Current Status (I), 23 July 2003. Manufacture & Assembly 2 PCBs back from manufacture at Express Circuits & now being assembled at Cemgraft Mechanical parts Brass PCB supports (in manufacture) Perspex cover for AOH (needs minor modification to drawings). Front panel (in design).

yeva
Download Presentation

Current Status (I), 23 July 2003

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Current Status (I), 23 July 2003 • Manufacture & Assembly • 2 PCBs back from manufacture at Express Circuits & now being assembled at Cemgraft • Mechanical parts • Brass PCB supports (in manufacture) • Perspex cover for AOH (needs minor modification to drawings). • Front panel (in design). • Brass/Perspex AOH support (in manufacture). • VHDL • Almost complete. Still to do: Error diagnostics, TTC & BC0 check • ModelSim simulation (include both FPGAs, VME master & I2C slaves) • FE: DACs, X-Switch, QPLLs & Master/Slave Control • BE: VME, Temp Control (I2C & PID), AOH (I2C) • Synthesised FE @ 120MHz & BE @ 40MHz. PROM files made. 96 Chann FED Tester Status : Greg Iles

  2. C++ Code (James Leaver) HAL object: Allows you to read/write to registers HAL application: Higher level operations XDAQ application: Needed to talk to FED (Started, but not yet finished) JTAG Almost complete. For JTAG experts: JTN & DIF generated. NIF & GEN almost done Misc Still not received AOHs.... When ? Fibre Viewer: Not clear to me if we need male (~£800) or male/female (~£2000) MPO viewer or neither. Crate being assembled by Costas & Osman. Linux 7.2.1 & XDAQ being installed today. SBS PCI-VME card on order. Current Status (II), 23 July 2003 96 Chann FED Tester Status : Greg Iles

  3. FED Tester PCB Analogue Optical Hybrids (AOHs) BE FPGA VME, Temp Control (I2C & PID) APV Frame generation, DACs, X-Switch, QPLLs Opto-Connectors DACs Clk & Control Power Fibre reels Cross-point switches 96 Chann FED Tester Status : Greg Iles

  4. Faults 1 schematic and 1 layout fault found. Can be rectified on prototype. Schedule Test prototype in August. I have only 13 working days so we may venture into September Manufacture 4 or 5 further boards in September. Manufacture 2 weeks Assembly 2 weeks Have full 96 channel system by the end of October. Mistakes & Schedule 96 Chann FED Tester Status : Greg Iles