1 / 44

Slide-in of I-75 Bridge over US-6

Slide-in of I-75 Bridge over US-6. Tim Keller, PE, Ohio DOT Bob Beasley, PE, ARCADIS US, Inc. AGENDA. Tim Accelerated Bridge Construction (ABC) in Ohio Bob Project Description ABC Approach for I-75 over US-6 Bridge and ABC Details Construction. Accelerated Bridge Construction in Ohio.

winter-wise
Download Presentation

Slide-in of I-75 Bridge over US-6

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Slide-in of I-75 Bridge over US-6 Tim Keller, PE, Ohio DOT Bob Beasley, PE, ARCADIS US, Inc.

  2. AGENDA • Tim • Accelerated Bridge Construction (ABC) in Ohio • Bob • Project Description • ABC Approach for I-75 over US-6 • Bridge and ABC Details • Construction

  3. Accelerated Bridge Construction in Ohio • ABC is not a new concept in Ohio. • How long will it take to build this bridge? • How much disruption to traffic? • Years, Months, Weeks, Days

  4. Accelerated Bridge Construction in Ohio • Why Slide-in construction? • NOT New. • Why Pilot Program? • Why I-75 over US-6? • Public Outreach

  5. Project Description • Location • Timeline • Structure Type • Project Changes

  6. Location Insert Location Map

  7. Timeline • Programmatic Selection - September 2011 • Structure Type Study Approved – November 2012 • Use Accelerated Bridge Construction – December 2012 • Incorporate Project into 3rd Land Widening Project – February 2013 • Revised Structure Type Study Approved – March 2013 • Final Plan Package Submitted – December 2013 • Project Awarded – May 2014 • Bridge Slide – June 2015

  8. Structure Type • Existing Twin Structures: • 4-Span Rolled Steel Beam & Concrete Deck • Spill-through Stub Abutment on H-piles • Cap & Column Piers on Spread Footings • Proposed Structures: • 2-99’ Span Prestressed Concrete I-beam & Concrete Deck • Widen Roadway from 41’-4” to 60’-0” • Stub Abutment on H-piles behind MSE Wall • Cap & Column Pier on H-piles

  9. Project Changes • Profile Adjustment to Facilitate Bridge Slide • Revise I-75 profile to match existing • Lower US-6 profile to provide vertical clearance • Maintenance of Traffic for Bridge Closure • Contraflow and use of ramp

  10. ABC Approach for I-75 over US-6 • ABC Homework • Attend FHWA ABC Workshops • General Approach to Slide-in

  11. ABC Homework • How to slide: • Push, pull • Sliding surface – PTFE, rollers, etc. • Similar projects: • Iowa’s DOT SR 92 over small stream • 120’ Single Span Precast I-Beams • Slid on PTFE coated elastomeric bearings • Utah DOT I-80 over Echo Dam road • 78’ Single Span Precast I-Beams • Slid on PTFE coated elastomeric bearings • Superstructure supported on temporary steel bents • Approach Slabs moved with superstructure • FHWA: • Website • Webinars • Workshops

  12. Attend FHWA ABC Workshops • Utah: I-84 over Echo Frontage Road • Single span precast box beams & no approach slab • August, 2013 • Bridge Slide • Pulled using 2 cranes with cable placed through diaphragm • Slid on PTFE coated elastomeric bearings

  13. Attend FHWA ABC Workshops • Utah: I-84 over Echo Frontage Road

  14. Attend FHWA ABC Workshops • Utah: I-84 over Echo Frontage Road • Lessons Learned • Pulling with cranes • Tension in cable difficult to control • Sliding force is variable at each end • Bridge tended to “rack” • Sliding on PTFE coated elastomeric bearings • Bearings are very “slippery” • Did not take much force to move bridge • Kinetic friction much less than static friction • “Racking” of bridge difficult to control

  15. Attend FHWA ABC Workshops • New York: I-84 over Dingle Ridge Road • Single span precast double tee NEXT beams & precast approach slab • October, 2013 • Bridge Slide • Pushed with hydraulic ram on steel guide rail • Slid on PTFE coated elastomeric bearings

  16. Attend FHWA ABC Workshops • New York: I-84 over Dingle Ridge Road

  17. Attend FHWA ABC Workshops • New York: I-84 over Dingle Ridge Road • Lesson Learned • Sliding on PTFE coated elastomeric bearings • Rain during move increases coefficient of friction • Measure movements during slide to control racking • Pushing with hydraulic ram effective way to slide • Construction of temporary supports most time consuming portion of building bridge

  18. General Approach to Slide-inTraffic on Existing Bridge

  19. General Approach to Slide-inTraffic on Existing Bridge

  20. General Approach to Slide-inTraffic on Existing Bridge

  21. General Approach to Slide-inTraffic on Existing Bridge

  22. General Approach to Slide-inWeekend Closure

  23. General Approach to Slide-inWeekend Closure

  24. General Approach to Slide-inWeekend Closure

  25. General Approach to Slide-inWeekend Closure

  26. General Approach to Slide-inWeekend Closure

  27. General Approach to Slide-inTraffic on New Bridge

  28. Bridge and ABC Details • Abutment & Approach Slab • Pier • Superstructure & Approach Slab • Slide-in Restrictions/Liberties

  29. Abutment & Approach Slab Before Closure

  30. Abutment & Approach Slab During Closure

  31. Pier • Proposed pier in same location as existing • Temporary support required • Load rating of existing beams with new span arrangement • Seismic pedestal • Pedestal conflicts with bridge slide • Cheekwall designed as seismic pedestal

  32. Pier

  33. Pier

  34. Superstructure & Approach Slab

  35. Superstructure & Approach Slab

  36. Superstructure & Approach Slab Call out sliding plate

  37. Superstructure & Approach Slab

  38. Slide-in Restrictions/Liberties • How to move bridge • Slide Only

  39. Slide-in Restrictions/Liberties • Temporary supports

  40. Slide-in Restrictions/Liberties • Geometry Control • Limit translation: • 1” between supports • 2” between abutments

  41. Slide-in Restrictions/Liberties • Test Move

  42. Slide-in Restrictions/Liberties • Schedule

  43. Construction • I-75 3rd Lane Widening - $71,178,816 • I-75 Bridges over US-6: $7,790,879 (includes MSE Walls) • Slide Cost: $2,000,000 (25.7%) • Temporary Support of Existing Bridge: $450,000 (5.8%) • 3rd Lane Project Schedule • Summer 2014 to Summer 2016 • Slide-in Schedule • Early Summer 2015

  44. Questions?

More Related