Work-packages for 2011-2016, planning and status

R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011. Work-packages for 2011-2016, planning and status. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011. Status at the last Collaboration Board (February 2011):

virgil
Download Presentation

Work-packages for 2011-2016, planning and status

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 Work-packages for 2011-2016, planning and status

  2. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Status at the last Collaboration Board (February 2011): • First top-down resource evaluation (see next slides) • First work-package list available • (http://indico.cern.ch/getFile.py/access?contribId=9&resId=0&materialId=0&confId=117583)

  3. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 “Resource – drivers” • Status at the last Collaboration Board (February 2011, from Steinar’s slides): Very preliminary

  4. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Status at the last Collaboration Board (February 2011, from Steinar’s slides) – Material Budget: • Ramp-up to about 30 MCHF/year in 2013 • Total integrated 2012-2016  150 MCHF • Assuming planned CERN contribution • (MTP 2010 – about 90 MCHF) •  need from collaborators 60 MCHF • Material contributions from outside CERN should rise from 20-25% (present level) up to more than 1/3

  5. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Status at the last Collaboration Board (February 2011, from Steinar’s slides) – Material Budget: Ramp-up from about 110 to 170 FTE Planned CERN contribution (MTP 2010) slightly decreasing! However, in the MTP after 2011/2012 most of non-staff manpower is not accounted for Taking this into account, the CERN manpower is substantially flat (however, a fraction of this will have to be provided by a material-to-personnel transfer)  need from collaborators up to ~ 60 additionalFTEs

  6. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Status at the last Collaboration Board (February 2011): • First top-down resource evaluation (see next slides) • First work-package list available • (http://indico.cern.ch/getFile.py/access?contribId=9&resId=0&materialId=0&confId=117583) • Since then: • Discussions at 6 (out of 9) CLIC Accelerator Steering Committes • One-day CASC retreat (March 4th) • UK-CERN collaboration start-up meeting • But also new CERN MTP 2011

  7. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • CERN MTP 2011 • Some increase in Personnel budget • Material budget generally decreased by 7.3% due to a negative material indexation

  8. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Present Status: • Work-program organized in WPs covering from hardware (very straight-forward WPs) to working-groups (attempt to also describe as WPs) • Description of work-packages in some detail done (see next slides) • Including material and manpower profile over 2012-2016 • Mainly top-down, but some input from CERN groups and collaborators in some areas • Some cuts in material budget already implemented…

  9. CTF3 Other comments: First review with Oxford at UK kick-off. Problem with schedule – agreed on strategy (first stage at reduced performance, possibly with commmercialampli (commercial 25 kW ampli 800 k$), compromise on power/bandwidth.

  10. CLIC 0

  11. CLIC 0 Other comments: Modulator/Klystrons are on the critical path. Lower efficiency prototypes (direct scaling from ILC/X-FEL?) could arrive earlier, allowing to keep the schedule. Discussion with RF group needed. Option: delay program. First stage with minimum number of 1 GHz klystron prototypes (4), short pulse + compression. Full upgrade in 2017-2018 (GAIN 13 MCHF)

  12. 200 R. Corsini, CASC 6 May 2011 CTF3+/CLIC 0 • Spending profile for integrated beam systems tests

  13. CTC-004 two-beam module development CLIC Linkperson: G. Riddone

  14. CTC-004 two-beam module development Other comments: total modules considered for construction: 13-16 (see task 1); All deliverables for modules (Alignment, Stabilization, BI, vacuum, RF structures etc) paid by TBA module budget.

  15. X-band Rf structure Production

  16. X-band Rf structure High Power Testing

  17. Creation and Operation of x-band High power Testing Facilities

  18. Two-Beam Acceleration

  19. Two-Beam Acceleration (cont.)

  20. Integrated Dynamic Studies

  21. Integrated Dynamic Studies (cont)

  22. 200 R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Global – Material, reviewed Total integrated: 140 MCHF In CERN MTP: 86 MCHF Needed from Collaboration: 64 MCHF over 5 years

  23. 200 R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 • Global – manpower (preliminary) Ramp-up from about 110 to over 200 FTE Planned CERN contribution (MTP 2010) slightly decreasing, however, in the MTP after 2011/2012 most of non-staff manpower is not accounted for Taking this into account, the CERN manpower is substantially flat (however, a fraction of this will have to be provided by a material-to-personnel transfer)  need from collaborators up to ~ 100 additional FTEs Under review

  24. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 Summary table • Full info: • (https://indico.cern.ch/getFile.py/access?contribId=10&resId=0&materialId=slides&confId=134291)

  25. R. Corsini, 13thCLIC/CTF3 Collaboration Board Thursday 19 May 2011 Summary table

  26. 200 R. Corsini, CASC 6 May 2011 CTF3+/CLIC 0 • Manpower profile for integrated beam systems tests CERN staff & fellows about constant, some increase in M to P Ratio PCERN / PColl goes from 3 to 2