40. PMT DELIVERIES • Total number of pmt: 890 • Number tested for each test: • Dark Current: 740 (batch 1-6) • Gain: 700 • Linearity: 610 • Timing: 250 • After Pulse: 25 (batch 1-5) • Surface Uniformity: 25 • Double Pulse: under development

  41. Absorber PMT Box Light Guides Muon Beam Electron/Pion Beam PMT Box Fiber Bundle TB2011 Setup HF TB2011 Results B. Bilki & T. Yetkin

  42. PMT Locations inside ROBOX NEW ROBOX OLD ROBOX CLI 1-Anode: 5B, 6B, 8B, 6C, 5C 2-Anode: 3B, 4B, 3C, 4C 4-Anode: 1B, 2B HF TB2011 Results B. Bilki & T. Yetkin

  43. WC Selection for Bundle Data 80 GeV/c Electron Beam WC-E hits are weighted by the signal. A position based selection is applied. The x-y distribution shows that the fibers are not mixed well.(consequences on p.e. comparison on data) HF TB2011 Results B. Bilki & T. Yetkin

  44. 8B 6B 4B 2B 5B 3B 1B y (mm) 6C 4C 5C 3C x (mm) 150 GeV/c Muon Beam Muon beam was positioned at different locations to hit the new PMTs directly. The data are used to verify the spectrum and fraction of large signals from window hits & study flagging-recovery algorithm. Spectrum from all PMTs Fraction of events above 30 p.e.= 4x10-4 HF TB2011 Results B. Bilki & T. Yetkin

  45. Verification of Filter&Recovery HF TB2011 Results B. Bilki & T. Yetkin

  46. Different Recovery Algorithms HF TB2011 Results B. Bilki & T. Yetkin

  47. HF Collision Data-2 /Jet/Run2011A-v1/RAW All Collision Runs in 2011 (RunNo>159268) HF(29,67,1) Anode_1_4 HF(29,67,2) Anode_2_3 (S1-S2)/(S1+S2) < 0.4 (S1-S2)/(S1+S2) < 0.4 No Cleanup (S1-S2)/(S1+S2) < 0.4 TB algorithms are directly applicable to collision data. Will work better with improvement.