An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HVDC Link Romania – TurkeyShort presentation George VISAN Director, Investment Projects Management Direction

  2. A major and complex project to be considered and developed Pasakoy

  3. Where we are now ? • Scope of MOU -1 between Transelectrica and TEIAS for the elaboration of the system study is achieved; • System study was analysed and finished by signing the Joint Position Paper of 26 december 2006 ; • What to do next ?

  4. Simplified Roadmap MOU - 1 Opportunity ( system ) study Preliminary Joint Position Paper Political Joint Statement MOU -2 Feasibility Study Business Study Final Joint Position paper ( corporate level ) Project Approvals Project International Agreement between Romania and Turkey Project Implementation

  5. Roadmap – major phases and milestones • Phase 1 – elaboration of the system study ( opportunity study ) • Corporate Level : Transelectrica and TEIAS • Cooperation instrument : MOU 1 • Delivrable : Opportunity study – April 2006 • Validation : Preliminary Joint Position Paper ( P-JPP ) to be included in MOU 2 • Phase 2 – elaboration of the feasibility study and business study • Corporate Level : Transelectrica and TEIAS • Cooperation instrument : MOU 2 • Delivrables : • Feasibility study • Business study • Validation : Final Joint Position Paper ( F-JPP ) • Corporate approval of the business study and the feasibility study

  6. Roadmap – major phases and milestones • Phase 3 – Preparing implementation • Project organization ( project company ) • Financing structure • Project implementation plan • Phase 4 – Project Approvals • Approval of the feasibility study in Romania (by Governmental Decision) • Approval of the feasibility study in Turkey • International agreement between Romania and Turkey • Phase 5 – Implementation • Transelectrica –TEIAS binding agreement to jointly build the HVDC link • Phase 6 – Preparing technical and comercial operation of the HVDC link

  7. Preparing Phase 2 • Transelectrica’s proposal : • To meet in May TEIAS for negotiating MOU -2 for the Feasibility study and the Business study; • Preliminary JPP to be included in MOU -2; • Draft MOU-2 to be prepared by Transelectrica and send in advance to TEIAS

  8. Feasibility study -1 • Structure of the feasibility study : • Part 1 – HVDC link – Conection to the Romanian Transmission grid • Part 2 – HVDC link – Conection to the Turkish Transmission grid • Part 3 – HVDC link – Undersea cable • TOR : • To be written; • To include prefeasibility needs • Needed technical assistance for TOR • Transelectrica intends to use : • the expertise of Fichtner ( available in Romania and with previous expertise in similar projects ) • To cooperate with sister TSO companies having direct experience in such HVDC projects ( ex : Statnett /Norway ); • TEIAS position : TBD ( to be defined )

  9. Feasibility Study - 2 • Financing engineering services for the feasibility study : • Financing scenarios : • Without grant ( 100 % financing by Transelectrica and TEIAS with 50/50 % split for part 3 ) : • Advantage : supply independence of the engineering company; • Superior bankability for the project financing; • With grant for part 3/undersea cable : • Advantage : reducing financing effort • If grand to be taken, from where and when ? • Recommended scenario : without grant (100% corporate financing ); • Contracting engineering services : • Contracting procedure in accordance with legislation and type of financing; • To involve as much as possible local expertise • Romania : Fichtner and ISPE

  10. Business study • Extremely important and sensitive; • TOR to be written; • Consultancy partialy needed • To be done in parallel with the feasibility study; • Contracting : with international technical assistance • Financing : proposal - jointly by Transelectrica and TEIAS ( 50/50% split ) • To explore and facilitate involvement of private investors from Turkey and Romania in order to : • Increase the commercial use of the HVDC link • Reduce the cost of financing;

  11. Business study – main chapters in TOR • Marketing analysis • Clients ( for transmission services ); • Volumes and periods • Contracts and prices; • Regulatory analysis • Requirements of the national authorities; • Acceptance in the RAB ( regulated asset base ); • EU requirements, including UCTE, ETSO • Definition of the business model • Definition of the ownership model • Ownership structure; private investors; • Definition of the business plan • Compatibility cross-checkings • Sensitivity analysis