CDF Silicon Workshop 2006. 12 th May 2006. New BLM & BLM electronics. Jose E. Garcia, Jennifer Gimmell, Ulrich Husemann. Outline. New BLM System Motivation (why do we need an upgrade) Characteristics (electronics, …) Current Status Installation plans

wilmerv
Download Presentation

CDF Silicon Workshop 2006

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CDF Silicon Workshop 2006 12th May 2006 New BLM & BLM electronics Jose E. Garcia, Jennifer Gimmell, Ulrich Husemann

  2. Outline • New BLM System • Motivation (why do we need an upgrade) • Characteristics (electronics, …) • Current Status • Installation plans • Commissioning Plans (software, firmware, ACNET interface) • Summary • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 2

  3. Motivation • Tevatron project to improve ABORT system Prevent against this Long reaction time • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 3

  4. Motivation • CDF BLM Upgrade • Add more information to the old system which is working reliably • Use same well-understood type of detectors with enhanced capabilities (new electronics) • Maybe an intermediate step towards a diamond-based beam abort system • Goals: • Shutdown:install new BLMs and all cables • After shutdown:commissioning • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 4

  5. System Overview • Integrate BLM current and digitize at Tevatron turn frequency (every 21 s) • Form three running sums for additional integration periods • Programmable time constants • One abort threshold per integration period of each channel • Possibility to change abort thresholds and masks in response to machine status • Read-out using VME system and Ethernet • VME CPU can be used for system computations • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 5

  6. System Characteristics BLM Electronics High Voltage Power Supply Timing Card Synchronous integration clock digitizers BLM BLM Digitizer Card 4 Channels with integrator and ADC FPGA Compares readings and sums to programmed thresholds - i.e. 1ms, 10ms, 1s VME / ACNET BLM Abort Card FPGA info from digitizers compared with abort masks and produce abort signals BLM Controller Card Interface to VME crate • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 6

  7. Current Status • Picked up 5 new BLMs from Marv Olson of AD Instrumentation Department (4 to be installed, 1 spare) • BLMs are tested by AD, gain: 10 C/Gy • Old fixtures removed from collision hall • New fixtures finished in April 2006: add-on to old fixtures • Cables ready for the installation BLM BLMs • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 7

  8. Installation Plans Shutdown project Richard Tesarek • Sharing crate with diamonds (first-floor counting room 1RR04D) • Installation of new BLM System • BLMs and cables set-up New Modules already requested • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 8

  9. Commissioning Plans • Initial phase of testing correct read-out – immediately after installation • Check that the dose rate and integrated dose agree for old and new system. • Set up the abort logic of the new system such that the limit is reached during a regular store. Check if the radiation levels for an abort agree –immediately after accelerator start-up • Run the system with same limits and for an abort. Check if both systems have fired and compare their FIFO contents. • Keep new BLM as back-up system up to reliability is completely proved – depending on how much chances do we have to test it • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 9

  10. Before Commissioning Some infrastructure is needed : • Establish a integration of radiation (1 minute, full store) out of the built-in rolling sums • ACNET Controls for BLMs • Adapt actual settings in ACNET (E2 page) for new BLMs (next week) • Use similar set-up: • Global reset • Current rate and integrated dose • FIFO controls • Paul Derwent will help us in the integration Use New Java Front-End • Development of mechanisms for abort acknowledgment - equivalent to current Kludge card. • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 10

  11. Summary • We will have our slot in the following weeks • Material and BLMs are ready for installation • Commissioning • Read-out system: VME modules and ACNET controls will be set-up during next week • Prepare system for radiation level tests at the beam startup • New system working as backup for a test period Unfortunately, I was not able to join you there. Finally after some troubles I have my visa. Enjoy the weekend!!! • J.E.Garcia – CDF Silicon Workshop – Santa Barbara 11

  12. CDF Silicon Workshop 2006 12th May 2006 Additional Slides