An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12 GeV UpgradeProject Status Allison Lung Hall C Users Meeting Jefferson Lab January 18, 2008

  2. OUTLINE CD-2 Approval What does that mean? What is the project baseline? Path to CD-3 Update: Project Management staffing changes Update: Non-DOE Scope

  3. Upgrade magnets and power supplies CHL-2 12 6 GeV CEBAF 11 Two 0.6 GV linacs 1.1 Enhanced capabilities in existing Halls

  4. Hall C: SHMS and HMS

  5. WBS 1.6.3 Hall D Complex (New Construction) Facilities Mgt has begun tree-clearing and retention pond

  6. WBS 1.6.3 Hall D Complex (Rendering) Service Building Hall D Photon Beam Dump Cryo Plant Tagger Area Counting House N

  7. Path to CD-2 Approval November 9, 2007

  8. DOE Project Critical Decisions CD-0 Approve Mission Need CD-1 Approve Alternative Selection and Cost Range Permission to develop a Conceptual Design Report Defines a range of cost, scope, and schedule options CD-2 Approve Performance Baseline Fixes “baseline” for scope, cost, and schedule Now develop design to 100% Begin monthly Earned Value progress reporting to DOE Permission for DOE-NP to request construction funds CD-3 Approve Start of Construction CD-4 Approve Start of Operations or Project Close-out

  9. DOE CRITICAL DECISION SCHEDULE Now split in two to ease transition into operations phase Note → 6 to 18 months schedule float included (A) = Actual Approval Date

  10. 12 GeV Upgrade: Phases and Schedule (based on baseline funding guidance approved by DOE-NP in Nov 2007) • 2004-2005 Conceptual Design (CDR) - finished • 2004-2008 Research and Development (R&D) - ongoing • 2006 Advanced Conceptual Design (ACD) - finished • 2006-2009 Project Engineering & Design (PED) - ongoing

  11. 12 GeV Upgrade: Phases and Schedule • 2009-2013 Construction – starts in < 12 months! • Parasitic machine shutdown – May 2011 through Oct 2011 (6 months) • Accelerator shutdown start mid-May 2012 • Accelerator commissioning mid-May 2013 • Now-2012 Challenging balance act! • Expectation is to complete ~80% of approved 6 GeV program (Ops funding -limited) • Skill mix – lean (but improving) engineering and design manpower • 2013-2015 Pre-Ops (beam commissioning) • Hall A commissioning start ~October 2013 • Hall D commissioning start ~April 2014 • Halls B and C commissioning start ~October 2014

  12. 12 GeV UPGRADE SCHEDULE

  13. We are here  1 year Sept 2008 DOE Generic Project Timeline DOE CD-2 Reviews Nov 2007

  14. Path to CD-3 Goal - September 2008

  15. Path to CD-3 • Finish R&D • Hall B: pre-shower calorimeter (Jun 08) • Hall B: beamline design (Jul 08) • Hall B: FDC – mechanical (Sep 08) • Hall B: FDC – electrical (Sep 08) • Hall C: SHMS HB magnet (Apr 08 and Sep 08) • Hall D: barrel calorimeter fiber tests (Jun 08) • Hall D: tagger prototype (Jun 08) • Hall D: FADC prototype Master Trigger (Aug 08) • Hall D: auxiliary electronics prototype (Aug 08) • Hall D: FDC and CDC prototypes (Sep 08)

  16. Path to CD-3 • Nearly finish PED (tight schedule !!) • 100% design for all FY09 procurements • ~80% design for everything else • Design/safety reviews (~8 for Physics) • Complete Advance Procurement Plans • Major Milestones • OECM EVMS Contractor Certification Review (Jan 08) • Design Review of Superconducting Magnets (Apr 08) • Safety Assessment Document Complete (Jun 08) • Accelerator Safety Envelope Complete (Jun 08) • Design of Conventional Facilities Complete (Sep 08)

  17. Path to CD-3 • CD-3 Documents • Check-out, Testing and Commissioning Plan(May 08 draft) • 12 GeV Construction Project Safety and Health Plan (May 08) • CD-3 DOE Reviews • 2008 “Lehman” Independent Project Review (IPR) • CD-3 briefing package due to DOE-NP ~week of June 16th • IPR scheduled (tentatively) for July 22-24 CD-3 Approval meeting in late September 2008

  18. 12 GeV Project Management Staffing Updates

  19. 12 GeV Project Office Search Committee Formed; R. Ent chair C. Rode (Acting) J. Hogan M. Spata

  20. 12 GeV Integrated Project Team (IPT) Members PEP, Section 4.1 includes the description and charter of the IPT DOE-NP DOE-TJSO JSA-TJNAF

  21. Non-DOE Scope • Confirmed to date: • Foreign – donation of HERMES lead glass blocks for Hall C SHMS calorimeter • thanks to Armenia / Nikhef ! • NSF – MRI grant for Hall C detector systems approved June 2007 ; (W&M/HU/JMU/NCA&T) • strong collaboration of experienced Hall C Users • detector integration review scheduled for Jan 22, 2008 • Virginia – PED funds ($650K) FY06/07 ; • Construction funds ($500K) FY08

  22. Non-DOE Scope • Potential (proposals in development): • Foreign: • Hall B Central Detector EU proposal • Two NSERC requests (re Hall D BCal ; Hall C Cerenkov) • NSF MRI: • Hall B Preshower (OU/NSU/JMU) • Hall B Longitudinal Polarized Target (possible, non-12 GeV) ; (ODU/CNU) • Virginia – request for $9.5M Construction funds FY09-11; • Governor’s budget includes $7.5M in FY09-10 so far….

  23. 12 GeV Upgrade Summary • Construction start in < 12 months • Critical Decision 2 in November 2007 (baseline) • Critical Decision 3 in September 2008 (construction start) • We are on track for accomplishing this, but PED schedule is tight ! • Challenges: • Maintaining/building science case within political arena – Users! • Balancing ongoing operations with construction project – communication! Note - Quarterly meetings with Hall 12 GeV Steering Committee reps, UGBOD Chair, and 12 GeV Project Mgt reps have begun ; J. Roche is rep for Hall C