220 likes | 328 Views
Power Sector in Tanzania. Recent Developments, Current Crisis, Issues, Challenges and Solutions. AGENDA. Recent Developments Current Crisis Issues Challenges Solutions. Recent Developments. Power System Characteristics
E N D
Power Sector in Tanzania Recent Developments, Current Crisis, Issues, Challenges and Solutions
AGENDA • Recent Developments • Current Crisis • Issues • Challenges • Solutions
Recent Developments • Power System Characteristics • Installed generation capacity of 947 MW (Hydro 562 MW, Diesel 85 MW, IPPs 295 MW, Imports 5 MW), 550,000 consumers • 4 IPPs – IPTL, Songas, Kiwira Coal Mine, TANWAT selling power to TANESCO • Electricity imports from Uganda and Zambia, and exports power to Kenya • EWURA established – not yet fully operational • Several privately owned generation facilities mostly for standby
Current Crisis • Generation shortage load shedding (power rationing) in February and March, June to October/November • Severe cash shortage O&M costs financed through overdraft (now TShs 70 billion, expected to increase) • Under recovering about TSh 8.3 billion per month due to low electricity tariffs
Issues • Shortage of generation • High liquid fuel prices form about US$40/barrell in 2003 to over US$70/barrell now • High technical and commercial losses • Lack of investments since 1997 when TANESCO was specified • Low tariffs that under recover O&M costs • Poor quality of supply and service • Conflicting uses for the water and poor catchment management • Load shedding 1994, 1997, 2000, 2006
Issues • Delays in commissioning of Ubungo units 5 & 6 in 2005 • Outages of Songas’ generating sets and transformer in 2005 and 2006 • Sub-optimal operation of the hydro/thermal system (overuse of hydro system) • Unsuccessful procurement of emergency power plant in 2004 (IDA funding),
Challenges • Lower than average hydrology (drought) • High cost of thermal generation • Financing of future investments • Overloaded transmission and distribution • Unbalanced electricity tariffs – Zanzibar at TShs 26/kWh (US$0.0211/kWh) much lower than LRMC of US$0.04/kWh
Challenges • Costs about US$1.1 per kWh not served • TANESCO estimate load shedding to year end to be about 199 GWh • Cost to the economy estimated to be US$219 million • In addition, the government will loose VAT on electricity consumption amounting to about US$3 million
Solutions • Short Term • Procurement of leased gas based generation • Increase electricity tariffs by 25% • Convert IPTL to natural gas firing • Purchase of the IPTL power plant • Demand side management • Hydro/thermal generation optimization • Negotiate long term gas prices for new plant • Procurement of 100 MW gas based generation
Solutions 2) Short Term • Enforcement of water rights, catchment's management and protection, prohibit agro activities close to rivers, proper environmental management of river basins • Rehabilitation, reinforcement and expansion of the T&D systems, replace billing system and faulty meters
Actions with High Impact on TANESCO’s Financial Performance
Actions with High Impact on TANESCO’s Financial Performance
Solutions 3) Short Term – Studies and TA • Long Term Power Master Plan (2007-2032) • Demand Side Management • Capacity building • IPP Strategy and standardized bidding documents • Hydro/thermal generation optimization • Grid extension to Kigoma, and mines • Preparation of a new Sector Reform Strategy
Solutions 4) Short to Medium Terms • Demand side management: Replace incandescent lamps (ILs) with compact fluorescent lamps (CFLs) – less wattage on equivalent light output • Benefits to both the consumers (reduced energy consumption) and the utility (reduction of demand)
Comparisons CFLs and ILs on Equivalent Light Output • On equivalent light output, replacement of 23 @ 60 W ILs with 15 W CFLs would reduce the peak demand by about 1 kW • Consumers would save TShs 23 per day in electricity charges for every 60 W IL replaced (assuming usage of 5 hours/day) • Replacing just 2 ILs per consumer for the 550,000 consumers, would reduce the peak demand by 50 MW and the energy demand by 90 GWh annually (assuming usage of 5 hours/day)
Solutions • Medium to Long Term • TANESCO;s capital investments needs 2006 to 2010 TShs 1.3 trillion for: • New generation additions 345 MW • Transmission and distribution system rehabilitation and expansion • Increasing access to electricity in rural areas • Interconnections – EAC and SADC
Comparison of Tanzania’s Electricity Tariffs with selected African and OECD Countries US$ cents per kWh