An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Non-Store Closure Renovation

  2. Pre Construction Due Diligence • Meet with town to discuss expectations and pre-schedule inspections. Have Permits in hand • Meet with landlord to discuss dumpster & storage locations and to see if they have any site specific regulations • This is especially important in mall locations • Complete the detailed construction schedule • Cross reference the Material Schedules on plan to the FFE Plan to the Items Ordered Sheet to look for discrepancies • Conduct pre-construction meeting with the SM, DM, CM and GC to alleviate apprehensions and go over expectations

  3. Freehold, NJ Before & After

  4. Typical Closing Schedule • Day 1; Monday; 12:00 noon until 5:00 am (16 hours) • Day 2; Tuesday; 12:00 noon until 5:00 am (16 hours) • Day 3; Wednesday; 12:00 noon until 5:00 am (16 hours) • Day 4; Thursday; 12:00 noon until 5:00 am (16 hours) • Not needed if floor is not being done • Day 5; Friday; 6:00 pm close until 5:00 am (11 hours) • Days 6 & 7; No work over the weekend (OPTIONAL) • Day 8; Monday; 6:00 pm close until 5:00 am (11 hours) • Day 9; Tuesday; 8:00 pm until 5:00 am (9 hours) • Day 10; Wednesday; 8:00 pm until 5:00 am (9 hours) • Thursday; Store is back to normal hours

  5. Monday Day 1- Backline • Re-set equipment • Power and plumbing hook ups • Clean and re-set store for a normal morning opening • Demo of back line/int. walls • Rework electric & plumbing • Build new walls/rock 1 side • Blocking/install wall cubbies • Set backline cabinets & counters

  6. Tuesday Day 2 - Frontline • Demo floor tiles to be replaced • Scarify floor of thinset • Prep for back splash wall tile • Begin wall prep for paint • Demo and set panels at 1st R. R. • Clean and re-set this store for a normal morning opening • Demo frontline, save pastry case • Saw cutting for floor sink relo • Re-work electric and plumbing • Set new bar, POS, & pastry case • Re-set all equipment • Power and plumbing hook ups • Seam Corian counters at the BL

  7. Wednesday Day 3 – Lighting/Ceiling • Demo existing chair rail • Replace all damaged ceiling tiles • Install R.R. accessories • Clean and re-set store for a normal morning opening • Rough framing inspection • Re-locate/add wood soffit panels • Install new ceiling lighting • Finish first R.R. install Fixtures • Install Banquette seating • Continue wall prep

  8. Thursday Day 4 - Flooring • Final ceiling prep for Friday paint • Prep and install wall cladding at the accent wall • Install custom wood trim at hallway door • Clean and re-set this store for a normal morning opening • Install floor tile, base and grout • Install backsplash tile and grout • Continue wall prep • Demo and set panels at 2nd R. R. • Install under counter lights at cubbies • Install FRP at the wet cabinets

  9. Friday Day 5 – Ceiling Paint Protection for ceiling paint Install BOH Eliason door Finish 2nd R.R. install fixtures Install R.R. accessories Finish and sand all spackle Clean and re-set this store for a normal morning opening

  10. Sat/Sun DAY 6 &7 No Work Over The Weekend

  11. Monday Day 8 • Install free-standing merchandise bays • Build and set new condiment cart • Begin wall paint, paint R.R. • Install chair rail • Install new walk-off mat • Install FRP & re-set BOH as per plan • Install vinyl wainscoting • Clean and re-set this store for a normal morning opening

  12. Tuesday Day 9 • Install mural • Install artwork • Silicone throughout • Clean and re-set this store for a normal morning opening • Finish all wall painting • Install custom shelving unit • Install artwork/mural trim • Install metal corner guards

  13. Wednesday Day 10 Final electrical inspection Final plumbing inspection Build and set furniture General punch list Professional cleaning service window cleaning mechanical floor cleaning high dusting general cleaning After today, the store is back to normal hours Final building and health inspections are done during the day on Thursday

  14. Florham Park, NJ Store Expansion Before After OBJECTIVES: add Clover, claimed 500 square feet of unused square footage which increased customer seating from (18) to (32) seats, open-space feel with updated palette.

  15. Before and After Floor Plans

  16. Phasing Plan

  17. Mercer Mall Ten Year Reno with a Restroom Relocation & BOH Expansion, Before After OBJECTIVES; enlarge BOH and Managers area, get the full size refrigerator into the back of house, open up space, while increasing seating from (11) to (20) seats , we also replaced floor tile (tile over tile).

  18. Before & After Floor Plans

  19. Phasing Plan

  20. Glen Rock, NJ Reno Using The Temporary Trailer Keeping the customer happy WhileInside….

  21. Setting Trailer Utility Hookups General Guide Lines Trailer must fit the location Get prior approval from the town Safe & separate egress for customers and workers Plan on minimum 4 days to set trailer with inspections (NJ) Prior arrangements for ice delivery and bulk milk storage Prior coordination of data runs for POS and brewing equipment Temporary dry storage will be required We were able to open store and then remove trailer in one day

  22. This store was completed in 11 days working thru the weekend, turn over on Friday. We installed new floor tiles and did a full bar reversal. There were only a few hours of interrupted business.