1 / 16

Public Meeting Agenda

Public Meeting Agenda. PUBLIC MEETING Welcome & introductions Presentation Questions of clarification Open discussion Summary & closure.

wes
Download Presentation

Public Meeting Agenda

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Public Meeting Agenda • PUBLIC MEETING • Welcome & introductions • Presentation • Questions of clarification • Open discussion • Summary & closure

  2. Public Meeting:Environmental Impact Assessment (EIA) for the Proposed Upgrade of the Transnet Railway Line between Hotazel, the Port of Ngqura and Port Elizabeth Place: Date: Time: Presented by ERM Southern Africa

  3. Outline of the Presentation • Purpose of the public meeting • Project background & motivation • Project description • EIA process • Potential issues and opportunities • Specialist studies • Way forward

  4. Purpose of the Public Meeting • Public participation is an essential part of the EIA process. • The public meeting is one of numerous opportunities for stakeholders to become involved in the EIA. • We are here to share information about the project. • We would like to hear your views and concerns.

  5. Project Background: ERM’s Involvement • Appointed to conduct a High Level Screening Study – Feb 2008 • Screened for ‘Key Risks’ • Identified issues that would require further study/ investigation during the EIA incl. • Ecology • Traffic • Land issues • Stakeholder engagement • Appointed to undertake EIA in April 2008 – broader project scope Old station building at Golden Valley, Eastern Cape, Feb. 2008

  6. Project Background: Project Team Transnet Freight Rail ex Spoornet Transnet Capital Projects Port of Ngqura Development R&H Railway Consultants Railway Engineers HMGJV Project consultants/engineers ERM Environmental Consultants Specialist Specialist Specialist

  7. Manganese trains Container trains Project Background: Motivation Gauteng • Demand for increased container traffic capacity to service the new container terminal, Port of Ngqura – operational in 3rd quarter of 2009 • Global increase in demand for manganese ore Hotazel De Aar Port of Port Elizabeth (current) Port of Ngqura (future)

  8. Project Description: The Loops Upgrade & construction of 29 Loops (25 existing; 4 new) – 23 in E. Cape, 6 in N. Cape In the figure, No. 1 represents the main railway track and No. 2 represents the passing loop.

  9. Project Description: Additional Infrastructure • Upgrade of 5 yards – Beaconsfield &, Ronaldsvlei (both near Kimberley), Postmasburg, Mamathwane & Hotazel • New Traction Substation at Emil • Refurbishment of an existing second line between Kimberley and De Aar • Existing and new borrow pits Existing loop at Barkly Bridge, Eastern Cape, Feb. 2008

  10. Project Description: Construction Phase Activities • 8 Labour camps (typically 50mX 50m in size and fenced) • Addo, Kommadagga, Visrivier, Rosmead, Hanover Road, Kimberley, Posmasburg & Hotazel • Water - sourced locally or trucked in. Boreholes may be drilled • Electricity - will be provided by mobile generator • Site equipment – front-end loader, bulldozer, flat bed lorry, concrete mixer, drills, etc. • With approval from DEAT, construction expected to begin around Aug. 2009) • Jobs during construction (per 6 – 9 loop sites): • Skilled labour = ~75 people (sourced nationally) • Unskilled labour = ~100 people (sourced locally)

  11. EIA Process: Regulatory Requirements • Primary Listed Activity: 1(s) of R387 - construction of railway lines and associated infrastructure • Other listed activities related to construction of roads, establishment/ use of borrow pits, fuel storage, etc • Other permit requirements – borrow pits (DME) & water abstraction (DWAF) • Agreement has been reached with DEAT that two (2) applications be submitted to allow the most urgent components of this project to be expedited.

  12. EIA Process: Flow Diagram Key milestone dates: Draft Scoping Report out for public comment – earlyOctober ’08 Final Scoping Report submitted to DEAT – mid November ’08 Draft Environmental Impact Report compiled – January ‘09 we are here

  13. Potential Issues & Opportunities to Date

  14. The Specialists • Noise – Jongens Keet Associates • Vibration – Department of Mechanical and Aeronautical Engineering , University of Pretoria • Archaeology/Cultural Heritage – Archaic Heritage Project Management • Air quality – uMoya-NILU Consulting (Pty) Ltd • Traffic – ITS Engineers • Ecology – Natural Scientific Services

  15. Way Forward • Next steps in the EIA process: • Gather all public comments for input into the Draft Scoping Report by 19 September 2008 • Record of public meetings to be distributed to all Interested and Affected Parties by 12 September 2008 • Anticipated start date for the Impact Assessment Phase -January 2009 • The final Environmental Impact Report would be submitted to DEAT for approval by endApril 2009

  16. Contact Information • Sekena Masoet ERM Southern Africa (Pty) Ltd Silverwood House, Block A, Steenberg Office Park, Steenberg, 7945 Tel: 021-702 9100 Fax: 021-701 7900 Email: Sekena.Masoet@erm.com Web address: www.erm.com/transneteia

More Related