1 / 20

Risk analysis : - Splitters replacement - TCSC replacement

Risk analysis : - Splitters replacement - TCSC replacement. WG TDC2/TCC2 18 th June 2013. General risks. Common risk related to handling operation Breakdown of a handling equipment : Renewed and spares pieces available for repairs External exposure: Reduced to the minimum.

vidor
Download Presentation

Risk analysis : - Splitters replacement - TCSC replacement

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Risk analysis :- Splitters replacement- TCSC replacement WG TDC2/TCC2 18th June 2013 E. HARROUCH EN/MEF

  2. General risks • Common risk related to handling operation • Breakdown of a handling equipment : Renewed and spares pieces available for repairs • External exposure: Reduced to the minimum. • Number of contact operation very limited • Time of exposure limited • Add of shielding and training of the operators to optimize their position during the operation E. HARROUCH EN/MEF

  3. Risk analysis for North Area splitters replacement • Procedure • Hazard inventory, risk analysis and proposed measures step by step E. HARROUCH EN/MEF

  4. Where are they installed? TDC2 BA 80 One groups of 3 magnets They are designed with V supporting and automatic plug ins Installation rails are on place, and prealigned with the magnet E. HARROUCH EN/MEF

  5. Replacement procedure for North Area splitters • Slides from Jean-Louis : https://espace.cern.ch/sba-workspace/tcc2wg/21st%20Meeting/default.aspx?InstanceID=1 Installation has as well been tested https://edms.cern.ch/document/1155859/1 E. HARROUCH EN/MEF

  6. 3 2 1 E. HARROUCH EN/MEF

  7. 1ere étape : Retrait des splitters JL GRENARD EN/HE

  8. 1ere étape : Retrait des splitters E. HARROUCH EN/MEF

  9. 2ere étape : Dépose du splitter dans le fond du TDC2 E. HARROUCH EN/MEF

  10. 3eme étape : Réinstallation du splitter sur les tables plugins E. HARROUCH EN/MEF

  11. Risk analysis for the TCSC replacement • Procedure • Hazard inventory, risk analysis and proposed measures step by step E. HARROUCH EN/MEF

  12. Procedure TCSC 954 • Removal of the TCSC for storage in the 954 • Transport of the TCSC with the PRATT to the entrance of TCC2 • TCSC moved into TA801 with the trailer • The TCSC is lifted into the PA80 and transported to the 954 for storage BA 80 • Installation of the new TCSC in TDC2-> Inverted procedure JL GRENARD EN/HE

  13. 1ere étape : Retrait du TCSC E. HARROUCH EN/MEF

  14. 1ere étape : Retrait du TCSC E. HARROUCH EN/MEF

  15. 1ere étape : Retrait du TCSC E. HARROUCH EN/MEF

  16. 2eme étape : Roulage jusqu’en TCC2 E. HARROUCH EN/MEF

  17. 3eme étape : Reprise avec la remorque en TCC2 E. HARROUCH EN/MEF

  18. 4eme étape : Roulage jusqu’en bas du PA80 E. HARROUCH EN/MEF

  19. 5eme étape : Reprise au pont puis stockage au 954 E. HARROUCH EN/MEF

  20. Conclusion • Temps de réflexion du LS1 • Une grosse défaillance semble très improbable une fois toutes les mesures prises. • Les dangers les plus probables mènent àune situation non critique. E. HARROUCH EN/MEF

More Related