Results of Münster-Meeting. 4 flanges on roof instead of 12 ( two 2 DN250, 2 DN100) Stiffeners can be placed on the roof Also variabel in amount and / or placement Rails have to be built on the roof for safe access to the flanges Top disk is flanged to roof
E N D
Resultsof Münster-Meeting 4 flanges on roofinsteadof 12 (two 2 DN250, 2 DN100) Stiffenerscanbeplacedontheroof Also variabel in amountand/orplacement Railshavetobebuilt on theroofforsafeaccesstotheflanges Top diskisflangedtoroof Diameter of top disk will bechangedto 2.75m; tokeepheighttheslopeofroof will beincreased Cryo-pipe isleadthrough wall ofwater-tank by a flange
More activities • TPC • Cryofor TPC • Outervessel • Accessories • Gassystem • Check Layout • Check alreadyboughtvalves • List oftobeorderedparts (MFC, etc.) • Place in lab? Accessories.