1 / 14

Optimization Techniques in Engineering and Construction of a Bioethanol Plant

Optimization Techniques in Engineering and Construction of a Bioethanol Plant. ABENER North America St. Louis, MO Chris Hutson – Business Development Director. Engineering network – Spain, USA, Holland, Algeria, Morocco, Mexico, Brazil

Ava
Download Presentation

Optimization Techniques in Engineering and Construction of a Bioethanol Plant

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Optimization Techniques in Engineering and Construction of a Bioethanol Plant

  2. ABENER North America St. Louis, MO Chris Hutson – Business Development Director Engineering network – Spain, USA, Holland, Algeria, Morocco, Mexico, Brazil Focus – Biofuels, Solar Energy, Power Generation

  3. Bioethanol - Processes

  4. Bioethanol Experiences – Spanish Market

  5. Bioethanol Experiences – Spanish Market

  6. Bioethanol Experiences - USA Market

  7. Bioethanol Experiences - European Market

  8. Optimization Techniques – Engineering/Design Biofuels Process • Process provider • Air/Water Permits • Capacity/Design factors/Redundancy • Feedstocks • Batch/continuous • Coproducts • Receiving/Loadout (truck, rail, barge) • Minimize handling/movement • Future expansions • Plant layout • Plant elevation, slope, drainage • Foundation design • Seismic considerations • Platforms/access • Codes/standards Process design Logistics Civil / Structural

  9. Optimization Techniques – Engineering/Design Biofuels Process • Process requirements • Design factors • Equipment redundancy • Operation and maintenance considerations • Codes & Design Standards • Hazardous area classifications • Fire protection • Approved Equipment Suppliers • 3D CAD design/model • Moduralized pipe racks and equipment • Process requirements • Selected instrument vendors • Hazardous area classifications • Distributed control system (DCS) • Computer graphics and control features • Automation • Interlocks, Alarms, Safe operation • Reporting Mechanical / Piping Instrument & Control

  10. Optimization Techniques – Engineering/Design Biofuels Process • Utility supply/substation • Design factors • Equipment redundancy • Operation and maintenance considerations • Codes & Design Standards • Approved Equipment Suppliers • Hazardous area classifications • Packaged electrical buildings • Process water makeup • Natural gas • Waste water discharge requirements Electrical Utilities

  11. Optimization Techniques – Construction Biofuels Process • Roads, rail, barge • Plant roads constructed for required traffic (200 trucks/day – 25 trucks/hour) • Local codes and governing bodies • Foundations fermenters, silos,… • 51,000 cyd of concrete (Rotterdam Plant) Civil Works • Critical on site assembly activities • Modularization • Peak number of worker on site (400-600) • Different hazardous areas (different risks) • Welding: > 80,000 inches • Pipe Rack: 4,500 ft. (approx. 135,000 ft. of pipe) • Silos: up to 9,500 cyd/silo • 100 tanks (up to 2.1 MMG) Construction Works Mechanical • Cogeneration (up to 45 MW) • 170 km. cables • 4,500 instruments Electrical – I&C

  12. Conclusions I General Objectives • Maximize Bioethanol/Co-products Production • Minimize Period for Commercial Operation • Best cost-effective solution (bankable project) EPC - Driving Parameters • Technology supplier • Energy efficiency optimization (Design and Construction) • Minimization of self-consumption (Design and Construction) • Reduction of construction and assembly risks (Project Manag.) • Delivery time of critical equipment (Project Management) • Optimize plant efficiency during Start-Up (Expertise)

  13. Conclusions II EPC Contractor • Expertise in diversifying portfolio of projects: • Batch • Continuous • Second Generation • Strong and specialized design and engineering capabilities • Process engineering • Own capabilities • Cooperation/Alliances (technology supplier, manufacturers,…) • Involvement in relevant R&D activity • Multidisciplinary references (Bioethanol, Power, WTP, WWP, I&C,…) The successful EPC Contractor must help the developer and owner to achieve their Business Model

  14. Thanks for your attention! ABENER Campus Palmas Altas 41012 - Sevilla (Spain) Tel. +(34) 954 937 000 abener@abener.abengoa.com www.abener.com ABENER 14522 South Outer Forty Road Chesterfield, MO 63017 Tel. 314 275 1100 Fax 314 275 2408

More Related