1 / 71

Critical Design Review for Cessna Mustang Electromechanical Backup Altimeter & Airspeed

Critical Design Review for Cessna Mustang Electromechanical Backup Altimeter & Airspeed. Presenter Subject Time James Ramsey Mustang Team Introductions 9:00 – 9:10 Cessna Mustang Team Introductions 9:10 – 9:15

ursa
Download Presentation

Critical Design Review for Cessna Mustang Electromechanical Backup Altimeter & Airspeed

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Critical Design ReviewforCessna MustangElectromechanical BackupAltimeter & Airspeed

  2. Presenter Subject Time James Ramsey Mustang Team Introductions 9:00 – 9:10 Cessna Mustang Team Introductions 9:10 – 9:15 James Ramsey Project Overview, Schedule, System Requirements 9:15 – 9:30 Dave Newell Electrical Block Diagram 9:30 – 9:45 Mike Harrison Board Layout 9:45 – 10:00 Bill Hertz DSP Software 10:00 – 10:15 Break 10:15 – 10:30 James Ramsey PIC Software 10:30 – 10:45 Tim Sorenson Software Interface 10:45 – 11:00 Michael Schwader Reliability FEMA 11:00 – 11:15 James Ramsey Reliability MTBF 11:15 – 11:30 Todd White Quality and Certification 11:30 – 11:45 James Ramsey Test 11:45 – 12:00 Lunch 12:00 – 12:30 James Ramsey BIT Discussions 12:30 – 12:45 Brian Nielsen Pilot Interfaces, CDP Assembly, Lighting, Connections 12:45 – 1:00 Brian Nielsen Light/Bit Demo 1:00 – 1:15 James Ramsey Requirements 1:15 – 1:30 James Ramsey Action Items 1:30 – 1:45 Break Out 1:45 – 2:45 Agenda 2

  3. Mustang Team James Ramsey Program Manager Brian Nielsen R&D Engineer Bruce Esposito Quality Engineer Neil Saxon Drafter David Newell Electrical Engineer Todd White Quality/DO 178 Bill Hertz Software Engineer - DSP Tim Sorenson Software Engineer - Interface Mike Harrison PCB Layout Patrick Huyck DER – DO 178B, Level B Joe Ulrich Reliability Engineer Michael Schwader Quality Improvement 3

  4. Project Overview • Product overview • Schedule • System requirements • Risk assessment 4

  5. Cessna CDR - 4/30/04 5 Product OverviewUSB

  6. Cessna CDR - 4/30/04 6 Product OverviewRS232C Interface

  7. Schedule 9

  8. Schedule 10

  9. Requirements • Industry and Regulatory • IR-XXXX-X-MSALT • IR-XXXX-X-MSAIR • Must Have • MH-XXXX-X-MSALT • MH-XXXX-X-MSAIR • Highly Desirable • HD-XXXX-X-MSALT • HD-XXXX-X-MSAIR • Value Added • VA-XXXX-X-MSALT • VA-XXXX-X-MSAIR • XXXX – Number (i.e. 0001) • X - Rev Letter (i.e. B) 11

  10. Risk Assessment 12

  11. Hardware - Electrical • Electrical Block Diagram 13

  12. Hardware – Board Layout • Four (4) Boards 18

  13. PWB Design Overview • Cadsoft Eagle Design Software • Valor Computerized Systems (Enterprise 3000) PWB fabrication analysis software • Material: FR4 • Solder Mask (both sides) – LPI • External layer shielding – GND/CGND • .062” nominal board thickness 19

  14. Airspeed I/O PWB DesignPart Number 208914 • (W) 0.750” x (L) 1.625” • (4) four layer design • Components top side only • Interconnect through connectors to DSP and Power Supply 20

  15. Altimeter I/O PWB DesignPart Number 208913 • (W) 0.750” x (L) 1.625” • 6 layer design • Components both sides • Interconnect through connectors to DSP and Power Supply 21

  16. RTC PWB LayoutPart Number 208910 • (W) 0.750” x (L) 1.625” • 4 layer design • Components both sides • Interconnect through connectors to DSP and Power Supply 22

  17. Power Supply PWB LayoutPart Number 208911 • (W) 1.750” x (L) 1.825” • 4 layer design • Components both sides • Interconnect through connectors to RTC, Airspeed I/O or Altimeter I/O 23

  18. DSP PWB LayoutPart Number 208912 • (W) 1.750” x (L) 1.825” • 8 layer design • Components both sides • Interconnect through connectors to RTC, MEMSCAP CCA, Airspeed I/O or Altimeter I/O 24

  19. Software - DSP • Block Diagrams • Data Flow 25

  20. Cessna CDR - 4/30/04 26 DSP Software Block Diagram

  21. Cessna CDR - 4/30/04 27 DSP System Data Flow

  22. Software - PIC • Block Diagrams 28

  23. Cessna CDR - 4/30/04 29 PIC Software Block Diagram

  24. Software - Interface • Maintenance Repair Overhaul (MRO) • Interface • Tasks • OEM 30

  25. Cessna CDR - 4/30/04 31 MRO Interface PC Laptop with interface program. No need to remove instrument. • USB connection on front panel (after removing screw & cover) • Standard USB • Mini-USB on instrument

  26. MRO Tasks • Enable/Disable Trace • View Data Log • View Event Log • Get Time/Date • Display Configuration • Serial Number • Configuration/Part Number • System Info 32

  27. Cessna CDR - 4/30/04 33 OEM InterfaceRS232 Connection • Remove instrument • Proper connector • Have proper OEM software

  28. Reliability FEMA 34

  29. Advanced Product Quality Planning (APQP) • Define customer needs • Identify characteristics to control to meet customer needs • Verify specification for characteristics are properly set • Verify product can be manufactured • Determine process capability • Identify required controls to produce an “in spec” product • Communicate controls to employees 35

  30. Process Control Development • Design FMEA • Process FMEA • Control Plan 36

  31. Identify functional requirements Determine potential failure mode Measurable condition of product List potential effects of failure Determine severity and class Identify causes Design errors Probability of occurrence Current design controls Probability of an escape Risk potential number (RPN) Design FEMA 37

  32. Determine Potential Failure Mode • Twelve Potential Failure Modes Identified • Inaccurate readings while under IFR at various altitudes and varying degrees of error • Leaks • Inoperative when in Wheels Up mode • Sticks while under IFR • Friction while under IFR • Instrument does not fit in to panel • Instruments lights are out • BIT fails to complete its function • Interface characteristics do not mate properly • Instrument board fails • During WOW instrument fails to communicate with USB 38

  33. Failure Effects, Severity & Class • Identify impact of each potential failure • Given the failure occurred, a severity probability assigned • Numeric value between 1 and 10, 1 being least severe, 10 the most severe • Class assignment • Class I - Catastrophic. May cause death or system loss • Class II - Critical. Severe injury, major property or system damage resulting in mission loss • Class III - Marginal. Minor injury, minor property or system damage resulting in delay or loss of availability or mission degradation • Class IV - Minor. Not serious enough to cause injury, property or system damage. Results in unscheduled maintenance or repair 39

  34. Design Errors & Controls • Potential Causes or Mechanisms of the failure • Probability of occurrence • Numeric value between 1 and 10, 1 being least severe, 10 the most severe. • Current Design Controls that will eliminate the Potential Cause • Prevention Control • Estimate the cause will occur that the Design Control is attempting to prevent 40

  35. Cessna CDR - 4/30/04 41 Design Failure Mode & Effects Analysis (Risk Analysis)Product & Revision Level: Altimeter, Cessna Mustang P/N 162350-1161, Rev N/C

  36. Cessna CDR - 4/30/04 42 Design Failure Mode & Effects Analysis (Risk Analysis)Product & Revision Level: Altimeter, Cessna Mustang P/N 162350-1161, Rev N/C

  37. Reliability • MTBF 43

  38. Reliability Model • Any assembly/component failure considered a failure of the Altimeter/Airspeed Indicator • Reliability model consists of assemblies/components in series • Failure rate calculations based on • Airborne Inhabited Cargo Environment (AIC, AC) at a +30° C ambient temperature 44

  39. Failure Rate Sources • Electronic and electrical • MIL-HDBK-217 predicting principles. • Pressure Sensor Module • Provided by the manufacturer • Both Static and Pitot. • RELEX Reliability Software • Version 7.6 45

  40. Failure Rate Sources • Electronic components • MIL-HDBK-217F, Notice 2, Part Stress Analysis • Used RELEX software • Inputs • Dissipated Power • Rated Voltage • Operating Voltage • Initial Temperature Rise • Worst case operating conditions based on the schematics and component data sheets 46

  41. Failure Rate Sources • Mechanical components • The Handbook of Reliability Prediction Procedures for Mechanical Equipment, document NSWC-98/LE1 • RELEX Software supports this document 47

  42. Failure Rate Analysis • Will be updated to reflect the final design 48

  43. Preliminary Airspeed/Altimeter Failure Rate Data 49

  44. Quality and Certification • Software Lifecycle / Design Control Status • RTCA/DO-178B Level B • Configuration Management • DO-254 Applicability • Document Status • Website • DER 50

  45. Level B Software Verification • Structural Coverage Analysis • Decision Coverage • Requirements-Based Testing • Robustness Testing 51

  46. Lifecycle Development Status • Planning Phase • Preliminary Design • Detail Design • Module Build • System Integration 52

  47. Planning Phase • DO-178B Documents / Status • Plan For Software Aspects of Certification – RELEASED • Software Development Plan – RELEASED • Software Verification Plan – RELEASED • Software Configuration Management Plan – RELEASED • Software Quality Assurance Plan – RELEASED • Program Reviews • Engineering Program Review – COMPLETE • Software Planning Review – COMPLETE • Objective Evidence • Document Review & Transition Criteria Checklists - COMPLETE 53

  48. Preliminary Design Phase • DO-178B Documents / Status • Software Requirement Standards – RELEASED • Software Design Standards – RELEASED • Software Code Standards – RELEASED • Software Requirements Document – RELEASED • Program Reviews • Software Requirements Review – COMPLETE • Preliminary Design Review – COMPLETE • Objective Evidence • Document Review & Transition Criteria Checklists - COMPLETE 54

  49. Detail Design Phase • DO-178B Documents / Status • Software Design Description – RELEASED • Program Reviews • Eight Technical Interchange Meetings – COMPLETE • Critical Design Review – TODAY • Objective Evidence • TIM – Presentation Slides & Action Management System Requirements • CDR – Document Review & Transition Criteria Checklists 55

  50. Module Build & Test Phase • DO-178B Documents / Status • None • Program Reviews • Software Code Review - PLANNED • Weekly Technical Interchange Meetings (TIM) – PLANNED • Low Level Verification • Decision Coverage Verification - PLANNED • Objective Evidence • Transition Criteria Checklist - PLANNED • Detailed Unit Level Test Results - PLANNED 56

More Related