Gaz-System S.A. Transmission System Operator. Gdynia , 26.06.2009. AGENDA. 1. G AZ -S YSTEM S.A. Transmission system - Facts & Figures. 2. Disruption of supply 2009. System development. 3. 4. Activities. National gas transmission system operator (TSO)

varden
Download Presentation

Gaz-System S.A. Transmission System Operator

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gaz-System S.A. Transmission System Operator Gdynia, 26.06.2009

  2. AGENDA 1 GAZ-SYSTEM S.A. Transmission system - Facts & Figures 2 Disruption of supply 2009 System development 3 4 Activities

  3. National gas transmission system operator (TSO) Established on the basis of theDirectiveof the European Parliament and the European Council 2003/55/EC Formed in April 2004, unbundled from PGNiG S.A. Joint-Stock Company, owned by the State Treasury as the only shareholder GAZ-SYSTEM S.A. Facts&Figures

  4. GAZ-SYSTEM S.A. Facts&Figures • Company-owned transmission assets worth over 3 billionPLN • Near 2 000 employees across Poland. • 6 Regional Branches: • Gdańsk, • Poznań, • Rembelszczyzna, • Świerklany, • Tarnów, • Wrocław.

  5. Transmission System Overview Transmission system elements (2009): • 9 800 km pipelines • 14 compressor stations • 57 gas nodes • 970 exit points Main Characteristics: • Polish gas system is connected with the European Gas Network system but only along the East-West direction. • Gas imports mainly from Eastern direction. • Gas Imports amounting to 70% of total national consumption .The remaining 30% is covered by national production. • Transmnission of 14.7 bcm/year

  6. TRANSMISSION SYSTEM Network

  7. UndergroundGas StoragesCooperation with Transmission System

  8. DEMAND AND SUPPLY2008

  9. Supply2008

  10. Demand2008

  11. Supply and pressure - Drozdowicze01-02 2009

  12. Supply and flows Peakday 2009

  13. Supply and flows Peakday 2006

  14. AVAILABLE CAPACITIES AND CONGESTIONS

  15. Network expansion Baltic Pipe Szczecin-Gdańsk LNG Terminal Włocławek-Gdynia Świnoujście- Szczecin Rembelszczyzna-Gustorzyn Szczecin-Lwówek Gustorzyn-Odolanów Jeleniów-Dziwiszów Zdzieszowice-Ołtaszyn Skoczów-Komorowice-Oświęcim Strachocina- Wygoda Hermanowice-Strachocina

  16. Development of Interconnections • Poland- Czech Rep. Connection • New connection integrating the gas systems of both countries which will diversify and ensure stable gas supplies to end customers • Increase of safety of systems operations • Project developed in cooperation with Czech TSO • Commencement of operations: 2010/2011 • Enhancing Poland-Germany Connection • Development of existing interconnection between the gas systems of both countries • Increase of safety of systems operations • Possibility of increased flows from western direction in case of crisis • Capacity increase: 0,5 bcm p.a. • Commencement of operations: 2011

  17. LNG Terminal will be located in the Port of Świnoujście Project developed by SPV Polskie LNG (PLNG) owned by GAZ-SYSTEM S.A. One jetty for LNG tankers LNG Terminal’s regas capacity: Phase I/II: 2.5-5.0 bcm / 1,85-3,7 Mt LNG/year Phase III: 7.5 bcm / 5,6 Mt LNG/year LNG storage capacity: 2 tanks 160 000 m3 LNG each LNG loading infrastructure for trucks. Open season procedure - start 23 of June 2009 – end expected January 2010 documents available at www.polskielng.pl • LNG TerminalŚwinoujście

  18. Interconections - Conclusions LNG ? Baltic Pipe PL-CZ PL-DE 2009 2010 2011 2012 2013 2014 2015 2016

  19. OPEN SEASON • Applied in the case of constructing new elements of the gas system in order to adjust the parameters of the planned investment to market expectations. • Procedure implemented pursuant to ERGEG guidelines. • The procedure is conducted in strict cooperation with the Polish Energy Regulatory Office in order to ensure the Investor applies non-discriminative access policies to the network.

  20. NEW PROJECTS – OPEN SEASON

  21. GAZ-SYSTEM on Transparency Platform GAZ-SYSTEM is active on the Transparency Platform from its launch on 17th November 2008. The TSO-related information and Capacity & tariff information have been published On 17 march GAZ-SYSTEM switched display of its capacity data from Nm3/d to kWh/d. On 2 April GAZ-SYSTEM added to Transparency Platform data on its capacity allocation mechanism and on its balancing model, balancing tolerances applied and other static balancing information. GAZ-SYSTEM constantly uploads data files to the Transparency Platform. Actually GAZ-SYSTEM is working on its automatic upload of nominations, re-nominations and allocations for its respective interconnection points.

  22. Interconnection Points Agreements • GAZ-SYSTEM has signed IPA with all TSOs connected to our system: • Biełtransgaz (Belarus) • ONTRAS (Germany) • UKRTRANSGAZ (Ukraine) • Due to geographic position we are like transition area between two arts of gas market • Eastern: • quantity - volume by 20 C, • energy day 8/8, • allocation based on seller decisions • No balancing market • Western • Quantity – energy • Energy day 6/6 • OBA • Market based balancing • Middle (PL) • Quantity – volume by 0 C • Energy day 10pm/10pm • Regulated market • But all discrepancies are covered in practice

  23. Thank you for your attentionpiotr.bujalski@gaz-system.plstanislaw.brzeczkowski@gaz-system.pl