230 likes | 635 Views
Black Sea Regional Transmission Planning Project. By Predrag Mik
E N D
1. Regional Transmission Network Development: Implications for Trade and Investment
3. Regional model – modeled systems Transmission networks of all power systems in the region
Russia Romania Georgia
Ukraine Bulgaria Armenia
Moldova Turkey
Equivalent of western and south-eastern UCTE grid (ENTSO-E)
4. Regional model – Existing Interconnectors
5. Regional model - characteristics High voltage network-transmission network
750kV,500kV,400kV,330kV,220kV,150kV,110kV network
Generator units at their nominal voltage level
Step-up transformers for main generation capacities
All new substations and lines that are expected to be operational till 2020 (according to the long term development plans)
Development of Regional model Guidelines
6. BSTP – Regimes modeled Load flow Model development
2010 Winter peak,
2010 Summer off-peak
2010 Summer peak
2015 Winter peak
2015 Summer peak
2015 Summer off-peak
2020 Winter peak
2020 Summer peak
2020 Summer off-peak
7. Studies – Regional model analyses Promoting regional cooperation in transmission planning among Black Sea region TSOs
Collect national inputs and the development plans that will be used for power transmission system analysis
Load flow analyses
loading of the network
feasibility of base case exchanges
voltage profile analyses
contingency analyses (n-1 security check)
Border capacity overview
“bottle neck” evaluation (congestions)
Regional transmission planning rules
Identify potential transmission investment projects
8. Studies – Dynamic model development Dynamic stability major concern in region
system stability is major limiting factor for system operation and high electricity exchange level - necessity to analyze dynamic system behavior
check the maximum exchanges scenarios for stability
Russian built excitation systems to be modeled (non standard models)
New units (confirmation and verification)
HVDC devices
Dynamic model characteristics
395GW production modeled (156GW in equivalents of UCTE and part of Russia, 239GW real power plants, of which 7.1GW in wind power) in 1183 generators
9. Studies – network capacities evaluation Evaluation of network transfer capabilities
ETSO methodology used
Identify the existing potential for electric power trade in the region
Verify values through dynamic analyses
Critical regimes (exchange)
Select outage to investigate
Monitor machines
10. Regional model-balances and exchanges All countries in the region have surplus of power
Very limited transfer capacities
11. Regional model-balances and exchanges
12. Studies – results Border capacities present
13. Studies – results Border capacities 2015
14. Studies – results Georgia-Turkey border
220 kV line Batumi-Hopa (300MVA)
400kV HVDC Akhalchike-Borcka (600MW)
Total capacity 900MVA
Static capacity 750MW
Dynamic capacity 750MW
15. Studies – results Georgia-Armenia border
220 kV line Gardabani-Alaverdi (270MVA)
2X400kV line Qsani-Hrazdan (1330MVA)
Total capacity 1600 MVA
Static capacity 1200MW
Dynamic capacity 750MW
Limiting factor short circuit on Sipan line in duration 0.55s (critical clearing time)
16. Studies – results Georgia-Turkey border
220 kV line Batumi-Hopa (300MVA)
400kV HVDC Akhalchike-Borcka (600MW)
Total capacity 900MVA
Static capacity 1200MW
Dynamic capacity 750MW
17. Studies – results Composite capacities
18. Results, Findings & Conclusions 2015 & 2020 Model Status
National and Regional Load Flow and Dynamic Models have been built, tested and distributed.
2015 models are realistic and have been used to produce these reported results.
2020 models need additional work:
Adjust for world economic conditions
Adjust to include projected renewable energy supplies
19. Results, Findings & Conclusions Projected Synchronous Operations in the Black Sea Region
Presently 3 synchronous zones: ENTSO-E, IPS/UPS and Turkey.
2015 Possibilities are:
2 zones: ENTSO-E (including Turkey) and IPS/UPS
3 zones: ENTSO-E (including Turkey), Ukraine and Moldova in ENTSO-E testing mode and IPS/UPS.
2 zones: ENTSO-E (that includes Turkey, Ukraine and Moldova) and IPS/UPS.
20. Results, Findings & Conclusions Regional Power Balance
2015 Winter Peak Export Potential = 4,015MW
Russia, Ukraine, Romania, Bulgaria, Armenia have excess capacity in winter
Georgia and Moldova are balanced in winter
Turkey has a winter peak deficit
2015 Summer Peak Export Potential = 4,400MW
Russia, Ukraine, Romania, Bulgaria, Armenia, Georgia have excess capacity in summer
Moldova is balanced in summer
Turkey has a summer peak deficit
21. Results, Findings and Conclusions National Border Capacities
Presently limited between:
Russia and Georgia
Georgia and Armenia
Georgia and Turkey
Improvements by 2015
HVDC Connection between Georgia & Turkey
400 kV connection between Armenia & Georgia
New connection between Turkey and Greece
22. Results, Findings & Conclusions Regional Composite Transfer Capacities
Assuming Synchronous Operations in the Region
Capacity to Drive Large Quantities of Power
Along Market Realistic Routes
Large Indicative Values of Transfer Capacity in 2015 but all areas are NOT Synchronous
To realize potential
Synchronous operation
Strategic Locations for HVDC or
Island Mode solutions
23. Results, Findings & Conclusions Importance of using Dynamic Analysis in the Region.
Dynamic stability further limits interchange capacities calculated using the static security evaluation method
Georgia/Armenia
Georgia/Turkey
24. Potential Next Steps Updates of 2015 and 2020 Models
More Realistic Models
Integrating Renewables
Training on Modeling Renewables with PSS/E
Study Tours
TSO Partnerships
Additional Synchronous Scenarios for 2015
3 Synchronous Zones: 1)ENTSO-E (including Turkey); 2) Ukraine & Moldova in ENTSO-E Test Mode; and 3) IPS/UPS
2 Synchronous Zones: 1) ENTSO-E (including Turkey); 2) Ukraine and Moldova in IPS/UPS
25. Potential Next Steps Analysis of network capacity based on most likely market based trade scenarios
To utilize Potential of Black Sea Network:
Additional Synchronous Scenarios for 2020
2 Synchronous Zones: 1) ENTSO-E including Turkey, Ukraine & Moldova; and 2) IPS/UPS
2 Synchronous Zones: 1) ENTSO-E including Turkey; and 2) IPS/UPS (including Ukraine & Moldova
Strategic Locations for HVDC or
Island Mode solutions
26. Thank You!