2. . 1. Why Use Net present value (NPV) NPV = PV (cash inflow) PV (cash outflow)Example: ABC Inc. is considering a riskless project. Initial cash outflow is $100, and ABC Inc. receive $110 one year later. The interest rate is 6% p.a.Solution: NPV = -100 110/1.06 = $3.77.NPV Rule: