1 / 11

Historically largest cement producer in Kazakhstan located near the new capital Astana

Historically largest cement producer in Kazakhstan located near the new capital Astana Current production of 0.8 m. tons will increase to over 3 m. tons once refurbishment exercise is completed New production will serve to curb imports in Kazakhstan currently 2 m. tons per year

virgil
Download Presentation

Historically largest cement producer in Kazakhstan located near the new capital Astana

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Historically largest cement producer in Kazakhstan located near the new capital Astana • Current production of 0.8 m. tons will increase to over 3 m. tons once refurbishment exercise is completed • New production will serve to curb imports in Kazakhstan currently 2 m. tons per year • Equity listed in AIMS under STCM code since October 2005 • 114 million shares outstanding, market cap approximately $400m. • Free float 38% • Bonds listed in the KASE under CACMb1, $21 m. market value STCM Nov 2006

  2. PRODUCTION, SALES & PRICE thousand tonnes Price per tonne Kazakh tenge STCM Nov 2006

  3. FINANCIAL HISTORY OF CAC / STEPPE CEMENT STCM Nov 2006

  4. KAZAKHSTAN CEMENT SUPPLY AND DEMAND STCM Nov 2006

  5. ESTIMATED FUTURE CEMENT CONSUMPTION STCM Nov 2006

  6. NORTH EAST WEST CENTRE SOUTH REGIONAL CEMENT MARKET SALES Source: Association of Cement Manufacturers Kazakhstan STCM Nov 2006

  7. EXPORTERS TO KAZAKHSTAN STCM Nov 2006

  8. PROJECT SCOPE AND TARGETS • Refurbished line 6 maintaining kiln, pre-heater and cooler but full electrical repairs by ABB • Change of pyro-processing line 5 by FL Smidth and full electrical and mechanical repairs • Project may be extended to cover improvements in raw mills, cement mills, quarry, compressors and dispatch STCM Nov 2006

  9. PROJECT ORGANIZATION AND PROGRESS • New COO, Stuart Elliot ex COO Cimentiere du Liban • 7 expatriate mechanical and electrical engineers on site with over 200 years combined experience in the cement industry • Mace UK acting as project manager with 7 employees on site • PEG, Philips Reamer, FL Smidth as technical consultants • 80% of contracts for line 6 and 60% of contracts for line 5 signed • Objective: to sign all contracts by end 2006 and complete lines 6 and 7 for the summer seasons 2007 and 2008 STCM Nov 2006

  10. FINANCING • First share offering completed in March 2006 raised $21 m. in AIMS • Bond issue completed in September 2006 for $21 m. Full disbursement to be completed in November 2006. Trading in the KASE • EBRD loan signed in December 2005. Planned to be disbursed in 1Q 2006 • Bridge finance of $46 m. from KKB for suppliers letters of credit • Income tax exemptions for all new production for 5 years starting in 2007 STCM Nov 2006