290 likes | 457 Views
Commissioning & Status of ALBA Power Supplies Roberto Petrocelli. ALBA overview and commissioning ALBA Power Converters Booster Power Converters Storage Ring Power Converters Tools for the day to day business Maintenance schedule Conclusions.
E N D
Commissioning & Status of ALBAPower SuppliesRoberto Petrocelli
ALBA overview and commissioning • ALBA Power Converters • Booster Power Converters • Storage Ring Power Converters • Tools for the day to day business • Maintenance schedule • Conclusions
Synchrotron Light Source in Cerdanyola del Vallès (Barcelona, Spain)
ALBA accelerators LINAC 100 Mev BOOSTER 100 MeV – 3 GeV STORAGE RING 3 GeV
COMMISSIONING SCHEDULE • Booster commissioning in parallel to SR installation 2010 • SR commissioning (1st phase) March-June 2011 • Installation Insertion Devices: SCW and IVUs Summer 2011 • SR commissioning with all IDs restarted Sept 2011 • Beam for beamlines commissioning Oct 2011 • First external users May 2012
SR COMMISSIONING 16 March: Beam Accumulated 1.5 mA stored Acummulation Current SR Current Booster
1st synchrotron light outside the tunnel
LIGHT from APPLE-II UNDULATOR Beam Image at Fluorescent Screen on the FE • Screen @ 9.35m from source (middle of straight section) • Source APPLEII undulator EU62 • Stored current I=0.8mA Minimum gap (15.5mm): Horizontal mode (K=5.2) Circular mode (K=3.0) Vertical mode (K=3.7)
ORBIT STABILITY 1week data 1shift (8h) data SLOW ORBIT FEEDBACK RUNNING 0.3 Hz 88 BPMs 88 CORH & 88 CORV FAST ORBIT FEEDBACK UNDER DEVELOPMENT
2012 In Operation • Beam-Line Users since May • 24 Hour operation • 2 injections. • Expected 2000 hours for Beam Lines and 1200 for Machine studies
Magnet Power supplies at ALBA Distribution of Power Supplies in the Service Area
Major Incidences with main BO PS Noise in Buck Module of BO_Bend_01 Buck input current
TOOLS FOR DAY TO DAY BUSINESS • PS Logbook • PS database • TRAINING OF OPERATORS
2012 MAINTENANCE SCHEDULE • 5 WEEKS FOR MAINTENANCE ( distributed along the year) • MAIN TASKS WE DO • Connection Checks • Rotate Spare Power Supplies • Check calibration in Booster and SR Bendings. • Perform annual test required by authorities ( CSN )
2012 MAINTENANCE Terminal not Crimped
2012 MAINTENANCE Fan out of order
STATISTICS Operation for users
Next Steps • Fast Orbit Feedback. • Project of Power supplies for future upgrades.
Conclusions • It is not realistic to expect to find all the problems during FAT, SAT and commissioning.
Thank You ! Questions ?