330 likes | 454 Views
SUCCESSFUL STRATEGIES FOR SCHEDULING PROJECTS TO FINISH ON TIME. Presented by Christopher J. Payne, PE, CCM McDonough Bolyard Peck. BACKDROP. Projects are frequently late Delays are contentious Schedules are contentious Not used properly Difficult to manage.
E N D
SUCCESSFUL STRATEGIESFOR SCHEDULING PROJECTS TO FINISH ON TIME Presented by Christopher J. Payne, PE, CCM McDonough Bolyard Peck
BACKDROP • Projects are frequently late • Delays are contentious • Schedules are contentious • Not used properly • Difficult to manage
WHAT WE ALL KNOW…or think we know • CPM is the best tool out there • Highly defined requirements will encourage contractor compliance • Schedules don’t build jobs, people do
So… How do we use the schedule successfully to ensure the project is completed on time?
AGENDA • Specifications • Building the Schedule • Partnering • Sub Buy-in • Cost Loading • Resource Loading • Updating the Schedule • Resolving Problems with the Schedule
BUILDING THE SCHEDULE UNLESS… • Specifications have too many rules WHAT WORKS • Clear Specifications
BUILDING THE SCHEDULE • Good • Activity Code Structure • Maximum durations • How time will be extended • Use for Payment • Bad • Minimum activity requirements • Numbering rules • Restrictions on relationships • Onerous reports
BUILDING THE SCHEDULE UNLESS… • People don’t partner WHAT WORKS • Partnering the Schedule
BUILDING THE SCHEDULE • Good • Jointly working on schedule • Making sure subs are present • Understanding philosophy of how job will be built • Making a complete schedule (all activities) • Bad • Dictatorial review comments • Contractor creating a submittal to fulfill a requirement • Pre-claim posturing • Mismatched subcontractor input
CHALLENGE • How to intelligently involve subs? • Subs not on board at beginning • G.C.’s practicing “mushroom” philosophy • G.C.’s running two schedules • One Solution… • Keep schedule on the table at all meetings with subs
BUILDING THE SCHEDULE UNLESS… • It becomes an unwieldy mess WHAT WORKS • Cost-loading the Schedule
BUILDING THE SCHEDULE CHALLENGE How do you get the Schedule of Values to agree with the CPM? • Build together • It takes work • Don’t duplicate work
BUILDING THE SCHEDULE UNLESS… • The purpose isn’t clear WHAT WORKS • Resource-loading the Schedule
BUILDING THE SCHEDULE • Good • Resource loading to identify manpower needs, smooth peaks, corroborate with bid • Bad • Hard to get real data • Is it necessary to update? • Sub reluctance • Use as a weapon
UPDATING THE SCHEDULE UNLESS… • Still waiting for/arguing over baseline • Schedule is unwieldy/lack of contractor help in updating WHAT WORKS • Update at the date of the pay requisition
STRATEGIES • Accurate Updates • Get into a rhythm • Have a substantive but informal review meeting • Agree on progress first, acknowledge status • Understand implications and deal with later • Two-part process
OBSERVATIONS • Delay is inevitable. • Disagreement is inevitable. • Communication and resolution are not inevitable.
RESOLVING PROBLEMS WITH THE SCHEDULE UNLESS… • Process gets behind • Process is unwieldy • Disagreement over impacts WHAT WORKS • Time Impact Analysis
TIME IMPACT ANALYSIS APPROACH • Develop fragnet of impact • Run schedule before impact • Run schedule with impact PITFALLS • Too many changes • Requires time to develop • How to address an ongoing change
TIME IMPACT PITFALLS – DISCUSSION • Can you agree on an impact without agreeing on entitlement? • Forward-looking mindset vs. backward-looking • Typical scenario may take 2-3 months to resolve…what to do about project in the meantime?
Owner worried about this… … …but not ready to agree on this … TYPICAL SCENARIO $ DELAY TIA 1 TIA 2 DD PROJECTION PLAN TIME
TIME IMPACT STRATEGIES • Acknowledge Delay Quickly • Do TIA’s but pick milestones to cut off analysis and assess globally • Tolerate negative float (for a while) • Continue to insist on performance • Allow (but discuss) minor logic changes
SAMPLE SITUATION Two-year project, $40 million • Baseline schedule submitted 4 weeks after NTP • Owner comments 7 weeks after NTP • Resubmit 10 weeks after NTP • Approval 12 weeks after NTP 1st update 14 weeks after NTP, shows project 6 weeks behind
SAMPLE SITUATION Contractor’s narrative: • We were delayed by bad weather, late approval of drilling plan, late availability of east access. • We anticipate recovering time by working six-day drilling schedule and in later work.
EXAMPLE What should Owner do? • Schedule unacceptable. All delays are contractor’s. Resubmit with recovery plan. • Acknowledge receipt of schedule, but do nothing else. • Dialogue, discussion, concession, analysis…
EXAMPLE Outcome No. 1: • Contractor disagrees, asserts right to file a claim, brings up constructive acceleration… • Schedule is now a “claims football”…but is no longer useful as a communication tool on the project.
EXAMPLE Outcome No. 2: • Contractor submits the next update, now nine weeks late. Cites more vague causes of delay… • Claims are brewing… • Job tracking late…
EXAMPLE Outcome No. 3: • Grant 5-day EOT for late pile approval. • Pay limited acceleration cost to overcome delay. • Cite lack of progress on other paths. • Job in good shape going forward.
SUMMARY • Schedule is a necessary tool too often overlooked. • Cost implications are huge. • Proper use of tool limits intimidation and ignorance.
SUMMARY Schedule should be a communication tool, not a communication barrier