260 likes | 378 Views
East Hope VFD Butler Station. Construction General Contractor: East Hope VFD Framing Contractor: Brent Lockwood & Norm Sommerfeld 2003. Conceptual Plan Architect : Fran Schuck Rendering: Ed Butler. Fire Station Lot 05/31/03. Clearing 06/07/03 Work Donated by Leonard Butler Jr.
E N D
East Hope VFDButler Station Construction General Contractor: East Hope VFD Framing Contractor: Brent Lockwood & Norm Sommerfeld 2003
Pouring Footings 08/22/03Brent Lockwood, Norm Sommerfeld & Volunteers
Constructing Forms 08/18/03Brent Lockwood, Norm Sommerfeld & Volunteers
Foundation Forms 08/24/03Brent Lockwood, Norm Sommerfeld & Volunteers
Pouring Slab 09/05/03Craig Comstock, Todd Woods & Volunteers
Wall Raising 09/10/03Brent Lockwood, Norm Sommerfeld & Volunteers
Wall Raising 09/10/03Brent Lockwood, Norm Sommerfeld & Volunteers
Trusses 09/26/03Brent Lockwood, Norm Sommerfeld & Bob Cordes