60 likes | 211 Views
CIP-010 and CIP-011 Current Status. Reliability First CIP Webinar Thursday, June 22, 2010 Mike Ketchens 06/22/10. Timeline Project 2008-06-Cyber Security Order 706 Phase II. Standard Drafting Team requested industry feedback on the initial drafts – due 6/3/2010.
E N D
CIP-010 and CIP-011Current Status ReliabilityFirst CIP Webinar Thursday, June 22, 2010 Mike Ketchens 06/22/10
TimelineProject 2008-06-Cyber Security Order 706 Phase II • Standard Drafting Team requested industry feedback on the initial drafts – due 6/3/2010. • ReliabilityFirst CIP Team provided feedback. • Drafting team met with FERC Staff members on May 27, 2010 to solicit their feedback. • Drafting team is currently utilizing the feedback received to refine the draft and hopes to put it out for formal review in July/August 2010.
Items of Special Note • CIP-010 and CIP-011 • Eliminate Critical Asset and Critical Cyber Asset terms • Introduce new terms and definitions • BES Cyber System Component • BES Cyber System • Control Center
Highlights of Changes • CIP-010 • Replaces CIP-002 • Has three (3) Requirements and three (3) sub-requirements • Classification of BES Cyber Systems as Low, Medium, or High based on categorization of impact on BES
Highlights of Changes • CIP-011 • Replaces CIP-003 through CIP-009 • Has thirty two requirements and thirty two tables each similar in format to a sub requirement • Implements a catalogue of controls based on impact of BES Cyber Systems as identified in CIP-010
QUESTIONS • Questions should be emailed to Matt Thomas (matt.thomas@rfirst.org), Subject: “CIP WEBINAR” • Questions will considered in the order they are received • Clarifying questions are welcome and we’ll do our best to answer during the question period • Challenges to a position should be addressed to the presenter and will be taken offline