PSC – 1 STAKEHOLDERS. BoARD BoWRD ARARI BoCP Woredas Communities Plus EPLAUA BoFED WAO others. PSC – 1 COMPONENTS/OUTPUTS. Knowledge and skills Schemes owned/managed Woreda integrated platform Strengthening institutions
E N D
PSC – 1STAKEHOLDERS BoARD BoWRD ARARI BoCP Woredas Communities Plus EPLAUA BoFED WAO others
PSC – 1COMPONENTS/OUTPUTS Knowledge and skills Schemes owned/managed Woreda integrated platform Strengthening institutions Sector coordination/cooperation WBS into 32 outputs conformed by 200+ activities Work and reporting based on RBM
PSC – 1IMPLEMENTATION PLAN/TEAM • Overall 6-yr plan and First year detailed plan Team CIDA ANRS 39 professional positions (23 Canadians) 20 support staff incl. drivers All Canadian positions filled 12 (80%of incl short-termer) local professional positions filled)
PSC – 1IMPLEMENTATION MILESTONES Jan 05: CEA Contract Feb Launching Late March Start Mobilization/installation April CCO May Training starts Early June Partner meeting, BoCP in; PMC meet start Sept Meeting of Committee; semiannual report Nov Field action starts in two woredas; subcommittees start Dec Core National Team in place; vehicles Jan-Feb06 Selection HH, irrigation, SWC;baselines
APPROACH • - CCO; CEA in Bureaux • - Resident field coordinators • - Partner and community involvement • - Committees and Subcommitees • - Selection criteria/ranking for field interventions • - Fora
PSC – 1PROGRESS Semiannual report to Sept reissued today (white cover) Overview of progress to January submitted (green cover): • *Changes in context • *Courses, documentation • *Comparison Planned vs Actual results • *Management, coordination • *Factors affecting performance and solutions • *Look ahead
PSC – 1LOOK at NOW and AHEAD F Consultants presentations for fresh look March mostly for planning for 2006-7 work Lessons and decisions taken into account Full involvement/integration of plans