1 / 39

Accotink Creek Longitudinal Peaked Stone Toe Protection (LPSTP) Project Description

Detailed step-by-step construction process of the LPSTP along Accotink Creek at Fort Belvoir, Fairfax, VA in 2008, with live willow poles, siltation, Bendway Weirs, and erosion control blankets. Includes drawings by Dave Derrick.

vwheeler
Download Presentation

Accotink Creek Longitudinal Peaked Stone Toe Protection (LPSTP) Project Description

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ACCOTINK CREEK @ AIRFIELD RUNWAY & RECHLORINATION PLANT PROJECTS GARRISON FORT BELVOIR, FAIRFAX, VACONSTRUCTED Dec 2-5, 2008

  2. LONGITUDINAL PEAKED STONE TOE PROTECTION (LPSTP)Built with Virginia DOT Class II stone, level-crested @ 3 ft above the base-flow water surface elevation & trenched 3 ft into the bed. One row of live willow poles (3 poles/ft) planted in the LPSTP & another row (3/ft) laid on top of LPSTP (termed Live Siltation).

  3. STEP-BY STEPS FOR ACCOTINK CREEK, FT. BELVOIR, VA Toe-down Enhanced LPSTP All drawings by Dave Derrick

  4. ACCOTINK CREEK, FT. BELVOIR, VA LOOKING UPSTREAM Typical cross-section for Accotink Creek in the proposed project area

  5. ACCOTINK CREEK, FT. BELVOIR, VA Dig toe-down section of LPSTP 3 ft below bed of stream

  6. ACCOTINK CREEK, FT. BELVOIR, VA Place Longitudinal Peaked Stone Toe Protection (LPSTP) stone in trench

  7. 3 ft deep trench dug, tracked backhoe placing 150-500 lb stone CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  8. Looking across. Backfilling eroded bank with suitable soil & placing stone as LPSTP. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  9. Looking across @ close up of LPSTP stone. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  10. ACCOTINK CREEK, FT. BELVOIR, VA Place Joint Planting (live willow poles) on top of stone (angled up at least 20 degrees) at the rate of 3 poles per lineal foot.

  11. Looking across @ willow poles on stone. Placing soil on poles. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  12. ACCOTINK CREEK, FT. BELVOIR, VA Complete installation of the LPSTP stone

  13. Placing stone on the row of live willow poles (joint plantings) CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  14. ACCOTINK CREEK, FT. BELVOIR, VA Place Live Siltation (willow poles) on top of stone at the rate of 3 poles per lineal foot

  15. Looking US. LPSTP with joint plantings & Live Siltation in place CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  16. Looking US @ completed LPSTP & poles & dug trench (beyond) CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  17. Looking US. LPSTP has been soil-choked. Unfinished LPSTP in background, live poles not installed yet. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  18. ACCOTINK CREEK, FT. BELVOIR, VA At 35 ft spacing intervals, stone Bendway Weirs will be installed that will move the thalweg away from the toe of the LPSTP.

  19. LPSTP with Joint Pole Plantings & Live Siltation with an Erosion Control Blanket

  20. ACCOTINK CREEK, FT. BELVOIR, VA Tuck the Erosion Control Blanket (ECB) at base of slope. Roll ECB out over willows & LPSTP stone. The ECB used here is a 100% coir (Coconut fiber) Rolanka BioD-Mat 40

  21. 100% coir (coconut fiber) Erosion Control Blankets. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  22. Looking US @ erosion control blankets with soil covering the bottom end CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  23. Looking US @ LPSTP, poles, & ECB ready to be rolled up-slope. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  24. Install Living Dikes midway between mid-project keys, 3 deep-planted Live Willow Poles per ft.

  25. Hoe starting to dig trench for Living Dike (perpendicular to direction of high flow) CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  26. Looking downhill @ Living Dike trench with willows installed & partially backfilled. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  27. Looking downhill @ Living Dike trench with willows installed & partially backfilled. Leave bank rough. Ready for ECB. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  28. ACCOTINK CREEK, FT. BELVOIR, VA Slope bank. A balanced cut/fill in some sections, heavily eroded areas required soil backfill. Backfill anchors the ECB. CUT FILL

  29. ACCOTINK CREEK, FT. BELVOIR, VA Seed all disturbed areas Thalweg will form off the stream ends of the Bendway Weirs

  30. ACCOTINK CREEK, FT. BELVOIR, VA Roll ECB up sloped bank, stretch tight, & key in at top of bank

  31. Looking uphill @ sloped bank with Living Dikes left & right. CONSTRUCTION-ACCOTINK CR.-RUNWAY & RECHLOR- DERRICK 12-08

  32. Looking US @ LPSTP, sloped bank Living Dikes & ECB. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  33. Looking US @ graded & grass seeded bank. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION- DERRICK 12-2008

  34. Looking US @ coir blanket & Bendway Weirs in place. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  35. ACCOTINK CREEK, FT. BELVOIR, VA Install rooted stock plants through ECB as appropriate

  36. Looking US @ workers installing rooted plants thru ECB. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  37. Looking US @ coir blanket, Living Dikes & rooted plants. CONSTRUCTION-ACCOTINK CR.-RECHLORINATION - DERRICK 12-2008

  38. CONSTRUCTION COMPLETE-Looking US nine months after completion. Most willows browsed by beaver CONSTRUCTION COMPLETE-ACCOTINK CR.-DERRICK 9-13-2009

  39. Man’s best friend, Cleophus Speed Elvis Derrick

More Related