The realities of a Project-Specific PMO

The realities of a Project-Specific PMO. Microsoft Project User Group Quarterly Meeting September 22 nd 2004 Celine Gullace, PMP. The Project. The client is a large university, with over 40,000 students.

yael
Download Presentation

The realities of a Project-Specific PMO

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The realities of a Project-Specific PMO Microsoft Project User Group Quarterly Meeting September 22nd 2004 Celine Gullace, PMP MPUG 9/22/04 Presentation

  2. The Project • The client is a large university, with over 40,000 students. • The project is a PeopleSoft Financials integration/implementation for the University, the Medical Center, and the Research Foundation (2,000 end users). The project will cost about $30M, and will span about 2.5 years. • The Project Team has 270 team members (about 200 at one time). MPUG 9/22/04 Presentation

  3. The Project (cont.) MPUG 9/22/04 Presentation

  4. What kind of Project Office (POF)? • Clerical or strategic? • Directors struggled with the POF mandate. • PM goals, tool (MS Project 2000/Project Central), some basic methodology. • Immediate needs for assistance with technical support, planning, and plan maintenance. • Pre-conceptions & different skills. MPUG 9/22/04 Presentation

  5. What kind of POF? (cont.) • The “Big 5” type? • Manager assistant/delegate • Knows & participate in day to day business. • Minimal PM tool work. • …Or… The “Tool Type” • More clerical/junior • Minimal business interaction • Makes beautiful plans! MPUG 9/22/04 Presentation

  6. What kind of POF? (cont.) • Getting buy-in from the managers • Balancing management and project management • Showing added value • Go the extra mile • …and respect! • Being a MS Project Guru doesn’t mean you’re useless at everything else • Importance of hiring properly MPUG 9/22/04 Presentation

  7. What kind of POF? (cont.) • An ultimate wish: Communication Czar • Lessons learned from Project Director • Be able to fill-in for the manager you are paired with • Know the business inside out • Maintain good plans (good knowledge of the tool) • Report good data • Be the main information repository for the project MPUG 9/22/04 Presentation

  8. What kind of POF? (cont.) • POF Staff duties: • Pair up with a manager (e.g. GL/Budgets) and assist with planning in MS Project • Maintain the plan when the phase is underway (track actuals, push/delete un-used work, re-level weekly) • Issues analysis: anticipate delays, over-allocations, propose solutions • Reporting on late tasks, actual vs. baseline work, budget tracking • Keep the technical architecture and the methodology sound and consistent • Write users manuals, train new users MPUG 9/22/04 Presentation

  9. Technical Architecture for the Plans • Plan shells for every team: • For each team, one plan per phase • Standard sub-phases: Plan, Execute, Control, Close • Track tasks and “buckets” (e.g. meetings) • Sharing data using a database MPUG 9/22/04 Presentation

  10. Technical Architecture (cont.) • Consistency across plans: • To report on the same type of data across all plans • Each task has to be “tagged” with codes. MPUG 9/22/04 Presentation

  11. Technical Architecture (cont.) • Weekly EAC variance by work category • Phase status MPUG 9/22/04 Presentation

  12. New team, new skills • Minimal MS Project training • No formal Project Management training (e.g. PMI) except for a few directors • Relies exclusively on Excel • Distrust of MS Project • Very little time for sound planning and scheduling • Hired for their technical expertise, asked to make room for sound project management MPUG 9/22/04 Presentation

  13. Learning from experience • Level of detail • In the beginning, very detailed + low tool maturity= discontent (back to Excel? Buckets?) • Eventually reached a balance • Interdependencies • Eventually a balance was reached: critical links remained, the rest of the tasks were Start-constrained • Planning for the next phase • To be completed under pressure while trying to close the current phase on time – a real challenge. MPUG 9/22/04 Presentation

  14. Learning from experience • Meta plan: a more high-level view, focused on critical interdependencies. • Tracking “Give/Gets” between plans. MPUG 9/22/04 Presentation

  15. Learning from experience • “The tool broke my plan” • “My Excel spreadsheet tells me I’m OK” • Reporting: too much or too little? • QA of data: too much or too little? MPUG 9/22/04 Presentation

  16. Anticipating issues • Using the project plan… (The work is planned for the next couple weeks only) • …and by being the eyes and ears of the Manager • Know the business • Attend meetings • Understand the issues Low High MPUG 9/22/04 Presentation

  17. Lessons Learned • Be prepared for the POF role to evolve • Support of the Project Management tools, while asking all parties to reach common ground. • Anticipate staffing issues, bottlenecks and critical dependencies with strong plans • The team acquires Project Management skills for a lifetime (and think they had them all along) • Strong sponsorship & flexibility are critical • Get buy-in for good plan maintenance • Conduct Lessons Learned after each phase (also a good way for the POF be recognized) MPUG 9/22/04 Presentation

  18. MPUG 9/22/04 Presentation

  19. MPUG 9/22/04 Presentation

  20. Questions? Thank you MPUG 9/22/04 Presentation