An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. User Compensation for NEC Storage Curtailment – Draft Proposal Transmission Workstream 01/12/2005

  2. National Grid Transmission 0052 response • Concerned about reduction in incentive for 0052 shippers and potential for increased role for Residual Balancer • Is 30 day SAP appropriate compensation

  3. Aims • Appropriately compensate Users affected by Storage Curtailment • Ensure that Users remain incentivised to contribute to the physical balance of the system • Recognise that title to the gas held in Storage remains with the User

  4. Proposed Compensation Amount Lesser of: SMPBuy – SAP or SAP – (ASSAP + 0.0611p/kWh) Where, ASSAP (average summer SAP) 0.0611p is the mod 0433 derived minimum differential between SMPBuy and SMPSell

  5. Example User Injects 25 units between curtailment periods 1st Curtailment Period 2nd Curtailment Period

  6. Example