Culvert Liners High Value Research. Sue Sillick Montana Department of Transportation July 2011. RESEARCH PROGRAMS. Purpose of Project. Install two types of culvert liners to restore function and structural integrity to corrugated steel pipe (CSP) Cure-in-Place (CIPP)

jaeger
Download Presentation

Culvert Liners High Value Research

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Culvert LinersHigh Value Research Sue Sillick Montana Department of Transportation July 2011 RESEARCH PROGRAMS

  2. Purpose of Project Install two types of culvert liners to restore function and structural integrity to corrugated steel pipe (CSP) Cure-in-Place (CIPP) High Density Polyethylene (HDPE) RESEARCH PROGRAMS

  3. Purpose of Project Why culvert liners vs. replacing the culverts? Improve worker and public safety during construction Minimize construction impact on the public and the environment Eliminate construction traffic delays and congestion Eliminate construction landfill waste Increase culvert performance and life Decrease maintenance costs RESEARCH PROGRAMS

  4. Culvert Condition Prior to Construction Culvert Outlet Culvert Inlet RESEARCH PROGRAMS

  5. Cure-in-Place Culvert Liner Installation Resin impregnated, three-layer polyester Cure-in-Place Pipe (CIPP) liner being inserted into existing culvert using compressed air RESEARCH PROGRAMS

  6. Cure-in-Place Culvert Liner Installation CIPP liner under cure using low-pressure steam RESEARCH PROGRAMS

  7. Cure-in-Place Culvert Liner Installation Completed CIPP liner inlet Completed CIPP liner outlet RESEARCH PROGRAMS

  8. Cure-in-Place Culvert Liner Installation Example of work zone during the CIPP installation RESEARCH PROGRAMS

  9. HDPE Culvert Liner Installation Seam welding the HDPE pipe for insertion into the existing culvert RESEARCH PROGRAMS

  10. HDPE Culvert Liner Installation Inserting the finished HDPE pipe into the culvert RESEARCH PROGRAMS

  11. HDPE Culvert Liner Installation HDPE pipe fully inserted and ready for grouting phase RESEARCH PROGRAMS

  12. HDPE Culvert Liner Installation Completed HDPE liner outlet with grouted bulkhead RESEARCH PROGRAMS

  13. HDPE Culvert Liner Installation Example of work zone in HDPE pipe installation RESEARCH PROGRAMS

  14. Condition at Three Years HDPE CIPP RESEARCH PROGRAMS

  15. Culvert Liner Evaluation Semi-Annual evaluations are being conducted for an initial 5-year period, including: Internal culvert deflection Lining integrity Leakage Flow Discoloration Other visual distress RESEARCH PROGRAMS

  16. Questions? Contact Sue Sillick ssillick@mt.gov 406-444-7693 Project website: http://www.mdt.mt.gov/research/projects/macpass_culvert.shtml RESEARCH PROGRAMS