1 / 15

Getting Paid: On Time

Getting Paid: On Time. A Guide To Mechanics’ Lien and Bond Claims and The Prompt Payment Act. Speaker: Jim Sterr IDOT. Topics . Do Your Homework Lien and Bond Claims Liens Against Public Funds (770 ILCS 60/23c) Bond Claims (30 ILCS 550/0.01) Prompt Payment Act (30 ILCS 540/7).

zahur
Download Presentation

Getting Paid: On Time

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Getting Paid: On Time A Guide To Mechanics’ Lien and Bond Claims and The Prompt Payment Act Speaker: Jim Sterr IDOT

  2. Topics Do Your Homework Lien and Bond Claims Liens Against Public Funds (770 ILCS 60/23c) Bond Claims (30 ILCS 550/0.01) Prompt Payment Act (30 ILCS 540/7)

  3. Do Your Homework Properly identify the IDOT contract number and the contractor’s job or project number Have a written contract (with contractor) in place before you start work Stay current on submission of payrolls, material certifications, etc. and keep copies Befriend the resident engineer/technician – always remember your contract is with the prime contractor

  4. Topics Do Your Homework Lien and Bond Claims Liens Against Public Funds (770 ILCS 60/23c) Bond Claims (30 ILCS 550/0.01) Prompt Payment Act (30 ILCS 540/7)

  5. Lien and Bond Claims An unpaid Subcontractor or Supplier may file a claim against the bond and a lien against Layered protection Seek legal advice

  6. Topics • Do Your Homework • Lien and Bond Claims • Liens Against Public Funds (770 ILCS 60/23c) • Bond Claims (30 ILCS 550/0.01) • Prompt Payment Act (30 ILCS 540/7)

  7. A Notice of Claim for Lien on Public Funds: • Must contain a sworn statement and/or be notarized • Must identify the contract and specify the unpaid items and the dollar amount claimed for each • Must be served on the Secretary of Transportation, the Prime Contractor and Subcontractor (if applicable) by hand delivery or certified mail (with return receipt requested, delivery to addressee only) • Will cause the withholding of the claimed amount from the Prime Contractor for ninety (90) days, but does not force IDOT to pay the lien claimant

  8. Continued… • Liens against public funds apply only to monies that become due the contractor after the lien is filed • If you wait to file a lien until the contract is almost complete, there may be insufficient funds available to cover all liens • No contract retainage • Any funds available will be shared among all lien holders

  9. Continued… • Must file suit within ninety (90) days if not paid • Must provide copy of suit to Department within ten (10) days

  10. Topics • Do Your Homework • Lien and Bond Claims • Liens Against Public Funds (770 ILCS 60/23c) • Bond Claims (30 ILCS 550/0.01) • Prompt Payment Act (30 ILCS 540/7)

  11. A Bond Claim • The Public Construction Bond Act (30 ILCS 550/0.01 et. seq.) provides in part: “Every person furnishing materials or performing labor, either as an individual or as a subcontractor for any contractor… where bond shall be executed as provided in this Act, shall have the right to sue on such bond … for his use and benefit…”.

  12. A Bond Claim • Does not cause IDOT to withhold payment from the Contractor • Preserves claimant’s right to sue under bond • Must be filed within 180 days from the last date of furnishing work or materials on the job • Must be served in writing on the Secretary of Transportation, with copies to the Prime Contractor, Subcontractor and Bonding Company • May need to be followed up by a lawsuit

  13. Topics • Do Your Homework • Lien and Bond Claims • Liens Against Public Funds (770 ILCS 60/23c) • Bond Claims (30 ILCS 550/0.01) • Prompt Payment Act (30 ILCS 540/7)

  14. Prompt Payment Act • Contractor must pay subcontractor/suppliers within 15 days of receiving payment • Does not guarantee payment for rejected work or when payrolls and certifications have not been submitted • After 15 days- interest at 2% per month • Administrative hearing is an immediate option • Seek legal advice before seeking an administrative hearing

  15. The End

More Related