1 / 20

IENG 471 - Lecture 04 - 3

Learn to optimize workstations by assigning ideal machines, calculating idle time, cost per unit, and space requirements. Collaborate in class for hands-on experience.

visaacs
Download Presentation

IENG 471 - Lecture 04 - 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IENG 471 - Lecture 04 - 3 Schedule Design: The Sequel’s Sequel IENG 471 Facilities Planning

  2. Assignments • Current Assignment: • HW: (HW 3) See Assignment Link • required input for each of the workstations • equipment necessary for each machine • steady state cycle time for each machine • ideal machine assignment for each machine • compute the idle time • unit cost at each workstation • total cost per good unit • square footage for each workstation and the total space required • We will use class time next period to work this problem • So sit with the people that you want to work with on this assignment! IENG 471 Facilities Planning

  3. Ex: Injection Mold Rubber Feet • We obtain one set of feet per cycle • Machine time is 35 s (steady state) after the operator starts the process • At the start of each cycle, the operator will spend 5 s unloading moldings from the machine and spraying release agent on the mold halves before starting a machine cycle • During automatic injection cycle, operator trims feet (15 s) and feeds re-grind & virgin material into machine hopper (10 s) IENG 471 Facilities Planning

  4. Ideal Machine Assignment • Neglects idle time: • Where: • a = concurrent activity time (both op & mach tied up) • b = independent operator activity time • t = independent machine activity time IENG 471 Facilities Planning

  5. Cycle Time: • Cycle time (Tc): • Where: • a = concurrent activity time (both op & mach tied up) • b = independent operator activity time • t = independent machine activity time • m = number of identical machines assigned to op. • n’ = ideal number of identical machines assigned to op. IENG 471 Facilities Planning

  6. Idle Machine Time: • Idle time for machine (Im): • Where: • a = concurrent activity time (both op & mach tied up) • b = independent operator activity time • t = independent machine activity time • m = number of identical machines assigned to op. • n’ = ideal number of identical machines assigned to op. IENG 471 Facilities Planning

  7. Idle Operator Time: • Idle time for operator (Io): • Where: • a = concurrent activity time (both op & mach tied up) • b = independent operator activity time • t = independent machine activity time • m = number of identical machines assigned to op. • n’ = ideal number of identical machines assigned to op. IENG 471 Facilities Planning

  8. Total Cost per Unit: • Based on assigning m machines per operator, total cost (TC(m)) is: • Where: • Co = cost per operator-hour • Cm = cost per machine-hour • a = concurrent activity time (both operator & machine tied up) • b = independent operator activity time • t = independent machine activity time • m = number of identical machines assigned to operator • n’ = ideal number of identical machines assigned to operator Add this to the material cost total from the BOM! IENG 471 Facilities Planning

  9. Idle & Costing Example (cont.) • Assume t = 35s • Case A: Operator is assigned 1 machine • Case B: Operator is assigned 2 machines • Case C: Operator is assigned 1.3 machines IENG 471 Facilities Planning

  10. Neglecting idle time: Where: a = 5s (load/unload) b = 15s (trimming) + 10s (feeding) = 25s t = 40s (cycle time) – 5s (load/unload) = 35s Example: Ideal Machine Assign. IENG 471 Facilities Planning

  11. Cycle Time: 1 Machine/Operator • Cycle time (Tc): • Where: • a = 5s • b = 25s • t = 35s • m = 1 • n’ = 1.3 M#1 IENG 471 Facilities Planning

  12. Cycle Time: 2 Machines/Operator • Cycle time (Tc): • Where: • a = 5s • b = 25s • t = 35s • m = 2 • n’ = 1.3 M#1 M#2 IENG 471 Facilities Planning

  13. Cycle Time: 1.3 Machines/Operator • Cycle time (Tc): • Where: • a = 5s • b = 25s • t = 35s • m = 1.3 • n’ = 1.3 4 machines 3 operators = 1.3 M#1 M#2 M#4 M#3 IENG 471 Facilities Planning

  14. Idle Machine Time: 1 Mach/Op • Idle time for machine (Im): • Where: • a = 5s • b = 25s • t = 35s • m = 1 • n’ = 1.3 I’m faster than one machine, so the machine is always busy! M#1 M#1 IENG 471 Facilities Planning

  15. Idle Machine Time: 2 Mach/Op • Idle time for machine (Im): • Where: • a = 5s • b = 25s • t = 35s • m = 2 • n’ = 1.3 M#1 I’m slower than two machines, so now I’m always busy! M#2 IENG 471 Facilities Planning

  16. Idle Machine Time: 1.3 Mach/Op • Idle time for machine (Im): • Where: • a = 5s • b = 25s • t = 35s • m = 1 • n’ = 1.3 4 machines 3 operators = 1.3 M#1 M#2 M#4 M#3 3 of us are just as fast as 4 machines, so everything is always busy! IENG 471 Facilities Planning

  17. Idle & Costing Example (cont.) • Assume the Following Costs: • Operator Wage = $15/hr • Operator Overhead = 40% • Electricity Cost/Machine = $6/hr • Maintenance Cost/Machine = $1/hr • Computing the Cost per Unit Components: • Co = Cost per Operator-Hour: $15/hr + (.40)($15/hr) = $21/hr • Cm = Cost per Machine-Hour: $6/hr + $1/hr = $7/hr IENG 471 Facilities Planning

  18. Total Cost per Unit: • Based on assigning 1 machine per operator: • Where: • Co = cost per operator-hour • Cm = cost per machine-hour IENG 471 Facilities Planning

  19. Total Cost per Unit: • Based on assigning 2 machines per operator: • Where: • Co = cost per operator-hour • Cm = cost per machine-hour IENG 471 Facilities Planning

  20. Total Cost per Unit: • Based on assigning 1.3 machines per operator: • Where: • Co = cost per operator-hour • Cm = cost per machine-hour IENG 471 Facilities Planning

More Related