An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Briefing to Dickinson City Council July 8, 2014

  2. TNMP Gulf Coast Region

  3. TNMP Mainland Area Customers • Texas City = 21,625 • Dickinson = 11,015 • La Marque = 5,462

  4. Measuring Reliability How Reliability is Measured Total Outage Minutes = ÷ Total number of customers SAIDI = Total Number of Outages ÷ Total number of customers SAIFI

  5. Dickinson Reliability (Year-to-Date May 2014)

  6. Dickinson Outage Causes

  7. Vegetation Management • TNMP’s vegetation management has a time-based component that incorporates mowing, herbicide treatment, hazard tree removal and trimming • There is also a condition-based component that provides for TNMP to address hazard tree removal and tree trimming based on site inspections and outage incidents • TNMP recommends specific schedules according to growth rate and types of trees located in the geographic area and the types and configuration of electric distribution facilities in proximity of vegetation • TNMP inspects and trims entire circuits, to improve efficiency and incorporates “spot” trimming when needed

  8. What Can Customers Do? • TNMP has a tree care guide book available on TNMP.com that references ideal trees for planting as well as many other helpful tree care basics • Trim or remove a tree that is close to or interfering with service wires • TNMP will, at no charge, temporarily disconnect the service so that the customer, or a professional arborist, can safely trim around electric lines

  9. Maintenance Program • TNMP performs line patrols on distribution circuits. • TNMP performs transmission line patrols 3 times per year, two are land patrols and the third one is an aerial patrol. The aerial patrol was completed 6/20/14 • TNMP has spent approximately $872K in Dickinson on reliability projects since January 2011 • Infrared and corona inspections are performed when conditions warrant

  10. System Improvements • Pole and hardware change-outs • Automated Meters—reduces the amount of time for energizing and de-energizing transactions • Wildlife Protection • Line Sectionalizing • Outage Management System

  11. Future System Improvements • Hardening the System—rebuilding transmission line between League City and Dickinson, target date 2015 • Substations –provides capacity for load growth and contingency options for Dickinson customers: • Butler Road Substation – 2015 • Hidden Lakes Substation – 2017 • Mainland Substation – 2017

  12. Emergency Operations Plan • TNMP’s Emergency Operations Plan (EOP) is updated every spring • Storm material and fuel are replenished • Several meetings and a mock drill are complete by June 1st • TNMP’s EOP is reviewed with employees and assignments are discussed

  13. Emergency Operations Plan • Everyone except TNMP’s core group is released • TNMP’s core group will be operating out of the Alvin facility and responding to emergency calls until it is not safe for employees to respond • TNMP will be in contact with the City throughout the event and will be communicating the condition of the transmission and distribution system • Once the storm passes and it is safe the core team will begin restoring power

  14. Emergency Operations Plan • TNMP employees are expected to return within 24 hours to begin restoring service to high priority circuits and performing assessments of TNMP’s system • TNMP crews will be arriving from Central and North Texas, along with crews from New Mexico • Mutual Assistance crews will be allocated to TNMP • The crews will staged at a specific location and will be assigned to substations on TNMP’s system • Crews will work on the highest priority circuit first and continue work until all circuits have been restored • Progress will be communicated to the City daily

  15. Q & A