1 / 14

Time/Cost Trade-off Analysis

Time/Cost Trade-off Analysis. Kathy S. Schwaig. A Roadmap of the Project Planning Process. Develop project charter Establish work breakdown structure Analyze sequencing relationships Estimate “normal” activity durations Perform network calculations Validate/revise initial schedule

zev
Download Presentation

Time/Cost Trade-off Analysis

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Time/Cost Trade-off Analysis Kathy S. Schwaig

  2. A Roadmap of the Project Planning Process • Develop project charter • Establish work breakdown structure • Analyze sequencing relationships • Estimate “normal” activity durations • Perform network calculations • Validate/revise initial schedule • Perform time-cost tradeoff analysis • Load resources to activities • Resolve any resource/workload imbalances • Develop budget and cash flow plan based on analysis of direct and indirect costs

  3. Validating the Schedule • Once the project network has been drawn and analyzed, you should check to make sure the results make sense . . . this is called validation • Is the project duration reasonable? • Is the critical path where you would expect it to be? • Are you missing any activities? Or precedence relationships? • If you are using project management software, has the data been entered correctly?

  4. Revising the Schedule • The schedule may be revised for many reasons • To correct errors • To reflect changes in assumptions • To reflect reductions in project scope (i.e., elimination of activities) • To reflect changes in the project calendar • In response to changes in the approach taken to complete an activity • In response to changes in precedence relationships

  5. Time/Cost Trade-off Analysis • Time/cost trade-off analysis is the compression of the project schedule to achieve a more favorable outcome in terms of project duration, cost, and projected revenues • Objectives of time/cost trade-off analysis • Minimize total project costs • Compress project to an acceptable duration • Done by selectively crashing specific activities to shorten project duration

  6. Time/Cost Trade-off Analysis • You might think that total project costs will increase when we begin to crash activities • But, total project costs consist of both indirect (project-based) costs (PBC) and activity-based costs (ABC) • ABC goes up when we crash activities in an effort to finish the project early • But, PBC (the indirect costs) goes down if we finish the project early

  7. Which Activities are the Best Candidates for Crashing? • Any activity that is on the critical path • Activities with relatively long durations • Bottleneck activities (that appear on multiple critical paths) • Activities that relatively low cost to crash • Activities that are not likely to cause quality problems if crashed • Activities that occur relatively early in the schedule and are labor intensive

  8. Steps for Performing Time/Cost Trade-off Analysis • Estimate project-based (indirect) cost per unit time • Identify critical activities that are good candidates for crashing • Determine activity-based (direct) cost of crashing selected activities vs. indirect cost savings • Select activities to be crashed • Recalculate the forward pass and check for changes in critical path

  9. Potential Problems with Crashing • Reduced flexibility and less margin for errorincreased risk of failure to complete project on time • Raises potential for poor quality • Increases potential for staff burnout, stress, and turnover (from what Yourdon calls Death March projects) • Raises activity-based costs • May negatively affect other projects • Creates unrealistic expectations for future projects

  10. Crashing Example A N=7, $50,000 C=5, $62,000 B N=9, $80,000 C=6, $110,000 Start Finish C N=10, $40,000 C=9, $45,000 D N=8, $30,000 C=6, $42,000

  11. Crashing Example Cont’d • Costs to accelerate are: • Activity A, $6,000/wk • Activity B, $10,000/wk • Activity C, $5,000/wk • Activity D, $6,000/wk • Makes sense to crash only those activities on the critical path(s) with the lowest acceleration cost per time period

  12. Crashing Example Cont’d Step 1: Crash C by 1 week A N=7, $50,000 C=5, $62,000 B N=9, $80,000 C=6, $110,000 Start Finish C N=10, $40,000 C=9, $45,000 D N=8, $30,000 C=6, $42,000 Path C-D = 9 + 8 = 17

  13. Crashing Example Cont’d Step 1: Crash C by 1 week Step 2: Crash D by 1 week A N=7, $50,000 C=5, $62,000 B N=9, $80,000 C=6, $110,000 Start Finish C N=10, $40,000 C=9, $45,000 D N=8, $30,000 C=6, $42,000 Path C-D = 9 + 7 = 16

  14. Crashing Example Cont’d Step 1: Crash C by 1 week Step 2: Crash D by 1 week Step 3: Crash D by 1 week AND crash A by 1 week. Why? A N=7, $50,000 C=5, $62,000 B N=9, $80,000 C=6, $110,000 Start Finish C N=10, $40,000 C=9, $45,000 D N=8, $30,000 C=6, $42,000

More Related