1 / 14

Tuesday 8.6.

Tuesday 8.6. Morning: Finishing BI intensity studies BPM versus beam intensity: orbit reading stable from 10 11 to 3 10 10 . BCT studies with up to 4 nominal bunches  4 10 11 . PLL studies with high intensities. First beam image for Beam 2 V and H from BGI .

wells
Download Presentation

Tuesday 8.6.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tuesday 8.6. • Morning: Finishing BI intensity studies • BPM versus beam intensity: orbit reading stable from 1011 to 3 1010. • BCT studies with up to 4 nominal bunches  4 1011. • PLL studies with high intensities. • First beam image for Beam 2 V and H from BGI. • 11:00: Hump studies. • Measuring the beam spectra as function of beam screen cooling (triplet L1 off; triplet R1 off; XL2 off; XR2 off; XL1 off; XL5 off; XR5 off; XL8 off; XR8 off) No obvious differences observed. • 13:00: Preparing for access. • Noisy nQPS board in A21L1 requires replacement. • Noisy reading of temperature at current lead of DFBX.R8 – RD1. • QPS card for RCBXH1.R2 requires replacement. • BLM card change and update of logger and concentrator 8:30 meeting

  2. Tuesday 8.6. • Orbit versus beam intensity: 8:30 meeting

  3. Tuesday 8.6. • BCT for high beam intensities: 8:30 meeting

  4. Tuesday 8.6. • Beam spectra with and without beam screen cooling in triplet IR1: 8:30 meeting

  5. Tuesday 8.6. • First image from BGI monitor for Beam 2: pressure 1e-8, intensity 2e11 8:30 meeting

  6. Tuesday 8.06 • Access issues: • Elevator at PM65 is. After talking with the DSO, it is OK to close the machine and pre-cycle/run. However not access possible to S56 (from Pt 5) or S67 (from Pt 7) until the elevator is fixed. • A large number of circuits (~30) failed the QPS soft reset in S12 • Performed some collimator checks parallel to pre-cycle: sensor readings for the minimum gaps were checked. No indication of a large scale error in collimator gap and position monitoring was found (was triggered by yesterday’s TCP/TDI measurements). • 19:00: Access finished and starting Damper studies • Completed the setting-up of the damper beam position modules for high intensity 1x1011. • High intensity check of the calibration only done in vertical plane for Beam 2: (Beam loss at the end of the shift due to the switching of BPM intensities for B1 while a nominal bunch was in B2). • tested new firmware for multi-bunch operation 8:30 meeting

  7. Tuesday 08.06 • 00:00 : Injection/dump protection studies • Local aperture scan at the BPM.31L5.B1: +14.5 mm. • Repeated yesterday's TDI beam size measurement with two different angles:With an angle of +/-1 mrad anti-parallel for both jaws the beam size and centre up and downstream was measured for different n-sigma settings of the TCP. • In the case of +1 mrad angles the centers are slightly different (150 mm) and the beam size is increased while for the -1 mrad case the measured centers remain and beam size remain unchanged. • 04:00 : Starting RF bunch length studies • Can not change the Beam Mode: stayed with "injection physics beam". • 04:49: Starting the ramp. • 05:08: starting longitudinal emittance blow-up. 8:30 meeting

  8. Tuesday 8.06 • V aperture in Q31L5.B1 (large local shift of orbit , ~2.5 mm, after recovering BPM following last tech stop) – OK now ! 8:30 meeting

  9. Tuesday 8.6. • Longitudinal beam size during ramp: The emittance was blown-up by a factor ~2 from 0.32eVs initial. 8:30 meeting

  10. Tuesday 8.6. • Very clean ramp: no beam losses. 8:30 meeting

  11. Tuesday 8.6. • Left beams at flat top to look at bunch length evolution. 8:30 meeting

  12. Tuesday 8.6. • Longitudinal emittance blow-up at flat top. 8:30 meeting

  13. Wednesday 09.06 • Program for today: • finish Longitudinal blow-up studies during ramp • Transfer line and injection checks • damper studies 8:30 meeting

  14. Wednesday 9.06 • Open Issues. • Elevator at PM65 is. After talking with the DSO, it is OK to close the machine and pre-cycle/run. However not access possible to S56 (from Pt 5) or S67 (from Pt 7) until the elevator is fixed. • A large number of circuits (~30) failed the QPS soft reset in S12 • ELQA needed on one V tap for current lead of RQS.A12.B2 (lost redundancy). • Multiplier tube for abort gap monitor of Beam 1 requires replacement  requires access (but not before the end of the week). • Sector 78 still requires final tests for validation of 10 A/sec ramp rate requires 1-2 h pre-warning and ca. 1 hour without beam). 8:30 meeting

More Related