New Rules on Legionella Prevention. N. Bangert TS Workshop 2005, Archamps. Table of Contents. Diseases caused by Legionella Living environment / Installations with risk Cooling towers at CERN Analysis and limits Preventive chemical treatment Corrective chemical treatment

wray
Download Presentation

New Rules on Legionella Prevention

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Rules on Legionella Prevention N. Bangert TS Workshop 2005, Archamps

  2. Table of Contents • Diseases caused by Legionella • Living environment / Installations with risk • Cooling towers at CERN • Analysis and limits • Preventive chemical treatment • Corrective chemical treatment • Annual preventive maintenance • Personnel protection • Conception and Follow up of Cooling Towers • Conclusions

  3. Diseases caused by Legionella = Legionellosis • Pontiac Fever • Flue-like illness (fever and muscle aches) • Incubation time: few hours to 3 days • Legionnaires’ Disease • Pneumonia (collapse of respiratory function) • Incubation time: up to 10 days • Mortality rate 5% to 30%

  4. Living Environment Warm stagnant water

  5. Installations with risks Showers Whirlpool spas Cooling towers Evaporative condensers

  6. Cooling Towers at CERN 23 Power: 1.25 MW to 70 MW Volume: 5 m3 to 4000 m3

  7. LHC and SPS Cooling Towers Cooling Tower

  8. Cooling Towers at the Meyrin Site Cooling Tower French / Swiss Border

  9. Analysis and Limits Frequency now on a monthly basis (In the past 2-4 times per year) Stop, disinfection, cleaning, purge Stop 100 000 UFC/l Corrective chemical treatment 1 000 UFC/l Preventive chemical treatment 0 UFC/l

  10. Preventive Chemical Treatment • Continuous treatment • Anti-scaling reduces formation of bio-films • Weekly treatment • Biocide targeted on general bio-contamination (algae, fungi, bacteria)

  11. Corrective Chemical Treatment • Amount of chemical depending on level of contamination and volume of circuit • Bio detergent detaches slime off the surfaces • Bactericide targets Legionella bacteria Slime Surface

  12. Annual Preventive Maintenance • Mechanical cleaning • Basins, structures, … • Disinfection of circuit • Similar to corrective chemical treatment • Purge of circuit • not always practicable • time consuming

  13. Personnel Protection • All personnel performing work in or close to cooling towers need to be properly trained regarding risks • Respiratory protective equipment need to be carried in case of exposure to aerosols or in cooling towers • Zones to be signaled

  14. Conception and Follow up of Cooling Towers • Free of dead end pipes • Drop separators installed • Good quality of supply water (Problems: SPS, STP18) • Accessibility for inspection and cleaning given • Technical documentation up to date • Installation logbook put in place • Follow up of water consumption and purges Methodical Risk Analysis

  15. Conclusion I: In Place • Respect of frequencies and type of analyses (100%) • Preventive and corrective chemical treatment defined (and applied if necessary) (100%) • Annual preventive maintenance (70%) • Completion and review of existing procedures about preventive and corrective activities (60%)

  16. Conclusion II: To-Do-List • Carry out a methodical risk analysis on all cooling tower circuits • Put warning signs in place • Implementation of a cooling tower Logbook • Training of personnel intervening on and operating the cooling towers • Update of hydraulic plans • …

  17. Conclusion III: Evaluation • Hydraulic disconnection of north area cooling towers to SPS ring • Hydraulic disconnection of STP18 from SPS • Put purge counters in place Budget evaluation / Schedule : ?

  18. Questions ?