ODOT Fix-It Program. Major Fix-It programs. Pavements. Bridge & Seismic. Culverts. Safety. Fix-It routes. Pavement Program components. Interstate Maintenance. Low volume roads. National Highway System. Maintenance & Operations. State h ighway pavement conditions
E N D
Major Fix-It programs Pavements Bridge & Seismic Culverts Safety
Pavement Program components Interstate Maintenance Low volume roads National Highway System Maintenance & Operations
State highway pavement conditions Percent fair or better
Gathering pavement data Windshield surveys
Gathering pavement data Contractor images and ratings Smoothness and rut depth Friction
Considerations in identifying needs Condition score Pavement age Data Maintenance history Highway importance Climate Potential fixes Cost Evaluation Impact on condition rating
Bridge Program components Major bridge maintenance Preservation Rehab/Replacement Seismic
Bridges in poor condition on Fix-It priority corridors Blue = bridges built prior to 1970 Red = bridges built between 1970 and 1999 Green = bridges built between 2000-2016
Project selection from other bridge data sources Preliminary needs list
Preliminarybridge needs list review Region staff review list and provide comment Desk scoping list Bridge program manager reviews list
Local Bridge Program Large Bridge Deck area of 30,000 square feet or greater Small Bridge On the Federal-Aid System Small Bridge Not on the Federal-Aid System
Culvert Program components Large culverts Major culvert maintenance Fish passage Priority route
Culvert conditions Blue = 33% culverts in critical/poor condition Red = 34% culverts in fair condition Green = 33% culverts in good condition
Invert condition rating Condition assessment Fair Good Critical Poor
ODOT Safety programs All Roads Transportation Safety Hot spot Hot spot Systemic Systemic
Crash data Data are compiled for all reported crashes on all roads.
Safety project selection • Evaluate applications. • Validate solution and cost. • Prioritize applications based on benefit cost. • Create 150-200% list of potential STIP projects. • Verify project details and support with local agencies.
Manage the condition of the system. • Collect and analyze data. • Considers program priorities and leadership directives. • Considers available funding. Fix-It projects: