Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32. Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32. Applied water pressure: day 1 to day 2: 0,1MPa day 3: 0,3MPa day 4 to day 7: 0,7MPa.
E N D
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32 • Applied water pressure: • day 1 to day 2: 0,1MPa • day 3: 0,3MPa • day 4 to day 7: 0,7MPa
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32 - 1 week after start of water pressure
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32 - 2 weeks after start of water pressure
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32 - 3 weeks after start of water pressure
Testing of water penetration under pressure – NBR 10.787/94 (April 2007) Cement: CPII-E 32 - 4 weeks after start of water pressure