Project and Certification Approval Processes Kaizen Event

Project and Certification Approval Processes Kaizen Event. Black Ink Ops: Ramiro Jara, Paul Koelle, Willis Read-Button, Jessica Watkins Report Out for May 12, 2010 MGMT E-5060. About Covidien. Global manufacturer of medical devices and pharmaceuticals

tyme
Download Presentation

Project and Certification Approval Processes Kaizen Event

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project and Certification Approval Processes Kaizen Event Black Ink Ops: Ramiro Jara, Paul Koelle, Willis Read-Button, Jessica Watkins Report Out for May 12, 2010 MGMT E-5060

  2. About Covidien • Global manufacturer of medical devices and pharmaceuticals • 42,000 employees with 58 manufacturing facilities located in 16 countries • 2009 Sales – $10.9 BB Medical Supplies OR, Nursing Care, SharpSafety Medical Devices Endomechanical, Energy, Airway, Soft Tissue Repair, Oximetry Pharmceuticals Specialty Pharma, Contrast, Radiopharma 2 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  3. OpEx Program Certifications to Date: > $1.2 BB OpEx Program Savings to Date: 3 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  4. Kaizen Event Daily Structure • Focused 5-day, team-based, action-oriented activity focused on one discrete improvement effort • Part of Value Stream Analysis of strategic processes • 4-6 people in a team, devoted to the effort for the week • Change is implemented as part of the Event • ‘Lean Sensei’ coach helps with methodology and learning 4 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  5. Process Overview: Project and Certification Approvals Candidate Certification Training Scope Exam Corporate OpEx Project #1 Approval Project #2 Certification Request

  6. Current State Process Paper Based Forms Project Tracking - Instantis Multitude of Steps Long Lead Time 6 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  7. Current State Value Stream Map (VSM) Int’lUSA Lead Time: 651.31hrs 650.81hrs Cycle Time: 3.31hrs 2.81hrs First Pass Yield: 50%

  8. Pareto Chart Incomplete Forms Batching Projects Lack Std. Work Misuse of Tools Excessive L/T

  9. Root Causes/Solutions

  10. Future State VSM Lead Time: 48.95 hrs Cycle Time: 0.95 hrs First Pass Yield: >90%

  11. VSM Side-by-Side Current Future

  12. Hand-off Diagram Side-by-Side: Project Approval Current Future

  13. Hand-off Diagram Side-by-Side: Certification Approval Current Future 13 | Covidien | September 18, 2014 | Confidential

  14. Metrics Side-by-Side *Corporate OpEx team savings based on current salary numbers.

  15. The Softer Side of Savings • Opportunity to find and catch project defects earlier in process • Improved mentorship from OpEx Directors to OpEx Managers/Leaders in the plant, and eventually to candidates • Accountability and performance tracking with better metrics, data collection, and report out capability • Empowerment of GBU and Plant OpEx personnel • Job satisfaction which results in less turnover • Environmental responsibility (less paper/toner waste)

  16. Implementation Timeline Workstream 1: Value Stream Analysis and Certification Kaizen Kaizen #1 to document and analyze VS IS develops eForms Roll out at one GBU for Testing Phase Train and roll out company-wide to 58 plants Run pilot in Texas plant May 12 May 14 June 15 July 15 August Scheduled In progress Workstream 2: Additional Kaizen Events Complete Future Kaizen Events: Monthly Review, Qtrly. Audit, DFSS May-July 16 | Covidien | September 18, 2014 | Confidential

  17. Q&A 17 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  18. Appendix 18 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  19. 19 | Covidien / Black Ink Ops | May 12, 2010 | Confidential

  20. Our team at work… 20 | Covidien / Black Ink Ops | May 12, 2010 | Confidential