THEMIS-SCM. SCM SCHEDULE. The CETP maintains a dedicated Schedule for SCM (MS-Project) the most important activities and dates are reported in the Themis Schedule Very simple for the moment, it shall be completed and improved
E N D
THEMIS-SCM SCM SCHEDULE The CETP maintains a dedicated Schedule for SCM (MS-Project) the most important activities and dates are reported in the Themis Schedule Very simple for the moment, it shall be completed and improved The main sub-contractor, 3D+, also maintains an internal Schedule the delivery date of the cubes to CETP is an entry for the SCM Schedule The other sub-contractors are less critical and no formal schedule is requested for teir activities – just the delivery dates Bertrand delaPorte THM-SCM-PDR – 2003.10.10
THEMIS-SCM SCM SCHEDULE The milestones for SCM are the delivery dates to UCB According to the current schedule: EM delivery to UCB : 16-Apr-04 - no difficulty expected FM-1 30-Jul-04 - very difficult for the PA FM-2+3 24-Sep-04 - very tight for the PA FM-4+5 19-Nov-04 - no difficulty expected FM-6 14-Jan-05 No difficulty is expected for any SC Because there is a screening at the end, all FM cubes (for all Models), will be delivered at the same date – according to the contract: 01-Aug-2004 Bertrand delaPorte THM-SCM-PDR – 2003.10.10
THEMIS-SCM 26-Jan-04 3D+ date 31-Jan-04 EM to UCB 16-Apr-04 PA /EM manufacturing & delivery Bertrand delaPorte THM-SCM-PDR – 2003.10.10
THEMIS-SCM 31-May-04 3D+ date 01-Aug-04 FM-1 to UCB 30-Jul-04 26-Jul-04 FM-2, 3 to UCB 24-Sep-04 PA /FM-1,2,3 manufacturing & delivery Bertrand delaPorte THM-SCM-PDR – 2003.10.10
THEMIS-SCM SCM SCHEDULE - CONCLUSION Real difficulty to delivery the PA /FM1 at the date currently specified Various solutions can be envisaged with UCB or with 3D+ to avoid any impact on the Integration Schedule of the Project All other Models can be delivered in time Bertrand delaPorte THM-SCM-PDR – 2003.10.10