160 likes | 174 Views
Case study Kromhout Barracks. Maarten Groothuis. The Kromhout Barracks challenge. Army Command Headquarters and other MoD units Location Utrecht Offices for 2000 employees (+ option for extra 1000) 90 hotel rooms, sport facilities, etc. Services: maintenance,
E N D
Case studyKromhout Barracks Maarten Groothuis
The Kromhout Barracks challenge • Army Command Headquarters and other MoD units • Location Utrecht • Offices for 2000 employees (+ option for extra 1000) • 90 hotel rooms, sport facilities, etc. • Services: maintenance, catering, security, facility management, etc.
Ambitions for the project • MoD wants to focus on its core tasks • Benefiting contractor’s specialised knowledge and experience • Higher quality (“one stop shopping”), lower costs
Approach • Pilot project for PPP in Defence • DBFMO for 25 years • European tender procedure: • Competitive dialogue • Maximum bid price • Economically most advantageous tender (EMAT) • Financial scope • DCF 335 million € • PPP savings exceed 15% • MoD is and will be owner • Performance-related availability fee
Preparations Selection Procurement guidelines Dialogue Public Sector Comparator Final tender DBFMO Contract Contract close Output Specification Building Operation Process Winter 2005 - Summer 2006
Preparations Selection Dialogue Final tender Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006
Preparations Selection Phase 1 (5 participants) Dialogue Phase 2 (3 participants) Final tender Phase 3 (3 participants) Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006 2007
Preparations Selection Dialogue Final tender Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006 2007 Final bid: 11 January 2008 Preferred bidder: 2 April
Preparations Selection Dialogue Final tender Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006 2007 Final bid: 11 January 2008 Preferred bidder: 2 April Summer 2008
Preparations Selection Dialogue Final tender Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006 2007 Final bid: 11 January 2008 Preferred bidder: 2 April Summer 2008 2008 - 2010
Preparations Selection Dialogue Final tender Contract close Building Operation Process Winter 2005 - Summer 2006 Autumn 2006 2007 Final bid: 11 January 2008 Preferred bidder: 2 April Summer 2008 2008 - 2010 2010 - 2035
Preferred bidder ‘Komfort’ 'AMB Kromhout' (Macquarie Bank, BAM, Arcadis, GTI, Unica and Kraaijvanger Urbis) 'Integra Partners Kromhout' (Heijmans, NIBC Infrastructure, Burgers Ergon, Facilicom, Quadrat and Broekbakema) 'Komfort' (Ballast Nedam, Strukton and John Laing, in cooperation with Meyer en Van Schooten Architecten, Karres en Brands Landschapsarchitecten and ISS Nederland BV. 12 12
Design 13 13
Impression 14 14