First Unitarian Universalist Church of San Diego

First Unitarian Universalist Church of San Diego. Campus Renovation Project Construction Budget Options. January, 2011. Campus Renovation Project.

vita
Download Presentation

First Unitarian Universalist Church of San Diego

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. First Unitarian Universalist Church of San Diego Campus Renovation Project Construction Budget Options January, 2011

  2. Campus Renovation Project • The Board of Trustees of First U.U. Church has called a special congregational meeting on Sunday, January 30, 2011 at 1:00 p.m. in the Meeting House to vote on a $5.39 million budget for the Campus Renovation Project that includes the replacement of Bard Hall • This slide show presents the three budget options that were considered.

  3. Project History 2005: Campus Renewal Team convened to improve Bard Hall 2006: Remodel of existing Bard Hall is planned 2007: Design is rejected as not visionary 2007: Master plan confirms need for additional meeting and office space

  4. Project History, cont. 2007: A design that incorporates all our dreams is rejected as too expensive Dec. 2008: Congregation approves a budget of $4.3 million for a less expansive design • $2.8 million raised; a $1.5 million loan is pursued • Design is expected to meet budget under best case scenario

  5. Recent History Sept. 2009-Jan. 2011—Delays in city planning and additional requirements incurred 2010: Unanticipated soft cost increases and driveway requirements added Nov. 2010: Bid reveals the building that will meet our needs will cost in excess of $5 million

  6. Recent Developments • $2 million loan has been secured at 5.3% • A Development Permit hearing is scheduled for January 26th, 2011 • Building permits should be secured by early March, 2011

  7. Main Reasons for Cost Overruns • Additional permitting requirements: $100,000 • Additional time securing permits: $100,000 • Additional driveway requirements: $250,000

  8. What Are We Paying For?

  9. Next Step • Consider a larger budget, because: -- More funds are available and affordable -- Our new building should provide the additional space and durability we need

  10. Options The Campus Project Oversight Team recommends the consideration of three budget options: • The Entire Project: $5.62 million • The Modified Project: $5.39 million • The Minimal Project: $4.82 million All three options involve the same external structure

  11. Architect’s Rendering Looking southwest from sidewalk

  12. Side-by-Side Comparison

  13. Side-by-Side Comparison FUNDING

  14. The Entire Project • This option includes all the construction that the congregation has authorized. • This is the submitted project and the building permit should be issued by early March. • It is possible to scale back these plans without additional City approvals, as detailed in the Modified Project.

  15. The Entire Project Overview • Expanded restrooms • New kitchen • Campus-wide landscaping with native plants • Accessible path through campus • Additional meeting spaces • Additional office spaces • Completely usable upper floor • Ecologically responsible • Durable materials • Stairs from UCSD sidewalk to driveway • Memorial Garden and Memorial Wall expansion • New Furniture

  16. The Entire Project Details • The Entire Project includes a large meeting hall, additional restrooms, a new kitchen and a second story with meeting rooms, offices and an outdoor meeting area. • A main component of the landscaping is a “green screen,” or trellis that will support deciduous plants that will give us shade in the summer and allow the sun to warm the walls in the winter. • The proposed landscaping includes blooming shrubs and trees that are native to California.

  17. The Entire Project Requirements • In order to construct the Entire Project at a cost of $5.62 million, an additional $820,000 in gifts will be needed by July, 2011.

  18. The Modified Plan • By delaying the construction of the Memorial Garden, it is possible to reduce the budget of the project to $5.39 million. • All other features of the Entire Plan are included in this plan, with the exception of new furniture.

  19. The Modified Project Overview • Expanded restrooms • New kitchen • New landscaping • Accessible path through campus • Additional meeting spaces • Additional office space • Completely usable upper floor • Ecologically responsible • Durable Materials • Stairs from UCSD sidewalk to driveway

  20. The Modified Project Details • In order to construct the Memorial Garden in the future, additional funds will have to be raised. • Additional start-up costs and likely material and labor price increases will inflate the price to construct the Garden at a later time.

  21. The Modified Project Requirements • In order to construct the Modified Project at a cost of $5.39 million, an additional $590,000 in gifts and/or short-term loans will be needed by January, 2012. • These loans could take the form of Bonds held by members of the congregation, and/or a bridge loan from a financial institution.

  22. The Minimal Project • The Minimal Project has a budget of $4.82 million, the amount of funding that is currently available to the church.

  23. The Minimal Project Overview • Expanded restrooms • New kitchen • New landscaping • Accessible path through campus • Unusable upper floor • Potential for additional meeting spaces • Potential for additional office space • Sacrificed durability • Sacrificed appearance

  24. The Minimal Project Details • At this budget level, it would not be possible to construct the Memorial Garden, the stairway to the sidewalk, or the green screen trellis. • In addition, less expensive, and less durable materials would be used, such as carpet instead of a highly durable concrete floor, and shingles instead of a metal roof. • While some of these items could be added later, when more money becomes available, other items are integral to the construction, and can’t be changed without major intrusion into the building.

  25. The Minimal Project Requirements • The Minimal Project can be built at a cost of $4.82 million, the amount currently available • In the future, additional funds will be needed to complete the second story, furnish the kitchen, purchase furniture and construct the stairway to UCSD and the Memorial Garden.

  26. The Campus Project Oversight Team and the Finance Committee recommend the Modified Plan, because it provides a fully usable building without incurring an excessive amount of additional debt.

  27. The agenda item for the special congregational meeting is the following recommended resolution: “Be it resolved that the Congregation of First U.U. Church of San Diego approves a five million, three hundred ninety thousand dollar ($5,390,000) budget on the Bard Hall construction project, and authorizes combined funding of congregational gifts, loans and/or bank bridge loans of additional debt not to exceed six hundred thousand dollars ($600,000).”

  28. Please vote: • At the special Congregational Meeting January 30th, • Or by absentee ballot, available from the church office starting January 26th