270 likes | 804 Views
NDPL CASE STUDY - Protection Requirements for Power Distribution by R. N. Kumar GM , NDPL Nilesh N. Kane Sr. Manager, NDPL. CENTRAL BOARD OF IRRIGATION AND POWER 5 th International Conference on Power System Protection and Automation. Flow of Presentation. Overview of NDPL network
E N D
NDPL CASE STUDY - Protection Requirements for Power Distribution by R. N. KumarGM , NDPL Nilesh N. Kane Sr. Manager, NDPL
CENTRAL BOARD OF IRRIGATION AND POWER 5th International Conference on Power System Protection and Automation
Flow of Presentation • Overview of NDPL network • Transformation for betterment • Exploration in Relaying • Exploitation of Relay facilities • NDPL Case Studies 4
Overview of NDPL Network • NDPL is a Joint venture of TATA Power and Govt. of NCT of Delhi • NDPL looks after Power Distribution of North and North-west area of Delhi • Area of distribution network - 510 sq. km • Total number of 66/33 KV Grid Stations – 59 • No. of Distribution Transformers – 9000 • Total no. of RMU’s - 8500 4
Transformation – Protection Reliability • System reliability and availability is the main focus of a power distribution utility. • Protection and control system and its timely and correct operation during faults is an important and crucial aspect in efficient and successful operation of Power distribution utilities. • NDPL has completed its GSAS (Grid Substation Automation Scheme) project in 2005 • Grids were commissioned with use of IED’s that are compatible to SCADA • This transformation from Electromechanical to Numerical relaying lead to better system reliability. 4
Transformation – Grid Stations After GSAS in Grid Substations 4
Transformation – Distribution Old Switch Gears New Ring Main Units 4
Expectations from newly adopted relaying system • Redundancy of Protection functions in terms of • Main/Backup relay. • Multiple protection elements. • Communication compatibility for SCADA systems. • Fast operation of the system with correct indication • Improvement of the system with faster Corrective and Preventive Actions. • Efficient and Correct Fault Discrimination • Record of Real time metering along-with its quality features • Online Diagnosis and relay setting 4
Distribution Fault Restoration using FPI’s • Fault occurrence • Upstream Breaker Opens • FPI indicate fault NO 4
Effective Distribution Protection • Application cum Coordination • Various characteristics like NI/VI/EI have been effectively used from grid to RMU to accommodate stiffer relay setting coordination of even 250ms. • Customer satisfaction has been ensured through faster restoration of supply. • Average restoration time • Grid tripping : 1.12 hrs • Tripping at FSS : 38 Minutes • Av. Tripping per month : 700 • Trippings reduced to 300 • Downtime reduction/month : 260 hrs 4
Improvement in System Reliability • All Protection relays cum BCU’s are well protected with Password. Separate Passwords for operation and Protection facilitate safe Protection settings and eliminated tampering of the relay settings. • Ultimate Goal of the Automation is to operate the system in Unmanned mode. Mimic diagrams and friendly relay functions of the Relay helps breakdown team to visualize and understand the fault and operation. • Additional Trip Supervision relay and wiring has been reduced by using status inputs of the Numerical Relay. • Following Logics has been Configured in the relay for having effective control and Protection of the system without conventional hard wiring. • CBFP cum LBB Scheme. • Reverse Blocking Scheme for Bus bar Protection. • No requirement of the Annunciation fascia due to availability of sufficient Configurable LED’s on relay itself. 4
Scheme/Logic Implementation • Important Projects/Logics includes: • Reverse Blocking • Local Breaker Backup • Transformer Monitoring Unit • CAP ON TAP • Remote Relay Parameterization • Multiple Relay setting groups • Safety concerns tackled with relaying • Life assessment of Lightning Arrestors 15
CT SATURATION AT 33 KV AIR KHAMPUR GRID SATURATED CORES 16
CASE STUDY 4 Tripping of 11 KV Incomer-2 Tripping without indication on Outgoing fault in 33 KV
C11 C31 C51 C71 => CDG Relay NC contact. => CDG relay Coil => Series Trip Coil Observations 1. It was found that at high currents with unbalance, the 11 kV Incomer-2 was tripping without indication.2. It was found that the tripping was occurring through series trip coil mounted on the 11 kV Incomer breaker.3. It was found that the series trip relay (CDG), though not operated gave a trip signal to the breaker when secondary injection was carried out on Phase to neutral CT.4. On checking the wiring of the series trip relay and the tripping circuit, one wire was found broken as shown in diagram. Breaker was tripping through series trip coil which was operating on spill current due to unbalance in system. Analysis For Wazirabad Inc. 2 tripping without indication during outgoing fault. 19
Conclusion & Corrective Action 1. As the interconnection between NC Contact and Neutral terminal was disconnected due to defective lug crimping, the unbalance current, whenever present, was not being bypassed by the NC contact of the relay. Instead, the current was going through the series trip coil, thereby making relay settings redundant. This was leading to the tripping of 11 kV Inc.2 breaker tripping on any unbalance or fault.2. Necessary correction wiring of contacts was done and Unbalance was simulated to check the correct operation of the relay .Now Control circuit and relay functionality found OK. 20
CASE STUDY 5 Tripping Analysis report for 11 KV Mithila Vihar feeder along with 11 KV Incomer
Case Study • Tripping Analysis report for 11 KV MithilaVihar feeder alongwith 11 KV Incomer • Details of Event • 11 KV MithilaVihar feeder tripped alongwith 11 KV Incomer • Observations • Total load of the station is around 800 Amps and System is keeping total load on any of the transformer keeping the other transformer on no load. • MithilaVihar feeder tripped on over current High set. • 11 KV Incomer-2 tripped on over current High set. • Fault data record of the Incomer show’s that Fault seen by 11 KV • Incomer is 9.1 KA while fault seen by MithilaVihar feeder is 6.2 KA. • It is observed that Nithari feeder was also seen the fault but not tripped due to isolation of the fault. Protection settings were Coordinated and CT Ratio adoption was found correct. 23
Conclusions After going through the tripping events it was observed that both feeders were getting tripped simultaneously. After going through the fault data record, it is very clear that fault seen by Incomer is always on higher side as compared to the outgoing feeder. The tripping in the incomer occurs as the fault current “seen” by the incomer breaker is a summation of the outgoing faults. It has been learnt from Concerned Zonal staff, that both the outgoing feeders in question, viz. MithilaVihar feeder and Nithari feeder, are routed on the same poles and on same cross arm. Thereby, the occurrences of birdages in both the feeders occur simultaneously. 24