Requirements of AIC J. Zmeskal Stefan-Meyer-Institut für subatomare Physik Vienna, Austria for the Antiproton Ion Collider Collaboration. AIC concept. Measurement of neutron and proton distribution of stable and unstable nuclei, with a new novel method:
E N D
Requirements of AIC J. Zmeskal Stefan-Meyer-Institut für subatomare Physik Vienna, Austria for the Antiproton Ion Collider Collaboration GSI, Dec.3, 2007 PBAR @ FAIR Workshop
AIC concept • Measurement of neutron and proton distribution of stable and unstable nuclei, • with a new novel method: • medium energy antiproton absorption • in a collider mode. This method will allow an independent measurement of proton and neutron radii within the same experiment. GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Collection and deceleration of Antiprotons in CR/RESR • Antiprotons collected in CR: ~ 109 • Stochastic and electron cooling • in RESR form 3 GeV down to 30 MeV • Extraction of antiprotons into E(A)R, • new beam transfer line GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Collection and deceleration of Antiprotons RESR Former ESR e-cooler from production targets CR to NESR/E(A)R GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Antiproton beam parameters • injected antiprotons into CR/RESR: • energy 3 GeV • transvers emittance 5 mm.mrad • momentum spread p ~10-3 • after decelerating and cooling in RESR: • energy 30 MeV • transvers emittance < 2 mm.mrad • momentum spread p ~5.10-5 GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Time evolution of the longitudinal momentum spread of the antiproton beam in the RESR (for 30 MeV pbars) GSI, Dec.3, 2007 PBAR @ FAIR Workshop
GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Antiproton Ion Collider to FLAIR Space for 70 kV electron cooler E(A)R from RESR antiproton transfer line NESR GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Operational sequences Prepare facility for pbar production (5 min) Acceleration of Primary Beam Production and Separation of Secondary Beam Cooling and Accumulation Deceleration in RESR Transfer to E(A)R Prepare facility for RIB production (5 min) Acceleration of Primary Beam Production and Separation of Secondary Beam Cooling and Deceleration Accumulation in NESR Perform AIC Experiment GSI, Dec.3, 2007 PBAR @ FAIR Workshop
COLLIDER Ion optical layout of E(A)R and injection line for AIC Ion optical layout of the interaction region for AIC Beam dynamics simulations Study of Antideuteron production and storage Work packages (I) GSI, Dec.3, 2007 PBAR @ FAIR Workshop
New design reports by BINP in 2006/7 Conceptual Design of the Electron-Nucleus and Antiproton-Nucleus Scattering Facility for FAIR project. I.A.Koop, P.V.Logatchov, A.V.Otboev, V.V.Parkhomchuk,V.M.Pavlov, E.A.Perevedentsev, D.N.Shatilov, P.Yu.Shatunov, Yu.M.Shatunov, A.N.Skrinsky, A.A.Valishev. Budker Institue of Nuclear Physics, Novosibirsk, Russia. 2006 The revision of the Interaction Point region in NESR and EAR Petr Shatunov BINP, Novosibirsk, July 2007 Further BINP studies planned for 2007/2008
SCHOTTKY Development of new fast Schottky detection method to follow uncooled ions and use their cooling behavior to extract momentum information Design and prototyping of LN2 cooled pickups, multiple pickups, high. frequency pickups Development of new data analyis methods and DAQ Work Packages (II) GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Work Packages (III) • DETECTORS • Extensive simulations of reaction dynamics • Design and prototyping of luminosity detectors • Design and prototyping of recoil detectors • Design and prototyping of pion detectors GSI, Dec.3, 2007 PBAR @ FAIR Workshop
Support of Design work by BINP through GSI TU Munich and SMI Vienna Towards technical layout of the EAR and interaction zone DFG application for theoretical investigations (H. Lenske, Giessen) and simulations (R. Krücken, TUM): Antiproton-Nucleon and Antiproton-Nucleus interaction in free space and in the nuclear medium Event-generator and full scale experiment simulation Next steps GSI, Dec.3, 2007 PBAR @ FAIR Workshop
AIC - Requirments • beam time per year: 2-3 weeks • Antiprotons for AIC: • number of stored pbars at E(A)R: 109 • filling cycle of E(A)R: 3-5 per day • Antiproton beam parameters: • final momentum spread: 5.10-5 • final transverse beam emittance: < 0.02 mm mrad GSI, Dec.3, 2007 PBAR @ FAIR Workshop
THANKS GSI, Dec.3, 2007 PBAR @ FAIR Workshop
GSI, Dec.3, 2007 PBAR @ FAIR Workshop
pbars to CR RIB to CR E(A)R CR/RESR NESR GSI, Dec.3, 2007 PBAR @ FAIR Workshop