1 / 19

Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer

Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer. LHC Stage 1: Planning. LHCC – 1 July, 2008. Milestones End CE works: December 2010 Installation: 2011 Linac commissioning: 2012 Modifications PSB: shut-down 2012/13 (6 months)

yoshe
Download Presentation

Santa Cruz Meeting August 12 th 2008 Layout options & Schedule Issues David Lissauer

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Santa Cruz Meeting August 12th 2008 Layout options & Schedule Issues David Lissauer David Lissuaer, Santa Cruz Meeting.

  2. LHC Stage 1: Planning LHCC – 1 July, 2008 • Milestones • End CE works: December 2010 • Installation: 2011 • Linac commissioning: 2012 • Modifications PSB: shut-down 2012/13 (6 months) • Beam from PSB: 1rst of May 2013 David Lissauer, Santa Cruz Meeting.

  3. Stage 2: Planning Construction of LP-SPL and PS2 will not interfere with the regular operation of Linac4 + PSB for physics. Similarly, beam commissioning of LP-SPL and PS2 will take place without interference with physics. • Milestones • Project proposal: June 2011 • Project start: January 2012 • LP-SPL commissioning: mid-2015 • PS2 commissioning: mid-2016 • SPS commissioning: May 2017 • Beam for physics: July 2017 LHCC – 1 July, 2008 David Lissuaer, Santa Cruz Meeting. 3

  4. Luminocity expectations Note: Predicted integrated Luminosity Lower than assumed. Collimation Linac4 + IR upgrade phase 1 New injectors + IR upgrade phase 2 Radiation damage limit ??? David Lissuaer, Santa Cruz Meeting.

  5. Peak luminosity… New injectors + IR upgrade phase 2 Early operation Linac4 + IR upgrade phase 1 Collimation phase 2 David Lissuaer, Santa Cruz Meeting.

  6. Integrated luminosity… New injectors + IR upgrade phase 2 Linac4 + IR upgrade phase 1 Early operation Collimation phase 2 David Lissuaer, Santa Cruz Meeting.

  7. Layout (4+3+2) Fixed Length Barrel 4 Pixel Layers: 1(2) b-layers “easily replaceable” inside a support tube. 3(2) Layers incorporated in the Fixed length Barrel. Mechanical Support: Off the tube? Off the Barrel 3 Pixel Discs on the outside. Internal Discs? David Lissuaer, Santa Cruz Meeting.

  8. Layout Overview Barrel Length: 240 Cm (Full length) 12 sensors/side. Discs: 5 Discs / Side. Need optimization. David Lissuaer, Santa Cruz Meeting.

  9. Layout Overview (4+3+2) Fixed Length. David Lissuaer, Santa Cruz Meeting.

  10. Solution with better coverage but more complicated from an Engineering point of view and more massive. - Need optimization. Disc Layout is still uncertain. We need to converge on a “baseline” by the time of the Nikhef meeting. David Lissuaer, Santa Cruz Meeting.

  11. Eng. Layout Studies Eng. Studies of the Layout. Global Support Tube: David Lissauer, Santa Cruz Meeting. Pixel? – Very Short strips?

  12. Baseline Assembly Sequence • “Full” Assembly on the surface in “Global Tracker Tube” • Barrel SS/LS • Pixel outer Layers (2 or 3) • Pixel Discs + Pixel Tube • EC LS/SS + Pixel Tube • Full test on the surface prior to installation • Insertion from the side • ~ 6.5 Meter Long • ~1 meter Diameter • Borated Poly insertion & Services preparation on the Cryostat • Global Tube insertion from the side • Services connections David Lissuaer, Santa Cruz Meeting.

  13. ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR C.BAULT May 15th 2008 Barrel-LS Barrel-SS Pixel Pixel Services Outer cylinder Pixel discs 5-6 End_Cap nose Services INSERTION END-CAP NOSE + PIXEL DISCS 5-6 INTO OUTER CYLINDER

  14. ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR C.BAULT May 15th 2008 Barrel-LS Barrel-SS Pixel Pixel discs 5-6 Outer cylinder Services End_Cap nose END-CAP NOSE + PIXEL DISCS 5-6 INSTALLATION OF SERVICES

  15. ATLAS UPGRADEASSEMBLY SEQUENCE OF INNER DETECTOR C.BAULT May 15th 2008 Barrel-LS Barrel-SS Pixel Pixel discs Outer cylinder End_Cap nose End_Cap main bloc with services INSERTION MAIN BLOC OF END-CAP INTO OUTER CYLINDER

  16. Atlas IT envelope layout drawing 160 Pixel Electrical Connectors

  17. ATLAS Timeline. LHCC will ask experiments for: • LoI Letter of Intent – Mid 2009 • TP Technical Proposal - spring 2010 • TDR Technical Design report / Subsystem (do not have to be at the same time) • ID – Late 2010 (early 2011) • Calorimeters - Middle of 2011 • Muons - Middle / Late 2011 (Depend on upgrade scope) David Lissuaer, Santa Cruz Meeting.

  18. Schedule Overview (Preliminary) • Ready for beam December ‘17 • Tracker Installation February ‘17 • Tracker Ready for installation (Testing) July ‘16 • Barrel Installation in the Support Tube January ‘16 • EC Installation in the Support Tube April ‘16 • Stave installation start June ‘14 • Support Structure ready for installation January ‘14 • Start services installation • EC Stave Production starts June ’13 • Barrel Stave Assembly starts January ’13 • Readout Electronics and Stave components ready for assembly at this time. David Lissuaer, Santa Cruz Meeting.

  19. Conclusions • Little feedback from Simulation to date!! • We might not have significant feedback from physics analysis before final decisions will need to be made. • To stay on Schedule need to agree on a baseline (at least for the barrel) by the NIKEHF meeting. • Assembly on the surface has significant advantages. Might be the only solution that will allow installation of the detector in 18 month shut down. • Has serious schedule implications!!! • Detector needs to be ready ~12-18 month earlier. David Lissuaer, Santa Cruz Meeting.

More Related