Primary School Expansion. Cranmer Primary School Wednesday 20 October 2010. Process for Cranmer. Bulge classes” in 2010/11 & 2011/12 a school admissions decision Specific planning application for temporary buildings
E N D
Primary School Expansion Cranmer Primary School Wednesday 20 October 2010
Process for Cranmer • Bulge classes” in 2010/11 & 2011/12 a school admissions decision • Specific planning application for temporary buildings • Expansion from 2012/13 = “Significant enlargement” requires a statutory process • Separate major planning application required
Births: 360 of 807 rise – 447 to go!
Expansion Programme 21 FE total - 630 extra reception places in 6 years)
Reception year expansions 2008 to 2010 and 2011 to 2012 for consultation
Key criteria in expansion decisions • Educational standards • Parental preference • Location and issues of pupil transport (home to school) • Physical constraints of existing school sites • School sustainability • Value for money
Next steps for Cranmer • Vision for school to inform building brief • Building feasibility study • Capital funding decisions in early 2011 • Statutory consultation on permanent build • Permanent building by September 2013