1 / 12

Hall A 12 GeV DVCS Status report

Hall A 12 GeV DVCS Status report. December 16th 2013 Hall A collaboration meeting Alexandre Camsonne. Outline. Experiment presentation Calorimeter building status Electronics status Task list Man power Conclusion. Hall A 12 GeV DVCS experiment. DVCS gamma* + p -> gamma +p

zion
Download Presentation

Hall A 12 GeV DVCS Status report

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Hall A 12 GeV DVCS Status report December 16th 2013 Hall A collaboration meeting Alexandre Camsonne

  2. Outline Experiment presentation Calorimeter building status Electronics status Task list Man power Conclusion

  3. Hall A 12 GeV DVCS experiment DVCS gamma* + p -> gamma +p Electroproduction e+p -> e’+ gamma + p Use HRS to detect electron in DIS Use Lead fluoride calorimeter to detect the real photon Same setup as 6 GeV experiment

  4. Experimental setup

  5. E12-06-114: setup and tests at JLab • Photon arm in Test Lab • All cabling is done • PbF2 blocks are ready (PMTs are assembled and blocks wrapped) • (Almost) ready to pile up blocks and take cosmics

  6. Calorimeter progress • DVCS area in test lab • DVCS stand moved • Shelves installed • PMTs checked in France and sent back • All PbF2 blocks rewrapped and on site • Racks for DAQ and slow control • 2 HV crates, controls software working • Power, network installed • All RG58 cables tested and connected • HV cables connected

  7. Electronics progress • 1 VME64X crate with intel CPU in FPP rack • Readout and decoder using Intel CPU ( 90 MB/s per crate ) • Calorimeter trigger installed • Logic and readout on separate FPGA • larger bus for interFPGA transfer to not loose resolution on threshold • block transfer mode implemented but need to be debugged and tested • Review in March

  8. Task list - Timeline • Calorimeter • Stack calorimeter - 2 weeks - End Dec 2013 • Test cosmics - Jan 2014 to June 2014 • Test DC current ADC ( missing patch panel ) - 1 week • Layout RG213 install stand - 2 month • DVCS Electronics • Install 2nd and 3rd VME crate - 3 days - Jan 2014 • Test trigger Block Transfer ( Need engineer for debugging )2 weeks - February 2014 • Cable trigger - 3 days - January 2014 • Timing with HRS - 3 days -January 2014

  9. Task list - Timeline • DVCS electronics • Test high rates full setup - End Feb 2014 • Hall A standard equipment • HRS • High Resolution VME TDC - 2 weeks - Feb 14 • Scintillator timing - 1 week - Feb / Mar 14 • BCM -1 week - Jan 14 • BPM - 1 week - Jan 14 • Helicity - 1 week - Jan 14 • Polarimetry

  10. Man power • Orsay ( calo / soft ) • Carlos Munoz • Rafayel Paremuzyan • Camille Desnault • Ohio University ( DAQ / analysis ) • Julie Roche • Paul King • Norman Israel • Mongi Diamini • Old Dominion University(Calo / HRS ) • Charles Hyde • Hashir Rashad HRS • Stacey Allison • Kijun Park Calo / HV • Jefferson Laboratory • Alexandre Camsonne DAQ / Calo • Robert Michaels DAQ / BCM/BPM/ Helicity / HV • Clermont Ferrand • Magali Magne Electronics

  11. DVCS collaboration meeting 19-20 December 2013 Old Dominion University 4600 Elkhorn AveNorfolk VA 23529 Room: OCNPS/PSB 1100 https://www.jlab.org/indico/conferenceDisplay.py?confId=58

  12. Conclusion Calorimeter ready by the end of the year Electronics needs debugging and test high rates, ready by March 2014 for review Can test electronics when beam is here in March. No issues to be ready by summer 2014, should be ready by March in case beam is good.

More Related