Scheduling & Resource Planning . CTC-415. Schedule Compression. Used to decrease schedule time At what price? Does cost of compression outweigh liquidated damages or possible profit from next job started early What are costs? – extra crew, equipment Benefits – less equipment time on job

zeroun
Download Presentation

Scheduling & Resource Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Scheduling & Resource Planning CTC-415

  2. Schedule Compression • Used to decrease schedule time • At what price? • Does cost of compression outweigh liquidated damages or possible profit from next job started early • What are costs? – extra crew, equipment • Benefits – less equipment time on job • How do you reduce time? • Increase daily output on activity • Increases costs • Labor & Equipment

  3. How to Compress a Schedule • Look at critical path and determine activities which cost the least per day • Look for logic revisions which could shorten schedule • Make sure that revisions don’t cause increased costs • Painting and flooring can be done concurrently but at a loss of productivity • Keep activity relationships in mind

  4. How to Compress a Schedule • Activity Duration Reduction • Activities have a minimum duration • IF 2 painters can paint a room in 2 days – how long does it take 4 painters? , 8 painters, 16 painters • Setup times and cleanup times are always present • Results in increased costs • Must watch CP to make sure it does not shift

  5. Cost vs duration Linear relation – only true to a point Linear with break points Step function shows equip needs Parabolic costs increase as duration decreases

  6. Indirect costs change with project length • Shortened project reduces indirect costs • Lengthening projects increase in direct costs

  7. How to compress schedule • 1. Determine CP • 2. Look for cheapest activity on CP and reduce 1 day – check CP (any movement) • 3. Go to 2 • 4. If multiple CP then must cut activities on all CPs • 5. Total cost and days reduced

  8. Example cut 6 days

  9. Scheduling Decompression • May be able to increase duration of activity and decrease cost • Why? • Keep crew busy • ahead of schedule and payment • slow down to keep handle on $ • How? • Look at increasing duration by reducing crew