1 / 25

HF UPGRADE PROJECT

HF UPGRADE PROJECT. Y. Onel PM Report April 30, 2012. Recent Highlights and News-I. We have now our detailed HF Internal schedule for 2012. Thru this internal schedule we have moved some of our delivery dates forward. Our DOE Project dates will remain the same

walt
Download Presentation

HF UPGRADE PROJECT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HF UPGRADE PROJECT Y. Onel PM Report April 30, 2012

  2. Recent Highlights and News-I • We have now our detailed HF Internal schedule for 2012. Thru this internal schedule we have moved some of our delivery dates forward. Our DOE Project dates will remain the same • Our Schedule starts with our PPP Final for the baseboards and follows a delivery sequence of “Test Stand” equipment, PMT’s and ROBOXes. • Alexi is preparing the 904 and SX5 (alcove) Test System write-up detailing our equipment, procedures and measurements. • Worked on the shipping plan of the PMT’s to CERN. The current plan is to ship the PMT’s from Iowa to CERN. The shipping will include full insurance directly from Iowa. In fact our latest estimates shows that this is the cheapest way to ship the PMT’s since the shipping from FERMI does not include any insurance (FERMI is self-insured). Requested a change-order for this cost. • Achiellehas allocated a new space to store delivered equipment safely at CERN. Contacts are Christian Joram and Thierry Gys, Didier Piedigrossi. • The New HF Physics and Detector group is now organized (Jane Nachtman). This group have members from Baylor, Brazil Universities, Iowa, Mississippi and Turkey. They had their first meeting on April 6th. • Developing our “Project Org Chart” adding Brazilian Universities and ITU, Istanbul.

  3. Recent Highlights and News-II • The PMT deliveries are now completed. Testing is going well. We had a meeting with Hamamatsu regarding our reject tubes. We have shipped back about 10 PMT’s ( low gain, high dark current and black cover problems) to be tested by them. The Base Board production is also going well. • Working on the New HV testing system and forming a committee to evaluate the RFP responses. Bulgarian new module testing started. Waiting report from German and Alexi. • The HV RFP and decision committee is now formed. Members are: Germain, Alexi, Ianos, S.Los, M.Miller, D.Winn from HF and Magnus and S. Lusin from CMS Coordination. • We have to decide on the shield length- 54 mm looks good. • Gain Sorting Proposal by Ugur -A uniform gain distribution for one HF is outlined from the foist 900 PMT sample. Other than the fringes at the edge of the sample, we can get gain uniformity within2% -EM and HAD, and 4 Quadrant separation would work if we can deliver different HV for each group (total 24 groups). -As the operation gain is decided, we can develop sorting and HV distributions for each group. There is a push for a new cable purchases– Thanks Chris Tully, Jeremy Mans and Pawel De Barbaro for this. There is also a strong support from Austin and Magnus on this.

  4. HF2012 Organization Chart

  5. Milestones 2012 HF UPGRADE PROJECT MILESTONS • PMT Testing 50% Complete 1/1/2012 • Production Readiness Review 1/12/2012 • New YETS 2012 ROBOX manufactured, tested and installed in CMS 2/17/2012 • New cable purchase decision 2 or 4 channel 7/1/2012 • Start of CMS 2012 Shutdown 12/5/12 • Equip ROBOX test stands at SX5 11/23/12 • Gather Miscellaneous Hardware/Equipment for in-situ HF Testing in Garages 11/23/12 • Install Miscellaneous Hardware/Equipment for in-situ HF Testing in Garages 12/19/12 • HF Plus Moved into Garages 12/21/12 HCAL INTERNAL MILESTONES • New HV system purchase decision 8/15/2012 • HF PMT characterization and testing 100% done 10/1/2012 • HF PMT's are shipped to CERN 10/15/2012 • HF PMT Boards QC testing 100% at Iowa 11/1/2012 • Start of the HF ROBOXes shipping to CERN 11/1/2012 • HF PMT's are shipped to CERN 10/15/2012

  6. New Advanced Schedule

  7. PCB production SL SL, IS, AM SL SL MM, JC, DS, ZJ, GF, JK ZJ SL SL 3/1/12 --- 4/15/12 4/15/12 ---5/15/12 5/15/12—6/15/12 6/15/12– 12/1/12 6/30/12 - 7/15/12 7/31/12 (Int. Milestone) 10/1/12 (Int. Milestone) 12/7/12 (Int. Milestone) 12x Jumper base board production/checking jumper board testing PCB production Board assembly/testing Testing and QC at Iowa First shipment of PCB's to CERN 50% board production done All done, tested and delivered to CERN

  8. PMT's Delivery dates at CERN Set 1 Set 2 Set 3 Set 4 Set 5 Set 6 Set 7 Set 8 05/15/12 06/01/12 06/15/12 07/01/12 08/01/12 08/14/12 09/01/12 09/14/12

  9. Assembly and Testing Base board population learning/training Populate and test baseboards HF+ Q1 (27) HF+ Q2 (54) HF+ Q3 (81) HF+ Q4 (108) HF- Q1 (135) HF- Q2 (162) HF- Q3 (189) HF- Q4 (216) AM, IS, DK, MK, OK AM, IS, DK, MK, OK, EE, OO, BU, MY, SD, YOz, HO, KD 07/31/12 - 08/21/12 08/22/12 - 09/07/12 09/07/12 - 09/22/12 09/22/12 - 10/07/12 10/07/12 - 10/22/12 10/22/12 - 11/07/12 11/07/12 - 11/22/12 11/22/12 - 12/07/12 12/07/12 - 12/22/12

  10. Test stand setup IS, AM IS, MF, PD, TK AM, IS, AP IS, MF, PD, TK AM, HB, EB AM, IS, AP, GA, YG AM, IS, AP, GA, YG AM, IS, AP, GA, YG, SD, YOz, FO, SS, SC, NB Adding two students Marcos and Thiago from Brazil. Test new box ( set-up new ROB) Produce and assemble test equip Establish Testing Procedures Produce Test stand equipment AM Tests new Box New ROBOX at 904- operating New ROBOX at SX5- operating Test Stands at SX5—operating 4/23/12 - 5/15/12 3/31/12 - 6/30/12 4/23/12 - 7/31/12 4/15-6/30 5/15 - 6/7/12 7/31/12 - 8/31/12 7/31/12 12/23/12

  11. ROB mechanics Finalize Shield dimensions & All materials ordered QN + Iowa students pre-assembly Ship to CERN CERN Setup HF+ mechanics pre-assembly/cable prep. ROB Completion Dates 25% completion 50% completion 75% completion 100% completion Production contingency PB, MT, IS, PD, TK ZJ, ET, GF, JC, JK, DS Olga, TK, PD, (+2 crews x2) Olga, TK, PD, (+2 crews x2) 04/01/12 - 05/14/12 06/01/12 - 07/01/12 09/01/12 09/14/12 - 10/01/12 10/01/12 - 03/01/13 05/01/12 - 06/31/12 07/01/12 - 08/31/12 09/01/12 - 10/31/12 11/01/12 - 12/21/12 12/22/12 - 02/28/13

  12. Shield Simulations 46 and 54 mm

  13. Shield Simulations 46 and 54 mm

  14. HF Simulation Plans • Goal: study implications of HF upgrade scenarios • 2 vs 4-anode readout • Timing • Trigger • Examples: CMS physics channels • VBF Higgs – forward jet tagging • MET-based channels, SUSY,etc : HF provides coverage for Missing ET measurement • Who is working on this effort: • Ken Hatakeyama (Baylor) + student • New collaborators from Brazil : Alberto Santo, GilvanAlves, Jorge Molina • Rob Kroeger and RahmatRahmat (Mississippi) • Mete Yucel and EsraBarlas (ITU) • Iowa group

  15. HF simulation – 2 and 4-anode readout • ITU grad students (Mete Yucel and EsraBarlas) are working on simulation of 2- and 4-channel readout options of new PMTs. • have made a new shower library in CMSSW -- Geant4 application based on the Quantum Efficiency of new tubes. • Use new shower library to tune GFlash for any other HF-based simulations • with TaylanYetkin, developed simulation code to adapt the current RecHits to 2-channel and 4-channel RecHits, based on findings from test beam. Distributions from CMSSW data match test beam distributions.

  16. Status of code • Working out technical issues in private release, will go into cvs soonwhich includes new quantum efficiency for upgrade PMT’s. • Currently single-channel readout, needs expanded RecHit collection for 2- and 4-anode readout. • Rahmat will use for Gflash tuning as soon as is available

  17. Back-up

  18. PMT test in 2012-I • Iowa is planning is to have all PMT's at CERN sometime in Sept 2012. • All of the PMT's and base boards will be tested in 2012 at CERN • We are in process of defining all test-stand setups and needed equipment to handle the testing of the base boards and PMT's. WE plan on having setups to test the equivalent of two boxes worth of PMT's at a time. The funding request is made- but the funding is not in place. • Burn in HF Plus Side ROBOXs in Garages210 days Mon 3/12/13 - Mon 1/14/14 and Burn in HF Minus Side ROBOXs in Garages 9/21/13 (as defined by the HF Project Schedule).

  19. PMT test in 2012-II • Functionality test – All base boards will be equipped with PMT’s and PMT + base board assembly will be tested at CERN. • Primary readout is with HCAL DAQ and HF QIE etc. • We will have four light distribution boxes (three in addition to existing one). • Number augmented to allow base board + PMT testing in parallel with new ROB test development. • Two will be set up for testing of PMT’s + base boards (6 base boards tested at a time). • In addition to light distribution unit, setups will have: • “Dark box” cover • Signal and HV cables ( At the moment we only have cables for the one upgraded box.) • Support for Base boards + PMT’s (using production ROB parts) All the necessary equipment components are designed currently at Iowa.

  20. PMT test in 2012-III • Before majority of PMT’s will be shipped, we will have 24 m-anode PMT’s + three baseboards at CERN to assemble and test one more “upgraded” ROBOX for test-stand/testing development • Most mechanics already assembled at CERN. • Needs cables from Fermi box. • Will be assembled and ready for use by May. • This ROBOX will be used to define all the test procedures –LED and PED runs, SPE runs. We will define what info goes to database, traveler runs etc.

  21. PCB Production- N

  22. PMT’s New

  23. Assembly&Testing -N

  24. PROJECT FILE-N

  25. PMT Shipping Cost

More Related