1 / 14

Challenges in Digital Controller Upgrade at OPG

2. Agenda. ObjectivesIdentified IssuesResolutionsChallengesSummaryQ/A. 3. Background. OPG - Three Nuclear Generation Stations Pickering A

york
Download Presentation

Challenges in Digital Controller Upgrade at OPG

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. 1 Challenges in Digital Controller Upgrade at OPG Chunlei Zhao, David Beattie, Brian Babcock Computers and Control Design Dept. OPG

    2. 2 Agenda Objectives Identified Issues Resolutions Challenges Summary Q/A

    3. 3 Background OPG - Three Nuclear Generation Stations Pickering A – 60s, Pickering B –70s, Darlington – 80s Hybrid Control in MCR Analog Controllers - Obsolete

    4. 4 Power-up Configuration

    5. 5 Power Interruption

    6. 6 Display Failure

    7. 7 Memory & Performance

    8. 8 Human Factor Issues

    9. 9 Software QA, Testing & Training

    10. 10 Summary Performance differences between digital replacements and the analog devices Identified Issues: Power-up configuration Power interruption requirement Display failure Memory size Human Factor Issues Software QA Extensive testing and training required

    11. 11 Q/A Thank You!

    12. 12

    13. 13 Integrated Test Configuration

    14. 14