As-built 09 April 2008

As-built 09 April 2008. RIGHT NOW, the Cuore experimental area is under construction. Many construction details are still being designed, Including clean room and Radon mitigation strategies.

xenon
Download Presentation

As-built 09 April 2008

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. As-built 09 April 2008 RIGHT NOW, the Cuore experimental area is under construction. Many construction details are still being designed, Including clean room and Radon mitigation strategies. Timing may well limit the options being considered for the installation of a Radon barrier and clean room modificatios. Cuoreconcrete support structure with jack screws in place Cuore site with elevator deck ready for installation Robin Lafever CUORE Structure assembly sequence

  2. Build-up sequence Superimposing the CAD model illustrates how the build-up sequence (TBD) may influence the choices for an appropriate Radon barrier because of access and installation constraints Support structure with major structural elements in place, including the elevator deck Robin Lafever CUORE Structure assembly sequence

  3. Build-up sequence The current clean room geometry is shown here as an ‘ideal’ layout with no interfering structure around it. Assuming a Radon barrier is applied to the outer surfaces of the clean room, this is the time to do it. However, this is not a real possibility. Therefore, we must consider methods for installing a barrier before the clean room construction. Or, modifying the clean room panels such that they ARE the Radon barrier. Robin Lafever CUORE Structure assembly sequence

  4. Build-up sequence The electronics bay currently has no requirement for either particle count or Radon exclusion, but, further restrict access to the clean room roof. Robin Lafever CUORE Structure assembly sequence

  5. Build-up sequence Continued Hut carpentry will probably precede clean room installation, But access to the clean room exterior is clearly restricted Robin Lafever CUORE Structure assembly sequence

  6. Build-up sequence Continued At this point, the only options for installing a Radon barrier will be limited to the INSIDE surfaces of the clean room. Robin Lafever CUORE Structure assembly sequence